Project: Lower Valley Transfer, Change Order No. 16
Mr. Nelson,
I am writing to formally acknowledge and award change order number 16 for the following Change
Order Proposals (COP):
COP #77 Compost Fencing
COP #78 Additional MRW Wind Wall Bracing
$16,493.46
$10,519.29
Change Order No. 16 Total $27,012.75
Base Bid and Additive A2 $18,441,939.80
Additive A1 $642,000.00
Change Order No. 2 <$11,754.08>
Change Order No. 3 <$28,041.41>
Change Order No. 4 $145,224.93
Change Order No. 5 $233,662.44
Change Order No. 6 <$24,051.84>
Change Order No. 7 $96,439.74
Change Order No. 8
Change Order No. 9
Change Order No. 10
Change Order No. 11
Change Order No. 12
Change Order No. 13
Change Order No. 14
Change Order No. 15
Change Order No. 16
$104,401.24
$127,737.00
$46,392.94
$49,209.69
$142,300.43
$68,044.01
$123,878.51
$261,511.94
$27,012.75
Subtotal $20,509,755.42
WSST $1,758,348.03
Total $22,268,103.45
Please consider this letter as our formal acceptance of the change order.
We look forward to successfully completing this project together with these agreed -upon
adjustments. Thank you,
_____________________________ ___________________________________
Bryan Nelson Brett Wachsmith
Secretary Chair, Board of County Commissioners
Belsaas and Smith Construction Kittitas County
103 E 4th Ave # 209 205 W 5th Ave #108
Ellensburg, WA 98926 Ellensburg WA 98926