Laserfiche WebLink
Vantage to Pomona Heights Chapter 2 <br />230 kV Transmission Line Project FEIS Proposed Action and Alternatives <br /> PAGE 2-31 <br />Table 2-4 Overhead Transmission Line Construction Estimated Personnel and Equipment <br />ACTIVITY PEOPLE QUANTITY OF EQUIPMENT <br />Survey 3 1 pickup truck <br />Road Construction 3 to 4 <br />2 bulldozers (D-8 Cat), 1 excavator <br />1 motor grader <br />1 vibratory roller <br />2 dump trucks <br />2 equipment and materials trailers <br />1 pickup truck <br />1 water truck (for construction and maintenance) <br />Direct embed pole holes and <br />Footing Installation 6 <br />1 hole digger <br />Concrete trucks as required <br />1 water truck <br />2 pickup trucks <br />1 line truck <br />Material Haul 4 <br />1 tractor/trailer <br />2 yard and field cranes or line trucks <br />1 fork lift <br />Structure Assembly <br />Per crew <br />2 crews required <br />4 1 pickup truck <br />1 truck (2 ton) <br />Structure Erection <br />Per crew <br />2 crews required <br />4 <br />1 truck (2 ton) <br />1 pickup truck <br />1 bucket truck <br />1 crane <br />1 line truck <br />Wire Installation 8 <br />1 wire reel trailer <br />1 diesel tractor <br />1 crane <br />1 line truck <br />3 pickup trucks <br />2 bucket trucks <br />2 3-drum pullers <br />1 single drum puller (large) <br />1 double bull-wheel tensioner (heavy) <br />1 static wire reel trailer OPGW <br />ROW Restoration and Cleanup 4 <br />1 truck <br />1 motor grader <br />1 seeding and planting equipment <br />1 pickup truck <br />1 water truck <br />Note: Maximum total personnel for all tasks is 45 persons (actual personnel at any one time would be less). <br />2.2.4 Overhead Transmission Line Design Operation and Maintenance <br />The design, construction, operation, and maintenance of the proposed Project would meet or exceed the <br />requirements of the NESC, which governs the design and operation of high-voltage utility systems, U.S. <br />Department of Labor, Occupational Safety and Health Administration (OSHA) standards and Pacific <br />Power’s requirements for safety and protection of landowners and their property. <br />The proposed transmission line would be protected with power circuit breakers and line relay protection <br />equipment. If a conductor fails, power would typically be automatically removed from the line in less <br />than 0.5 second. Lightning protection would be provided through overhead ground wires.