HomeMy WebLinkAbout2026-11-10-minutes-solid-waste-and-maintenanceKITTITAS COUNTY
SOLID WASTE AND MAINTENANCE MINUTES
BOCC CONFERENCE ROOM, 205 WEST 5TH ROOM 108 - ELLENSBURG
Regular Meeting
TUESDAY 1 2:00 PM I November 10, 2026
Board members present: Chairman Brett Wachsmith, Vice- Chairman, Laura Osiadacz
and Commissioner Jeff Leichleiter
Others: Jesse Cox, Cody Cupp, Charlie Smith and Lisa Lawrence.
Call to Order at 2:01 p.m.
Citizen Comments (1 min. time limit) None
Solid Waste Updates: Discussion was held on the approximate cost for removal and relocation
of compost, equipment and a storage shed from the old Transfer Stations site.
Discussion — Jail Change Order 416: Discussion was held on the details and cost of Change
Order # 16 for the Jail renovation project.
Discussion — EOC/SAR Change Order #4: Discussion was held on the details and cost on the
EOC/SAR project Change Order #4.
OTHER BUSINESS: A brief discussion was held on the paint samples for the bathrooms in the
Courthouse. A brief discussion was held on moving the screen in the Auditorium.
Meeting concluded at 2:11 pm
Lisa Lawrence
2026-11-10 MINUTES
KITTITAS COUNTY COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
Brett Wachsmith, Chairman
KITTITAS COUNTY COMMISSIONERS
Solid Waste and Maintenance
Regular Meeting
Tuesday November 10, 2026 - 2:00 PM
BOCC Conference Room
205 West 5th Room 108 - Ellensburg
1. Call to Order
2. Citizen Comments (1 min. time limit)
3. Solid Waste Updates
4. Discussion - Jail Change Order #16
5. Discussion - EOC/SAR Change Order #4
6. Other Business - No Action to be taken
7. Concluded
Kittitas County is committed to making its services, public meetings, programs, and activities readily
accessible to individuals with disabilities in accordance with the Americans with Disabilities Act (ADA).
Reasonable accommodations will be provided upon request.
To request an accommodation, please contact the Kittitas County ADA Coordinator as soon as possible
to allow sufficient time for the County to make the necessary arrangements.
A Request for Accommodation form is available at the Kittitas County Courthouse. You may also request
a form or submit an accommodation request by contacting the Kittitas County ADA Coordinator at
(509) 962-7082 or hraAco.kittitas.wa.us.
Created on 11/9/2026 7:13:10 AM
KITTITAS COUNTY
Board of County Commissioners
STUDY SESSION STAFF REPORT
DATE: November 10, 2026
ACTION REQUESTED: Information Only; no action requested
BACKGROUND: Solid Waste has received bids for the final removal and relocation
of compost, equipment, and a work shed. The bids received to
date total approximately $28,000. A final bid is pending so an
exact amount is not yet available.
The work includes moving a bobtail tractor compost screen, turner
hood, prefabricated shed, approximately 900 cubic yards of
compost, and approximately 425 yards of compost overs to
Ryegrass.
INTERACTION: Kittitas County Solid Waste
RECOMMENDATION: Information and discussion only; no Board action requested.
HANDLING: No Action required.
LEAD STAFF: Jesse Cox, Solid Waste Director
KITTITAS COUNTY
Board of County Commissioners
STUDY SESSION STAFF REPORT
AGENDA DATE: November 10, 2026
ACTION REQUESTED: Change Order #16 Discussion
BACKGROUND: Change Order #16 for the Jail renovation project encompasses
COP#26 Matron Room Door, COP#27 Janitorial Wall Repair,
COP#28 Grinder Pump Wi-Fi Alarm, COP#29 Acoustic Panels,
COP#30 Wall Pack Light Relocation, COP#31 Window Bars, and
Contract Time Extension. This Change order total is $14,706.28.
INTERACTION: Maintenance, BOCC.
RECOMMENDATION: No Action requested at this time.
HANDLING: N/A
ATTACHMENTS: Change Order # 16
LEAD STAFF: Cody Cupp, Facilities Maintenance Director
Docusign Envelope ID: BD46A443-5F6A-82FC-82CE-8CC3A8AC0140
Change Order
PROJECT: CONTRACT INFORMATION:
Kittitas County Jail Facilities Renovation Contract For: Renovation
Task 1
205 West 5th Avenue Date: 04-30-2025
Ellensburg, WA 98926
KNI1' Designirig C;omrrunitie�
Pr;„r-< No. 230076
CHANGE ORDER INFORMATION:
Change Order Number: 016
Date: 10-29-26
OWNER: ARCHITECT: CONTRACTOR:
Kittitas County Knit Belsaas & Smith Construction, Inc.
205 West 5th Avenue 7826 Leary Way, Ste. 200 103 East 4th Avenue, Suite 209
Ellensburg, WA 98926 Redmond, WA 98052 Ellensburg, WA 98926
THE CONTRACT IS CHANGED AS FOLLOWS:
This Change Order includes cost adjustments for the added scope of work identified in COP #26 through COP #31, and an
adjustment to the Contract Time for the Recreation Yard skylights. Architect -approved COP backup is attached.
1. COP #26 - Matron Room Door Gauge Change (8/21/26): Furnish and install heavier -gauge Matron Room door. $541.65 +
WSST. 0 days (lead time concurrent with Item 7).
2. COP #27 - Janitorial Wall Repair (10/7/26): Demo lower section of wall (19' W x T H), install new steel studs, replace
plywood and steel plating, caulk and paint entire wall. $5,301.48 + WSST. 0 days.
3. COP #28 - Grinder Pump Wi-Fi Alarm (ASI 010) (10/15/26): Wi-Fi alarm wired to pump control panel with new 120V
receptacle, Owner app setup, pit cleaning and float tie -off. $4,179.22 + WSST. 0 days.
4. COP #29 - Acoustic Panels (10/7/26): Furnish and install (7) acoustic panels inside the mesh ceiling of the new command
center. $1,942.34 + WSST. 0 days.
5. COP #30 - Wall Pack Light Relocation (10/14/26): Remove and reinstall wall pack light in conflict with the new structural
beam for the skylight framing. $724.50 + WSST. 0 days.
6. COP #31 -Window Bars (10/29/26): Fabricate, paint and install (7) steel angle bars across the inside of the new control
room windows in the jail annex. $2,017.09 + WSST. 0 days.
7. Contract Time Extension - Recreation Yard Skylights: Per Time Extension Request No. 2, Rev. 2 (10/15/26), add 189
calendar days for Velux skylight delivery delays. Substantial Completion revised from August 28, 2026 to a fixed date of
March 5, 2027. Contractor may demobilize once all remaining base contract and COP work is complete, following partial
close-out of completed non -skylight work. No change to the Contract Sum.
The original Contract Sum was $ 2,457,000.00
The net change by previously authorized Change Orders $ 1,721,439.06
The Contract Sum prior to this Change Order was $ 4,178,439.06
The Contract Sum will be increased by this Change Order in the amount of $ 14,706.28_
The new Contract Sum including this Change Order will be $ 4,193,145.34
The Contract Time will be increased by One Hundred Eighty -Nine (189) calendar days.
The new date of Substantial Completion will be March 5, 2027.
Contract Sum amounts exclude Washington State Sales Tax (WSST), which is applied at time of payment.
NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER.
�96BF4,2D_
d by' by:
,�VLd.LV'SbVU ._ 11 OAS-.. -
ARCHITECT (Signature) CONTRACTOR (Signature) OWNER (Signature)
Knit Belsaas & Smith Construction, Inc. Kittitas County
BY: John Anderson, Principal BY: Scott Carlson, Project Manager BY:
(Printed name and title) (Printed name and title) (Printed name and title)
11 /2/2026 11 /2/2026
Date Date Date
Kittitas County Jail Facilities Renovation I Charge (;tenet 016 1 Atta,?ti , r,t
KITTITAS COUNTY
Board of County Commissioners
STUDY SESSION STAFF REPORT
AGENDA DATE: November 10, 2026
ACTION REQUESTED: Change Order #4 Discussion
BACKGROUND: Change Order #4 for the EOC/SAR project encompasses COP#14
Extension of Culvert, COP#15 Credit for Skylight Curbs and Labor,
COP#16 Reimbersement for 3Td Party Testing, COP#17 Door
Hardware Additions, and Time Extension. This Change Order
Totals $6,535.25
INTERACTION: Maintenance, BOCC.
RECOMMENDATION: No Action requested at this time.
If* Ma 04 IRE
ATTACHMENTS: Change Order #4
LEAD STAFF: Cody Cupp, Facilities Maintenance Director
PROJECT: New Regional Search and RescuelEOC Facility
Kittitas County
2021 Airport Rd
Cie Elum, WA 98922
TO: Belsaas & Smith Construction inc.
PO Box 926
Ellensburg, WA 98926
INITIATION DATE:
November 3, 2026
ARCHITECTS PROJECT NO.:
2516
CONTRACT FOR:
General Construction
Notice to Proceed Date:
November 3, 2025
Substantial Completion Date:
July 31, 2026
The following work has been completed and incorporated as changes in this Contract:
COP-14
Extention of culvert pipe and gravel drive at Airport Road entrance
COP-15
Credit for skylight curbs and labor to install
COP-16
Reimbersment for 3rd party testing payments
COP-17
Door Hardware additions
Time Extension Request
CHANGE ORDER NO.: 4
Amount Days
$2,334.81 2
($7,046.66)
$5,607.50
$5,639.60
$0.00 36
TOTAL $6,535.25 38
Not valid until signed by both the Owner and Architect.
Signature of the Contractor indicates his agreement herewith, including any adjustment in the Contract Sum or Contract Time.
The original Contract Sum was................................................................................................................
$2,955,300,00
Net change by previously authorized Change Orders.........................................................................
$148,832.72
The Contract Sum will be (increased) by this Change Order..................................................................
$6,535.25
The new Contract Sum including this Change Order will be...............................................................
$3,110,667.97
Net change in Contract Time by previously authorized Change Orders ...................
79
The Contract Time will be changed per this Change Order
38
The Date of Substantial Completion is now., .......... ....................................... ..........
November 25, 2026
&fR/!rc(wtectym VUc
ARCHITECT
1320 North 16th Avenue, Suite C
Yakima, Washington 98902
By (j
Date 11 /03/2026
Authorized:
Kittitas County Belsaas & Smith Construction inc.
OWNER CONTRACTOR
205 West 5th Ave PO Box 926
Ellensburg, WA 98926 Ellensburg, WA 98926
By By
Date Date