HomeMy WebLinkAboutCOP78 MRW North Wall Structural Revision
P.O. BOX 926 / 103 EAST 4TH AVE, SUITE 209
ELLENSBURG, WA 98926
509-925-9747 FAX: 509-962-3031
brandon@belsmith.com
Sept 9,2026
Re: MRW North Wall Structural Revision
Per the description below, we present the following change order proposal #78 (COP#78).
COP #78 includes all the labor and materials needed to construct the additional structural
needs for the northern wall of the MRW Facility. The items included in this proposal are as
shown below.
• Box Beam and Wall Attachments
• All Columns and Wall Attachments
A more detailed cost breakdown is shown below along with the plans that we will be building
off. If you have any additional questions, please feel free to reach out.
Total cost added to contract: $10,519.29+WSST
Time extension required: 87 Calander Days.
These additional days extend the contract completion date from the current final contract day
of July 14th to October 9th.
If the required materials are ordered by Monday, September 14th, they are anticipated to be
received by September 24th. Following receipt of the materials, approximately two additional
weeks of labor will be required to complete the remaining work.
The remaining work consists of fabrication and installation of the box beam and columns, as
well as installation of the remaining metal siding.
Sincerely,
Riley Eres,
Belsaas & Smith Construction
BELSAAS & SMITH CONSTRUCTION
SHEET 1 of 2 C.O.P. #78
CHANGE ORDER PROPOSAL BREAKDOWN SHEET
UNIT COSTS EQUIP SUB MATERIAL LABOR
#DESCRIPTION QUAN.UNIT Mat.EQUIP LABOR COST COST COST COST
MRW North Wall
Materials
CWallA Steel Framing 1 LS 2484.11
SeaCon
Labor
Carpenter (2EA - 3 Days)60 HR 93.99 5,639
Office 4 HR 88.00 352
0
Equipment
Boom Lift 2 Weeks 3 DAY 250.00 750.00
*TOTALS 750 0.00 2,484 5,991
BELSAAS & SMITH CONSTRUCTION
SHEET 2 of 2 C.O.P. #78
CHANGE ORDER PROPOSAL BREAKDOWN SHEET
EQUIP SUB MATERIAL LABOR
COST COST COST COST
TOTALS FROM PREVIOUS PAGE 750.00 0.00 2,484 5,991.40
OVERHEAD 3%22.50 0.00 74.52 179.74
PROFIT 10%77.25 0.00 255.86 617.11
BONDING 1.5%12.75 0.00 42.22 101.82
SUB TOTAL 772.50 0.00 2,857 6,890.08
SUB TOTAL 773 0.00 2,856.71 6,890
LABOR 6,890
MATERIAL 2,856.71
EQUIPMENT 773
SUBCONTRACTORS 0.00
SUB TOTAL SUB TOTAL 10,519.29
GRAND TOTAL TOTAL 10,519.29
TIME EXTENTION REQUIRED:0
NOTICE TO PROCEED REQUIRED BY:
WE RESERVE OUR RIGHTS UNDER THE CONTRACT TO ACCESS THIS CHANGE
CUMULATIVELY AS IT AFFECTS TIME AND AMOUNT.
Project
www.lundopsahl.com |Tel: 206.402.5156
Project No.
Subject / Reference
Client
Date
Designer
1215 Fourth Avenue, Suite 1200
Seattle, Washington 98161
206-402-5156 |www.lundopsahl.com
Kittitas County Transfer Station
MRW Building - Adding Exterior Wall w/ Midway Support
SCS Engineers
AC
22-186-01
9/2/26
1.4 2.4 3.4 4.4 5.4
F.4
E.4
20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0"
20
'
-
0
"
7
4_S302
12
4_S302
TYP AT
COL
6
4_S302
6.4
4_S302
3 TYP
UNO
5'-0" x 5'-0" x 18" D CONC FTG,
w/ (7) #5, EA WAY BOT, TYP UNO
7
4_S302
7
4_S302
6
4_S302
SIM
BLIND SUMP PER MEP
SEE S-SK-07
A PARTIAL PLAN - MRW BUILDING FOUNDATION PLAN
SCALE: NTS
B EXTERIOR WALL CFS FRAMING CONNECTION TO (E) PEMB COL
SCALE: 1 1/2" = 1'-0"
B
(E) PEMB COL
BACK-TO-BACK
HORIZ TRACK PER A
400S150-33 BLOCKING
@ EA (E) PEMB COL
BACK-TO-BACK 400T150-33
@ 24" OC, TYP
(2) #8 SCREWS, TYP BLKG TO
HORIZ TRACK CONNECTION
(3) SELF TAPPING #12 SCREWS,
TYP HORIZ TRACK END TO (E)
PEMB COL CONNECTION
5/8"ø TITEN HD SCREW
ANCHOR @ 48" OC w/
4" MIN EMBEDMENT
T.O.E. CONCRETE
(E) CONC FOOTING
AND CURB
S-SK-11.R1A
(
2
)
4
0
0
S
3
5
0
-
6
8
B
O
X
E
D
C
O
L
U
M
N
,
T
Y
P
BOXED (2) 600S350-54 @ TOP
0"
S-SK-11.R1A
C
S-SK-11.R1B
TOP BOXED BEAM PER
A/S-SK-11.R1A, COPE END
AROUND (E) PEMB COL
BENT PL 3" x 2" x 33MIL x 0"-6" T&B
w/ (3) #12 SCREWS INTO (E) PEMB
(4) #8 SCREWS, T&B
Project
www.lundopsahl.com |Tel: 206.402.5156
Project No.
Subject / Reference
Client
Date
Designer
1215 Fourth Avenue, Suite 1200
Seattle, Washington 98161
206-402-5156 |www.lundopsahl.com
Kittitas County Transfer Station
MRW Building - Adding Exterior Wall w/ Midway Support
SCS Engineers
AC
22-186-01
9/2/26
B EXTERIOR WALL CFS FRAMING CONNECTION TO (E) PEMB COL
SCALE: 1 1/2" = 1'-0"
S-SK-11.R1B
T.O.E. CONCRETE
(E) CONC FOOTING
AND CURB
BACK-TO-BACK
HORIZ TRACK PER
A/S-SK-11.R1A
TYP MIDWAY SUPPORT
BOXED COLUMN PER
A/S-SK-11.R1A
X X X
X X X
TOP BOXED BEAM PER
A/S-SK-11.R1A
BENT PL 2" x 2" x 33MIL x 0"-3 1/2" T&B
w/ (3) #8 SCREWS INTO COL & BEAM,
EA SIDE OF COL
X X X
BENT PL 2" x 2" x 33MIL x 0"-3 1/2" T&B
w/ (3) #8 SCREWS INTO COL & 5/8"ø
TITEN HD SCREW ANCHOR w/ 4" MIN
EMBEDMENT, EA SIDE OF COL
X X X