Laserfiche WebLink
Snohomish County <br /> Snohomish County Code 30.70.110 Processing timelines. <br /> (1) Notice of final decision on a project permit application shall issue within 120 days from when the <br /> permit application is determined to be complete,unless otherwise provided by this section or state law. <br /> (2) In determining the number of days that have elapsed after an application is complete,the following <br /> periods shall be excluded: <br /> (a) Any period during which the county asks the applicant to correct plans,perform required <br /> studies,or provide additional required information.The period shall be calculated from the date <br /> the county mails notification to the applicant of the need for additional information until the date <br /> the county determines whether the additional information satisfies the request for information, <br /> or 14 days after the applicant supplies the information to the county,whichever is earlier. If the <br /> information submitted by the applicant under this subsection is insufficient,the county shall mail <br /> notice to the applicant of the deficiencies and the provisions of this subsection shall apply as if a new <br /> request for information had been made; <br /> (b) Any period during which an environmental impact statement is being prepared; <br /> (c) A period,not to exceed 30 calendar days,during which a code interpretation is processing in <br /> conjunction with an underlying permit application pursuant to chapter 30.83 SCC; <br /> (d) The period specified for administrative appeals of project permits; <br /> (e) Any period during which processing of an application is suspended pursuant to SCC 30.70.045(1) <br /> (b); <br /> (f) Any period during which an agreement is negotiated or design review is conducted for an urban <br /> center pursuant to SCC 30.34A.180(1)or 30.34A.180(2);and <br /> (g) Any period of time mutually agreed upon by the applicant and the county. <br /> (3) The time periods established by this section shall not apply to a project permit application: <br /> (a) That requires an amendment to the comprehensive plan or a development regulation in order to <br /> obtain approval; <br /> (b) That is substantially revised by the applicant,in which case a new 120-day time period shall start <br /> from the date at which the revised project application is determined to be complete; <br /> (c) That requires approval of a development agreement by the county council; <br /> (d) When the applicant consents to an extension;or <br /> (e) During any period necessary for reconsideration of a hearing examiner's decision.. <br /> (4) Subject to all other requirements of this section,notice of final decision on an application for a <br /> boundary line adjustment shall be issued within 45 days after the application is determined complete. <br /> Growth Management Act Appendix D 1 67 <br />