Task 2—Complete 30% Design engineering for the lift station(s) (40% of Project Effort, <br /> complete by 2/15/2026) <br /> 1. Complete 30% PSE for the South Interchange Lift Station <br /> a. Complete geotechnical investigation for the selected lift station site(s). <br /> b. Complete Cultural Resource Assessment for the selected lift station site(s). <br /> c. Complete detailed topographic survey for the selected lift station site(s) <br /> and force main route(s). <br /> d. Complete 30% engineering plan set. <br /> Task 3 —Complete 50% Design engineering for the lift station(s) (60% of Project Effort, <br /> complete by 6/30/2026) <br /> 1. Complete 50%PSE for the South Interchange Lift Station <br /> a. Complete 50% engineering plan set <br /> 2. Initiate permitting for the lift stations and associated force mains. <br /> 3. Initiation ROW acquisition for the lift stations and associated force mains. <br /> Task 4—Complete permitting for the lift station(s) (80% of Project Effort, complete by <br /> 9/30/2026) <br /> 1. Complete permitting for the lift stations and associated force mains. <br /> 2. Complete ROW acquisition for the lift stations and associated force mains. <br /> Task 5 —Complete 70% Design engineering for the lift station(s) (100% of Project Effort, <br /> complete by 12/31/2026) <br /> 1. Complete 70% PSE for the South Interchange Lift Station <br /> a. Complete 70% engineering plan set <br /> Page 2 of 2 <br />