S 5.4.2 Upon such assignment, if the Work has been suspended for more than 30 days, the Subcontractor's
<br />compensation shall be equitably adjusted for increases in cost resulting from the suspension.
<br />S 5.4.3 Upon such assignment to the Owner under this Section 5.4, the Owner may further assign the subcontract to
<br />a successor contractor or other entity. Ifthe Owner assigns the subcontract to a successor contractor or other entity,
<br />the Owner shall nevertheless remain legally responsible for all of the successor contractor's obligations under the
<br />subcontract.
<br />ARTICLE 6 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS
<br />s 6.1 OWNER'S RtcHT TO PERFORM CONSTRUCTTON AND TO AWARD SEPARATE CoNTRACTS
<br />S 6.1.1 The Owner reseryes the right to perform construction or operations related to the Project with the Owner's
<br />own forces, and to award separate contracts in connection with other portions of the Project or other construction or
<br />operations on the site under Conditions of the Contract identical or substantially similar to these including those
<br />p-ortions related to insurance and waiver of subrogation. If the Contractor claims that delay or additional cost is
<br />involved because of such action by the Owner, the Contractor shall make such Claim as provided in Article l5'
<br />$ 6.1 .2 When separate contracts are awarded for different portions of the Project or other construction or operations
<br />on the site, the term "Contractor" in the Contract Documents in each case shall mean the Contractor who executes
<br />each separate Owner-Contractor Agreement.
<br />$ 6.1.3 The Owner shall provide for coordination of the activities of the Owner's own forces and of each separate
<br />conhactor with the Work of the Contractor, who shall cooperate with them. The Contractor shall participate with
<br />other separate contractors and the Owner in reviewing their construction schedules. The Contractor shall make any
<br />revisioni to the construction schedule deemed necessary after a joint review and mutual agreement. The construction
<br />schedules shall then constitute the schedules to be used by the Contractor, separate contractors and the Owner until
<br />subsequently revised.
<br />$ 6.1.4 Unless otherwise provided in the Contract Documents, when the Owner performs construction or operations
<br />related to the Project with the Owner's own forces, the Owner shall be deemed to be subject to the same obligations
<br />and to have the same rights that apply to the Contractor under the Conditions of the Contract, including, without
<br />excluding others, those stated in Article 3, this Article 6 and Articles 10, I I and 12.
<br />$ 6.2 MUTUAL RESPONSIBILIW
<br />$ O.Z.t The Contractor shall afford the Owner and separate contractors reasonable opportunity for introduction and
<br />storage of their materials and equipment and performance of their activities, and shall connect and coordinate the
<br />Contractor's construction and operations with theirs as required by the Contract Documents.
<br />S 6.2.2 If part of the Contractor's Work depends for proper execution or results upon construction or operations by
<br />ihe O-n.i or a separate contractor, the Contractor shall, prior to proceeding with that portion of the Work, promptly
<br />report to the Architect apparent discrepancies or defects in such other construction that would render it unsuitable
<br />foi such proper execution and results. Failure of the Contractor so to report shall constitute an acknowledgment that
<br />the Owner'Jor separate contractor's completed or partially completed construction is fit and proper to receive the
<br />Contractor's Work, except as to defects not then reasonably discoverable.
<br />$ 6.2.3 The Contractor shall reimburse the Owner for costs the Owner incurs that are payable to a separate
<br />conhactor because of the Contractor's delays, improperly timed activities or defective construction. The Owner shall
<br />be responsible to the Contractor for costs the Contractor incurs because of a separate contractor's delays, improperly
<br />timed activities, damage to the Work or defective construction.
<br />S 6.2.4 The Conkactor shall promptly remedy damage the Contractor wrongfully causes to completed or partially
<br />completed construction or to property of the Owner or separate contractors as provided in Section 10.2.5.
<br />$ 6.2.5 The Owner and each separate contractor shall have the same responsibilities for cutting and patching as are
<br />described for the Contractor in Section 3.14.
<br />AIA Document A2O1 - 2OO'1. Copyright @ 1911, 1915, 7gI8t L925, 1931, L951, r958' 1951, 1963, 1966, 1'910, 79'16, I98
<br />rights reserved. ,'The American Institute of Architects," "American Institute of Architects," {AIA," the AIA Logo,
<br />Documents,, are trademarks of The American Institute of Architects. This dlaft was produced at 09:51:3? PT on 05,/1
<br />No,410424304? which expires on 06/:10/2024, is not fo! resale, is licensed for one-tj"me use only, and nay only be
<br />the AIA Contract Documentso Terms of Service, To report copyright violations, e-mail docinfocaiacontracls.com.
<br />Uger Notes:
<br />?, 1997 and 2007. All
<br />and "AIA Contract
<br />3/2024 under Order
<br />used in accordance with
<br />(1164916017)
<br />20
|