PROJECT NARRATIVE <br />1. Project Description: Describe the scope of work. Indicate the major work involved, including a brief <br />comparison of existing and proposed conditions. <br />The proposed scope of work includes replacing or moving structures in Runje Field including bleachers <br />multi-game court, and climbing poles ; locating bike racks and wayfinding signs at major intersections in the <br />downtown. <br />2. Explain the specific Infrastructure issues the project addresses and how they are linked to economic <br />development improvements. <br />Visitors experience difficulty while navigating the downtown area which could be resolved by installing <br />wayfinding signs for restrooms, parking, parks, trailhead, and the cemetery. <br />We have seen a significant increase in bicycle traffic downtown, but without the ability to lock a bike up <br />safely, we find that most visitors get their business done quickly and move on. With the addition of bike <br />racks in the commercial zone, we hope to extend their visits and encourage them to patronize more <br />businesses. <br />Through feedback from citizens and event organizers, we have identified several small projects in Runje <br />Field that would improve the functionality and safety of the space, which is a cornerstone to our downtown <br />core. These projects include bleachers, replacement of climbing poles, relocation of multi-game court, and <br />increased power service. <br />3. Preliminary Engineering Phase: <br />Estimated Start Date: A~p~fl .... ·1 ~1..!.. • .!:2~O .o..16",--_____ Estimated End Date:-:..A.:.,:u:eg"",u,!::s.::..t =.20><..1~6~ _____ _ <br />Please explain phase status (work already completed, in progress, awaiting funding, etc., and factors that <br />may slow phase progress). <br />Awaiting Funding: multi-game court relocation , way-finding signs, bike racks, power to park . <br />The wayfinding signs and bike racks can be designed, purchased, and installed by staff. The power and <br />court work will need to be completed by a contractor, and therefore may be delayed in the process of <br />contracting. <br />4. Right of Way Phase: None Is It Required? Yes ___ No _X __ <br />Estimated Start Date: _______ _ Estimated End Date: ________ _ <br />Please explain phase status (work already completed, in progress, awaiting funding, etc., and factors that <br />may slow phase progress). <br />No Right of Way permit is required for these projects. <br />II