Laserfiche WebLink
6.STAGING PLAN <br />Following is a staging plan describing the sequence of construction for all the elements <br />on the plans: <br />Phase 1 <br />•Estimate of Phase 1 Construction Start Date..................................2-4 Months from FDP Approval <br />•Ph a se 1 Co n st ru ct io n ..............................................................................................................4 m o.-2 yr s.fromSt a rtD ate <br />o Pre-Construction Meeting <br />o Establish Clearing Limits and Install Temporary Sediment <br />and Erosion Control Measures <br />o Clearing,Grubbing,Grading <br />o Water Reservoir Construction <br />o Membrane Bio-Reactor Construction (Phased Installation) <br />o Utility Construction <br />o Roadway/Parking Construction <br />o Signage,Lighting,Landscaping and Vineyard Installation <br />•Lot and Building Construction..........................................................................................1-2 Years from Start Date <br />•Final Stabilization and Finish Date...............................................................................2-3 Years from Start Date <br />Phase 2 <br />·Phase 2 drawings submitted to county.................................................4-6 Months from FDP Approval <br />·Estimate of Phase 2 Construction Start Date....................................................6mo.-1yr from PH 1 Start <br />•Phase 2 Construction................................................................................................4mo.-2yrs.from PH 2 Start Date <br />o Pre-Construction Meeting <br />o Establish Clearing Limits and Install Temporary <br />Sediment and Erosion Control Measures <br />o Clearing, Grubbing,Grading <br />o Membrane Bio-Reactor Expansion (Phased Installation) <br />o Utility Extension <br />o Driveway/Parking Construction <br />o Signage,Lighting,Landscaping and Vineyards <br />•Hotel and Winery Construction.......................................................................6mo.-2yrs.from PH 2 Start Date <br />•Final Stabilization and Finish Date................................................................1-2 Years from PH 2 Start Date <br />Please note that subdivision lot sales may precede other elements of the development <br />upon final plat approval (KCC 17.36.040(1)). <br />7.SEPA MDNS CONDITIONS <br />Kittitas County issued conditions of approval with the SEPA Mitigated Determination of <br />Nonsignificance that were attached to the approved ordinance adopting the Preliminary <br />Plat and Planned Unit Development (Ord.2006-060). Table 7.1 is provided to verify that the <br />alterations included with this FDP do not increase any environmental impacts taken into <br />consideration by the original SEPA threshold determination. <br />3\Page <br />Index #27