Project Costs
<br />To prepare an estimate of probable construction costs for the TTC master plan, trails were divided into
<br />geographic zones and segments. These trail segments can be built over time and will help organizers
<br />phase in the full project implementation. The cost estimate is based on public bid and construct costs
<br />and is provided in 2018 US Dollars. The trail lengths are based on the trail layouts shown on the master
<br />plan graphic. See the Appendix for more detailed planning -level cost estimate breakdown and list of
<br />assumptions.
<br />Zone A Summary
<br />Mobilization
<br />Trails
<br />Trail Signage
<br />Trailhead 1 With Parking (Zone A - Ronald)
<br />$37,922.40
<br />$260,509.00
<br />$7,600.00
<br />$107,115.00
<br />Zone A Trailhead Landscape
<br />$0.00
<br />Site Amenities
<br />$4,000.00
<br />Subtotal
<br />$417,146.40
<br />Total (including tax, O&P, contingency)
<br />$608,866.89
<br />Total Including design & permitting (20%)
<br />$723,965.92
<br />Zone B Summary
<br />Mobilization
<br />$104,763.18
<br />Trails
<br />$734,316.75
<br />Trail Signage
<br />$24,400.00
<br />Trailhead 2 With Parking (Zone B - Roslyn)
<br />$16,000.00
<br />Trailhead 3 With Parking (Zone B - Roslyn)
<br />$171,635.00
<br />Zone B Trailhead Landscape
<br />$85,280.00
<br />Site Amenities
<br />$16,000.00
<br />Subtotal
<br />$1,152,394.93
<br />Total (including tax, O&P, contingency)
<br />$1,682,035.63
<br />Total including design & permitting (20%)
<br />$2,000,004.44
<br />Zone C Summary
<br />Mobilization
<br />$109,622.78
<br />Trails
<br />$558,262.75
<br />Trail Signage
<br />$171,635.00
<br />Trailhead 4 With Parking (Zone C - Cle-Elum High School Area)
<br />$171,635.00
<br />Trailhead 5 With Parking (Zone C - Cle Elum)
<br />$171,635.00
<br />Trailhead 6 With Parking (Zone C - Cle Elum)
<br />$16,000.00
<br />Trailhead 7 With Parking (Zone C - Cle Elum)
<br />$107,115.00
<br />Zone C Trailhead Landscape
<br />$53,300.00
<br />Site Amenities
<br />$4,000.00
<br />Subtotal
<br />$1,363,205.53
<br />Total (Including Tax, O&P, Contingency)
<br />$1,760,059.43
<br />Total Including Design & Permitting (20%)
<br />$2,092,777.70
<br />Total TTC Project Summary
<br />Total (including tax, overhead & profit, and contingency) $4,050,961.94
<br />Total including design & permitting (20%) $4,816,748.06
<br />Towns to Teanoway Corridor Master Plan p 124 of 26
<br />Prepared for: Economic Development Group of Kittitas Co. & Kittitas Co. Parks and Recreation District No. 1
<br />Prepared by: J.A. Brennan Associates, Landscape Architects & Planners