<br />KVEC RV Park <br />August 13, 2026 <br />Page 5 of 9 <br /> <br />25 N Wenatchee Ave, Suite 238  Wenatchee, WA 98801  Office 509.886.3265  Fax 360.352.1509  scjalliance.com <br />Phase 20 Underground Electrical Project <br />Task 1 Underground Electrical Construction Services <br />1) Project Management <br />a) Weekly project updates and correspondence on progress. <br />b) Resource loading project and scheduling <br />2) Pre-Construction <br />a) Inspector Plans and Specification review. <br />b) Field record and project documentation preparation. <br />(a) Photos/video of the existing site. <br />c) Pre-construction meeting preparation. <br />d) Pre-construction meeting (1 in person). <br />3) Office Engineering <br />a) Documentation of prevailing wages <br />b) Review sub-contractor requests. <br />c) Contractor schedule submittal review. <br />d) Develop working day statements. Estimate 2 statements. <br />e) Review of traffic control plans. <br />f) Material submittal reviews. Estimate materials <br />g) Monthly Pay Estimates <br />(a) Pay Estimate setup for the project. <br />(b) Review of field pay notes <br />(c) Pay Estimate review (office materials back check). <br />(d) Revisions based on Contractor responses. <br />(e) Requests to the contractor for additional information for payment. <br />(f) Estimate 3 pay estimates for the project duration. <br />h) Request for Information (RFI’s) <br />(a) Setup tracking <br />(b) Review an estimate of 3 based on project size and complexity. <br />(c) Response to RFI’s. <br />i) Change Order(s) <br />(a) Setup tracking <br />(b) Review or develop and RFP. <br />(c) Estimate 1 based on the size and complexity of the project. <br />4) Construction Observation <br />a) Project field observation <br />(a) Estimate 5 onsite field observation days. <br />(b) Observing contractor’s compliance with contract documents