Vantage to Pomona Heights Chapter 4
<br />230 kV Transmission Line Project FEIS Environmental Consequences
<br /> PAGE 4-146
<br />• Route Segment 2a: MP 0.0-1.0
<br />• Route Segment 2b: MP 0.0-2.2, 2.4-2.5, 4.9-5.0, 5.9-6.1, 6.5-6.8, 7.0-7.6, 11.1-11.7, and
<br />15.0-16.4
<br />• Route Segment 2c: MP 0.0-0.1, 0.3-2.9, 3.3-3.7, 5.2-6.1, 6.3-7.2, 7.5-7.9, 8.0-9.5, 10.2-10.4,
<br />11.1-12.9, 13.2-14.0, 14.4-17.1, and 17.7-18.2
<br />• Route Segment 2d: MP 0.0-0.3, 0.6-1.0, 1.7-2.0, 2.3-5.1, 5.6-6.0, and 6.4-7.0
<br />• Route Segment 3b: MP 3.0-3.7, 5.2-8.4, 10.6-10.8, 15.7-15.8, and 18.1-19.6
<br />• Route Segment 3c: MP 0.0-2.4, 2.9-3.4, 3.8-3.9, 4.8-10.4, 10.6-11.6, 11.9-12.5, 12.7-13.0,
<br />13.8-15.1, 15.4-15.5, 16.7-16.9, 17.4-17.5, 18.0-18.3, 18.5-18.7, 20.5-21.1, 21.7-22.5, and
<br />22.8-24.1
<br />• Route Segment MR-1: MP 1.5-1.7, 3.4-3.7, 4.7-4.8, 5.7-7.8, and 8.0-11.8
<br />• Route Segment NNR-2: MP 0.1-0.4, 0.7-1.7, 2.4-2.5, and 4.3-4.9
<br />• Route Segment NNR-3: MP 0.4-0.5, 4.1-4.2, 4.7-4.9, 5.2-5.4, and 6.1-6.4
<br />• Route Segment NNR-4o/4u: MP 1.1-2.0 and 4.3-4.5
<br />• Route Segment NNR-5: MP 0.2-1.0
<br />• Route Segment NNR-6o/6u: MP 0.4-0.5, 1.9-2.0, and 5.9-6.0
<br />• Route Segment NNR-7: MP 0.9-1.1, 1.3-1.4, 1.8-2.2, 2.8-2.9, 4.0-4.1, 6.5-7.2, and 7.8-7.8
<br />4.4.6 Impact Summary by Alternative
<br />4.4.6.1 No Action Alternative
<br />Under the No Action Alternative, the proposed Project would not be constructed or operated. No Project-
<br />related impacts to land use would occur.
<br />4.4.6.2 Action Alternatives
<br />Table 4.4-4 presents a summary of the long-term impacts and residual impact levels for Project Action
<br />Alternatives.
<br />Alternatives E, F, G, and H would have the greatest impacts on residential land use. Alternative H would
<br />have the greatest impacts on irrigated agriculture. The NNR Alternative - MR Subroute would have the
<br />highest impacts on JBLM YTC land uses. The most disturbance on state grazing or agricultural leased
<br />land would occur for the NNR Alternative - MR Subroute. Alternatives A and F would have the greatest
<br />impacts on BLM grazing leases. Overall, the greatest distance of high impacts on land use would occur
<br />for Alternative H.