Laserfiche WebLink
Vantage to Pomona Heights Chapter 4 <br />230 kV Transmission Line Project FEIS Environmental Consequences <br /> PAGE 4-2 <br />The amount of ground that could be disturbed as a result of Project activities was estimated based on the <br />typical design characteristics of this 230 kilovolt (kV) Project (Section 2.2.2). Short-term, long-term, and <br />access road disturbance was estimated and the disturbance model calculations and assumptions are <br />presented in Chapter 2, Section 2.2.3.2. Short-term disturbance included structure work areas for the <br />staging and installation of the tangent H-frame, single pole structures, and angle/dead end structures as <br />well as the conductor pulling and tensioning sites. Long-term disturbance included H-frame, single pole, <br />angle/dead end, and lattice structure base areas as well as work pad areas in slopes over eight percent for <br />equipment stability for structure installation. <br />The amount of ground that could be disturbed as a result of Project activities for the New Northern Route <br />Alternative - Underground Design Option is based on industry standards and methods used on other <br />transmission line projects. The description of the construction components, technologies, methods, and <br />disturbance assumptions are based on other projects implemented by utilities that have installed 230 kV <br />underground facilities elsewhere in the United States and reflect the assumptions detailed in Section 2.2.5. <br />These assumptions include contraction of the continuous concrete duct bank, splice vaults every 1,500 <br />feet, and overhead-to-underground transition stations. Access road construction was assumed to be the <br />same for the Overhead Design Option and the Underground Design Option, with a continuous, permanent <br />24-foot cleared area and permanent 30-foot ROW. <br />Overhead and Underground Design Option transmission line access for construction would be via a <br />combination of new access roads, overland access, improvement to existing roads and use of existing <br />terrain or roads as is. Where the proposed transmission line would parallel existing transmission lines or <br />other linear utilities, the existing access roads along the existing utilities would be used wherever possible <br />to minimize the amount of new access road construction. In some areas, only temporary roads would be <br />needed. Long-term access roads would be constructed where needed for construction and long-term <br />maintenance. Overland access would occur in areas where no grading would be needed and would be <br />used to the greatest extent possible. Overland travel would consist of “drive and crush” and/or “clear and <br />cut” travel. Drive and crush is vehicular travel to access a site without significantly modifying the <br />landscape (i.e., vegetation is crushed, but not cropped and soil is compacted, but no surface soil is <br />removed). Eight levels of access (Levels 0 through 7) were developed and numerically arranged based on <br />the anticipated ground disturbance expected with Level 0 having the lowest level of ground disturbance <br />and Level 7 having the most disturbance (see Table 2-3). <br />The short-term, long-term, and access road disturbance calculations by route segment and end-to- end <br />Action Alternatives are presented in Section 2.6 and Tables 2-7 through 2-16. <br />4.1.1.2 Impact Assessment <br />Based on the estimated ground disturbance associated with the Project (Chapter 2) and the resource <br />inventory information reflecting the existing environment, each resource specialist determined the types, <br />level, and amount of impacts that could occur on the resource. Computer-assisted models were developed <br />to support this determination, which allowed the method used for each resource to be tailored to specific <br />requirements and assumptions for analysis of each resource. Qualitative and quantitative variables of <br />resource sensitivity, resource quantity, and estimated ground disturbance were considered in predicting <br />the magnitude of impacts. Four levels were established and defined for each resource: high, moderate, <br />low, and no identifiable impact. A high impact could cause substantial change or stress to an <br />environmental resource or use and would generally be considered a significant impact and could be <br />reduced through mitigation; a moderate impact could potentially cause some change or stress to an <br />environmental resource or use ranging between a significant and insignificant impact and could be <br />reduced through mitigation; a low impact could be a detectable but slight change or stress and would <br />generally be considered an insignificant impact; and a no identifiable impact would be considered where <br />there is no measurable impact to the resource. Mitigation measures applied to the Project may reduce