CIP 11-CRYSTAL CREEK RESTORATION AND WETLAND CREATION DEMONSTRATION PROJECT <br />Schedule: 2017 <br />Estimated Cost: $195,000 <br />This project will involve restoring an 850 foot portion of Crystal Creek to a natural state and enhancing <br />its water quality by creating a wetland buffer around it. Currently the creek channel is highly incised and <br />the alignment is straight. The creek restoration will involve re-grading the creek channel so that its <br />alignment is more natural. A wetland area will be created to provide a creek buffer. Because portions of <br />this project are located outside right-of-way, an easement may be required. <br />Figure 1 shows the locations of recommended projects discussed below and Table 2 shows the cost for <br />each project. Projects are listed in order of priority. Detailed cost estimates are provided in Appendix C. <br />STREET SYSTEM PLAN <br />Roslyn has approximately thirteen miles of streets, which are mainly chip sealed; a few sections <br />are asphalted where needed. Most streets have a sixty-foot wide right-of-way. Pennsylvania <br />Avenue has an BO-foot wide right of way. Snow plowing in the winter months takes up most of <br />Roslyn's street budget. Repairingthe snow-plow equipment and fuel also consume many budget <br />dollars. Roslyn's plow equipment consists of two 1970's secondhand graders, a used State <br />Department of Transportation plow/sand/dump truck and a backhoe the City purchased new in <br />1988. Another grader was given to the City in 1999 by the Summit at Snoqualmie and is used for <br />parts. <br />CAPITAL IMPROVEMENT PROJECTS: <br />ST-l-E. PENNSYLVANIA AVE <br />Schedule: 2016 <br />Estimated Cost: $3,067 <br />This project would include Chip-Sealing/Overlay from pt St to A 5t (435 ft) <br />5T-2 -E. DAKOTA AVE <br />Schedule: 2016 <br />Estimated Cost: $3,525 <br />This project would include Chip-Sealing from pt St to A St (500 ft) <br />ST-3-N A ST <br />Schedule: 2016 <br />Estimated Cost: $2,115 <br />This project would include Chip-Sealing/Overlay from E Dakota Ave to E Pennsylvania Ave (300 <br />ft) <br />ST-4-N BST <br />Schedule: 2016 <br />Estimated Cost: $2,115 <br />June 15, 2016