Laserfiche WebLink
Vantage to Pomona Heights Chapter 2 <br />230 kV Transmission Line Project FEIS Proposed Action and Alternatives <br /> PAGE 2-41 <br />lubricating the passage of the conduit pipe. Bentonite is non-toxic and commonly used in farming <br />practices. The drilling fluid is sent into a machine called a “reclaimer” which removes the drill cuttings <br />and maintains the proper viscosity of the fluid. Drilling fluids are designed to match the soil and cutter. <br />They are monitored throughout the process to ensure that the bore hole stays open, pumps remain <br />operational, and drilling fluid circulation throughout the borehole is maintained. Drilling muds are <br />“thixotropic” and thus thicken when left undisturbed after bore removal. However, unless cementitious <br />materials are added, the thickened mud is approximately as stiff as very soft clay. <br />There is a potential for drilling fluid release or “frac-out” during installation, which can occur when <br />pressure in the drill hole is not maintained and a loss of circulation of drilling fluid occurs. Frac-out is <br />typically caused by pressurization of the drill hole beyond the containment capability of the overburden <br />soil material, which allows the drilling fluid to flow to the ground surface. Releases can be caused by <br />fractures in bedrock or other voids in the geologic strata that allow the fluid to surface even if down hole <br />pressures are low. Providing adequate depth of cover for the installation can substantially reduce the <br />potential for inadvertent releases or frac-out. <br />2.2.5.2 Typical Underground Construction Activities <br />Duct Bank Requirements for Off-Road Construction <br />For off-road construction or construction not occurring within an existing roadway, installation of an <br />underground cable would require a dedicated area for construction consisting of a permanent access road <br />for future maintenance and repair activities and an additional temporary access road during the initial <br />construction for equipment and temporary storage of materials. <br />The entire length of the ROW would be cleared of all vegetation to accommodate installation of the <br />underground cable. The total construction surface impact area for underground cable construction and <br />installation would be approximately 55 to 60 feet or greater in width along the entire underground route to <br />accommodate trenching machines or excavators, truck mounted rock drills, dump trucks to haul out <br />excavated material unsuitable for backfill and to haul in backfill material. <br />A permanent access road of approximately 14 feet in width would be required to perform operation and <br />maintenance (see Section 2.2.3.2). A permanent cleared surface area would be required for the width of <br />the cable structure duct bank: 5 to 10 feet wide plus the permanent 14 foot access road for a total <br />permanent cleared area of approximately 24 feet wide (Figure 2-10). Disturbance assumptions along the <br />proposed centerlines for access roads are considered identical for the Overhead Design Option and <br />Underground Design Option detailed in this FEIS. <br />Splice Vault Requirements <br />The outside dimensions of splice vaults for 230 kV underground cables are approximately 9 feet wide by <br />10 feet tall and up to 28 feet long. The installation of each splice vault therefore typically requires an <br />excavation area approximately 10 feet wide, 11 feet deep, and 30 feet long. The actual burial depth of <br />each vault would vary, based on the cable manufacturer’s splice and cable racking requirements, site- <br />specific topographic conditions, and on the depth of the adjacent cable sections that must interconnect <br />within the vault. <br />Splice vaults would require a permanent cleared area for future access for maintenance and transmission <br />cable repairs, and an additional temporary cleared area for construction activities. Within the easements <br />for the splice vaults, certain uses such as the development of structures and growth of shrubs and trees <br />would be prohibited to avoid duct bank damage and impacts to the operation of the cables.