Laserfiche WebLink
EXHIBIT "A" <br />SCOPE OF WORK <br />In addition to providing all material and labor, the Contractor shall perform the following: <br />Scope of Work <br />Task 1: Data Gathering and Project Management <br />Two weeks prior to the project kick-off meeting, CH2M will transmit a data request list to the County to <br />obtain readily available existing transfer station and County program information including historic <br />tonnages, number and type of customers (MSW, green waste, recycling, moderate risk, other), <br />operating contracts, program revenue, and cost information. <br />CH2M will routinely communicate with County staff via phone and e-mail to provide project updates, <br />review project scope and budgets, and to discuss and resolve project issues and concerns. Monthly <br />invoices will be prepared and submitted to the County identifying task budget, amount spent this <br />period, and remaining budget. We will prepare monthly summary reports with each invoice identifying <br />work performed for the period, projected items to be completed, issues resolved, deliverable items, and <br />provide updates to the project schedule. <br />This task will be primarily conducted by Tom Parker with some assistance from lyndsey lopez and <br />administrative staff. <br />Task 2: Kick-off Meeting and Project Workshop <br />CH2M will conduct a site tour, kick-off meeting, and project workshop as part of this task. These three <br />activities will occur during one 8-hour day. <br />Prior to the kick-off meeting, CH2M will tour the existing transfer station facility, moderate risk facility, <br />and administration office to observe facility operations including scalehouse operations, customer <br />unloading, material loading and transfer operations, green waste processing and composting, and <br />moderate risk facility customer processing. <br />CH2M will conduct a project kick-off meeting (up to 1 hour) with County staff to discuss project scope, <br />schedule, budget, and to identify critical project milestone dates. <br />After the kick-off meeting, we will conduct a workshop (up to 6 hours) with the County to discuss the <br />following: <br />• Design Parameters (design life, tonnage (by material type), traffic, operating days/hours, <br />contracting changes/requirements) <br />• Discuss Facility Design Features <br />o Transfer Station <br />• Tipping Floor Options (size, clearance, configuration, push walls) <br />Professional Services Agreement <br />Page 15