HomeMy WebLinkAboutExecuted Change OrderFederal Aid Number N/AElectrical Improvements Kittitas Counry Event Center Contract TitleContract Number scJ 22-000i86-3 Date 9lt'712026 Change Description Tree Removal and Trench Modilications Change Order Number 1 Prime Conhactor / Design-Builder Belsaas and Smith Construction Inc -W H:;:ltg:T, ?Hl,,,oorrarion Change Order / Ordered by Engineer under the terms of Section 1-A4.4 of the Standard Specifications f] Cnange proposed by Contractor / Design-Builder Verbal Approval Given By Patti Stacey Verbal Approval Date Working Days +l 7 Original Conkact Amount $102,927.82 Current Contract Amount $t02,927.82 Est. Net Change This C.O. $20,s91.i0 Est. ContractAmount $ 123,5 18.93 WSDOTFoTm 140-005 Revised 04120'15 Change Description Change Order t consists of the following: Tree Removal (RFP I Revision I - attached) An existilg tree that has been designatecl by the City of Ellensburg Arborist as a hazard tree and has been recommenclecl to be removed. The r-esult of this tree removal is recluction in public safety, reduction in requirecl utility easements on the CoLrnty property, and a more efiicient utility trench. Per RFP l, Option I (stump ."*o,.,rol) will be incorporatecl into this project as ciescribed in RFP l. Addilional 7 working days (2 for tree removal and 5 for "g"i,"y coorclinationj woulcl be added to the Contract Working Days based on an NTP of 911412026. A new bid item (#14) will be adcled to the contract "Tree Removal" Unit: Lump Sum, Unit Cost: $18,918'00 (+ WSST), QTY: 1, Total Cost: $18,918.00 (+ WSST) =520,544.95 SEE NEXT PAGE ,/ Approval Recommended Approved Date I q Approval Recommended qlBI o ?-(e Date Other Approval As Required Signature Representing Date Page 1 Change Order Number IElectrical Improvements Kittitas County Event Center Contract TitleContract Number scJ 22-000186-3 Change Description Cont. Trench Modifications (RFP 2): Modifications to the as award trench width requirements and utilities to be incoqporated have been changed (addition of gas and other private utilities). See Rfp 2 for frrther details' The net change in the deletion of BI iz (s-+g,eoo.00)and the addition of BI 15,16,17 (549,642.50) is ($a2.50 + wssT)' Bid Item 12 UTILITY TRENCH LF 800 Unit cost: -$62.00 Total Cost: -$49,600'00 l5 T6 t7 UTILITY TRENCH A,B,C,F,G 24'' WGAS LF 518 UTILITY TRENCH D I2'' LF 278 UTILITY TRENCH E 18" WGAS LF 59 Unit cost: $60.50 Total Cost: $31,339.00 Unitcost: $53.00 Total Cost: $14,734'00 Unit cost: $60,5 Total Cost: $3,569'50 rotal cost change(wio,l1? 11t"1? WSDOT Form 140-005 Revisecl O4l2A15 Page 2