September 3, 2026
Re: ASP Added Fencing
Per the description below, we present the following change order proposal #77 (COP#77).
COP #77 includes all the labor and materials needed to construct the additional fencing
between the ASP and ponds. The proposed fencing will be an identical match to the existing
perimeter fence color and installation methods.
Total cost added to contract: $16,493.46+WSST
Time extension required: 0 Days
Sincerely,
Riley Eres,
Belsaas & Smith Construction
BELSAAS & SMITH CONSTRUCTION
SHEET 1 of 2 C.O.P. #77
CHANGE ORDER PROPOSAL BREAKDOWN SHEET
UNIT COSTS EQUIP SUB MATERIAL LABOR
#DESCRIPTION QUAN.UNIT Mat.EQUIP LABOR COST COST COST COST
ASP Added Fencing
M2 Quote 1 LS 14,139.62$
Project Manager 3 HR 88.00$ 264.00$
*TOTALS 0 14,139.62$ 0 264
BELSAAS & SMITH CONSTRUCTION
SHEET 2 of 2 C.O.P. #77
CHANGE ORDER PROPOSAL BREAKDOWN SHEET
EQUIP SUB MATERIAL LABOR
COST COST COST COST
TOTALS FROM PREVIOUS PAGE 0.00 14,139.62$ 0 264.00
OVERHEAD 3%0.00 424.19$ 0.00 7.92
PROFIT 10%0.00 1,413.96$ 0.00 27.19
BONDING 1.5%0.00 212.09$ 0.00 4.49
SUB TOTAL 0.00 16,189.86$ 0 303.60
SUB TOTAL 0 16,189.86$ 0.00 304
LABOR 304
MATERIAL 0.00
EQUIPMENT 0
SUBCONTRACTORS 16,189.86
SUB TOTAL SUB TOTAL 16,493.46
GRAND TOTAL TOTAL 16,493.46
TIME EXTENTION REQUIRED:0
NOTICE TO PROCEED REQUIRED BY:
WE RESERVE OUR RIGHTS UNDER THE CONTRACT TO ACCESS THIS CHANGE
CUMULATIVELY AS IT AFFECTS TIME AND AMOUNT.
M2 INDUSTRIAL, INC.180 Hanson Road
Ellensburg, WA 98926 509-925-6303
Cont. Reg. #MTWOII*088DQ office@m2industrial.com
Page 1PROPOSAL/CONTRACT
09/01/2026
Customer Information:Job Information:
Belsaas & Smith Lower Valley Transfer Station
700 E. Mountain View, #504 Leachate Pond-Debris Fence
Ellensburg, WA 98926
--
Notes:
1. Price does not include Sales Tax.
2. Price is for installation of fence as shown on the attached drawing.
3. Terms: Balance due upon completion.
4. No fee for cash or check payments. Additional fee for credit card payments
5. Owner will identify property line for fence installation.
6. M2 Industrial will call for underground utility locates prior to starting work.
Approved & Accepted for Customer:
Contract Amount:14139.62$ Date
Down Payment:$ Accepted for M2 INDUSTRIAL, INC.:
Balance Due:14139.62$
Salesperson Date
M2 INDUSTRIAL, INC.180 Hanson Road
Ellensburg, WA 98926 509-925-6303
Cont. Reg. #MTWOII*088DQ office@m2industrial.com
Page 2PROPOSAL/CONTRACT
09/01/2026
Customer Information:Job Information:
Belsaas & Smith Lower Valley Transfer Station
700 E. Mountain View, #504 Leachate Pond-Debris Fence
Ellensburg, WA 98926
--
TERMS & CONDITIONS
M2 INDUSTRIAL, INC. agrees to guarantee above fence to be free from defects in
materials and workmanship for one year. Locating, clearing, grading and staking of
fence lines is the sole responsbility of the customer. Customer agrees that M2
INDUSTRIAL, INC. shall not be held responsible for any damage to underground pipes,
wires or hidden obstructions, and herewith waives any claims relating thereto. If
property pins cannot be located it is recommended that the customer have the property
surveyed. The parties further agree that if client fails to pay balance, M2
INDUSTRIAL, INC. may claim a lien on the premises upon which the within materials are
to be installed. This proposal shall become a binding contract between the parties at
such time as both parties sign it. Unless otherwise specified on page one under
notes, all work is due and payable upon completion, no retention to be withheld.
Customer agrees that the delinquent account shall bear interest at 1.5% per month from
the date said account is due. Any alteration or deviation from bid specifications
involving extra costs will become an extra charge over and above the estimate.
Customer and M2 INDUSTRIAL, INC. agree that in the event it is necessary for either
party to retain the services of an attorney to enforce any of the terms or conditions
of this agreement that the prevailing party in any litigation shall be entitled to
reimbursement for attorney fees and costs incurred and that the venue for any action
at law shall lie in Kittitas County, Washington. The costs of all licenses or permits
required for the construction of this project shall be added to the cost of the
contract. This contractor, M2 Industrial, Inc., is registered with the State of
Washington, Registration No. MTW0II*088DQ, as a general contractor for negligent or
improper work or breach of contract in the conduct of the contractors business. The
expiration date of this contractor's registration is 10-20-26. This bond or cash
deposit may not be sufficient to cover a claim which might arise from the work done
under your contract. If any supplier of material used in your construction project or
any employee of the contractor or subcontractor is not paid by the contractor or
subcontractor on your job, your property may be leined to force payment. If you wish
additional protection, you may request the contractor to provide you with original
"lien release" documents from each supplier on your project. The contractor is
required to provide you with further information about lien release documents if you
request it. General information is also available from the Department of Labor and
Industries.
CUSTOMER Initial _______
SALESPERSON Initial _______