HomeMy WebLinkAbout2026-09-14-minutes-public-works-study-sessionKITTITAS COUNTY
PUBLIC WORKS STUDY SESSION MINUTES
COMMISSIONERS' AUDITORIUM, 205 WEST 5TH ROOM 109
MONDAY 1:30 PM SEPTEMBER 14, 2026
Board members present: Chairman Brett Wachsmith, Vice -Chairman Laura
Osiadacz and Commissioner Jeff Leichleiter.
Others: Joshua Fredrickson, Arden Thomas, Lisa Godden, Kittitas
County Public Works; James McCubbin, Kittitas County Prosecutor's
Office; Darren Higashiyama, Kittitas County Sheriff's Office; Cory
Wright, Kittitas County Conference of Governments; Kristi More and
Christopher Griffin, The Ferguson Group (virtual), no members of the
public.
At 1:30 PM Chairman Brett Wachsmith opened the Public Works Study
Session.
NO CITIZEN COMMENTS
YAKIMA RIVER AT EASTON FLOOD RISK CATEGORIES
Arden Thomas briefed the Board of County Commissioners on the need to
establish additional flood risk categories for the Yakima River at
Easton following the December 2025 flood event. Arden Thomas
explained that the existing National Weather Service forecast
information identifies only an action stage and minor flooding,
limiting the ability to communicate the potential severity of larger
flood events to the public. Staff requested direction to coordinate
with the National Weather Service to develop and publish additional
flood impact categories using available hydraulic modeling. The Board
supported staff proceeding with this coordination and public
outreach. Arden Thomas noted that the categories would be reviewed
and adjusted as conditions warrant.
OTHER BUSINESS - NO ACTION TO BE TAKEN
Joshua Fredrickson introduced Cory Wright and Kristi More regarding
the proposed regional federal advocacy and grant -services arrangement
through the Kittitas County Council of Governments and The Ferguson
Group. Cory Wright stated that the County's annual contribution would
remain at $7,000 and that the arrangement is anticipated to begin
October 1, 2026. Kristi More described expanded services, including a
County -specific strategic funding plan, identification of federal,
state, foundation, and private funding opportunities, regional
advocacy, and continued support for County -specific federal
priorities. No action was taken.
2026-09-14 MINUTES
PORTION OF 1ST STREET RONALD ROAD VACATION REQUEST
Joshua Fredrickson briefed the Board of County Commissioners on a
petition to vacate approximately 0.04 mile of First Street in Ronald
to allow expansion of an adjacent business. Joshua Fredrickson
explained that, as submitted, the vacation would create a landlocked
parcel. Staff has advised the applicant that an easement or boundary
line adjustment is needed before the request can be supported.
Following discussion, the Board directed staff to request the
applicant's written agreement to postpone the public hearing while
the applicant completes the necessary property -line work, with the
application remaining active under the existing fee. If the applicant
requests that the hearing proceed before the issue is resolved, staff
will return to the Board with the matter and a recommendation to deny
the request.
STONE ROAD SPEED REVISION
Joshua Fredrickson briefed the Board of County Commissioners on a
proposed reduction of the posted speed limit on Stone Road, south of
Ellensburg off Canyon Road, from 50 mph to 35 mph. The roadway is a
0.6-mile no -outlet road, and the most recent 85th-percentile speed
study recorded a speed slightly above 36 mph. Joshua Fredrickson
explained that the reduced speed would support the proposed roadway
elevation and flood berm work while maintaining access to County -
owned floodplain property and adjoining private driveways. The Board
directed staff to prepare the engineer's report and documents
necessary to schedule a public hearing on the proposed speed
revision.
BEAD BROADBAND PROJECT UPDATE
Joshua Fredrickson briefed the Board of County Commissioners on the
Broadband Equity, Access, and Deployment (BEAD) program. The County
has been awarded funding for seven project areas, totaling more than
$32 million, to expand service to unserved and underserved locations.
Joshua Fredrickson reported that the funding is fully supported by
federal and state sources and includes reimbursement for County
administration, grant compliance, and related staff resources. The
County is expected to enter a subgrant agreement with the Washington
State Broadband Office, then execute a corresponding agreement with
the selected provider. The project will include an irrevocable right
of use for a 12-strand fiber line throughout the project area for
County and government -partner communications needs. The State
requested execution of the subgrant agreement by October 8, 2026;
construction must be completed by 2030, subject to the provider's
ability to complete work sooner. No action was taken.
2026-09-14 MINUTES
6-YEAR TRANSPORTATION PLAN UPDATE
Joshua Fredrickson briefed the Board of County Commissioners on the
annual update to the Six -Year Transportation Improvement Plan.
Following the public -comment period, staff corrected calculation
errors and added a final -year feasibility study for an extension
connecting Bowers Road to Look Road near the airport. Public comments
also addressed Passmore Road and the Kittitas Highway No. 6
intersection. Joshua Fredrickson reported that the intersection
remains the County's top transportation -safety priority for pursuit
of state funding, while the requested speed reduction will proceed as
a separate process. The updated plan will be brought forward for
final consideration at a future meeting. No action was taken.
BOWERS FIELD AIRPORT UPDATE
Joshua Fredrickson briefed the Board of County Commissioners on
airport capital projects and lease activities. The hangar taxi -lane
project is under construction and is expected to be completed by the
end of fall 2026; it will provide access to additional hangar sites
with nearby water and sewer utilities. Staff is also advancing design
of a parallel taxiway project estimated at approximately $15 million.
The project is anticipated to require a 10 percent County match,
estimated at approximately $1.5 million, with a smaller design -phase
match expected in 2027 and the larger construction match anticipated
in 2029. Staff is evaluating potential funding sources for the match.
Joshua Fredrickson also reported that four grazing leases will expire
at the end of 2026. The Airport Advisory Committee supports a new
solicitation for the leases, which will be presented to the Board at
a future meeting. No action was taken.
FLOOD CONTROL ZONE DISTRICT 2027 - 2032 CAPITAL IMPROVEMENT PLAN
Arden Thomas briefed the Board of County Commissioners on the Flood
Control Zone District's 2027-2032 Capital Improvement Plan. Current
priority projects include the Whiskey Creek siphon implementation
project, Lower Kittitas Reach floodplain reconnection project, and
Mercer Creek flow conveyance restoration project. Arden Thomas
reported projected 2027 capital expenditures of $3.3 million,
contingent upon receipt of a $1 million Federal Highway
Administration grant; expenditures would decrease substantially if
the grant is not received. Arden Thomas also described the importance
of partnerships with the Kittitas County Conservation District, Mid -
Columbia Fisheries Enhancement Group, and the City of Ellensburg in
delivering flood -risk -reduction and habitat projects. No action was
taken.
2026-09-14 MINUTES
NO OTHER BUSINESS
Meeting concluded at 2:25 PM
isa Godden,
Administrative Assistant
2026-09-14 MINUTES
KITTITAS COUNTY COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
Brett Wachsmith, Chairman
KITTITAS COUNTY COMMISSIONERS
Public Works Study Session
Regular Meeting
Monday September 14, 2026 -1:30 PM
BoCC Auditorium
205 West 5th Room 109 - Ellensburg
1. Call to Order
2. Citizen Comments (1 min. time limit)
3. Portion of 1st Street Ronald Road Vacation Request
4. Stone Road Speed Revision
5. BEAD Broadband Project Update
6. 6-Year Transportation Plan Update
7. Bowers Field Airport Update
8. Yakima River at Easton Flood Risk Categories
9. Flood Control Zone District 2027 — 2032 Capital
Improvement Plan
10. Other Business - No Action to be taken
11. Concluded
Created on 9/10/2026 2:18:07 PM
KITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
PUBLIC WORKS — BOARD OF COUNTY COMMISSIONERS
STUDY SESSION STAFF REPORT
STUDY SESSION DATE: September 14, 2026
TOPIC: Yakima River at Easton Flood Risk Categories
ACTION REQUESTED: Direction to staff
LEAD STAFF: Arden Thomas
RECOMMENDATION: Direct staff to work with the National Weather
Services to update flood risk categories.
BRIEFING SUMMARY:
• The National Weather Service uses flood risk categories to communicate how
severe flooding is expected to be at a particular location.
• The Elk Meadows, Elk Meadows II, Pine Glen, and Sun Island communities are
our most at -risk flood communities. While river forecasting is available for this
area, flood risk categories for moderate and major flood stages have not been
identified.
• The National Weather Service has requested that Kittitas County provide input on
flood risk categories.
• Recent investments in hydraulic modeling have enabled us to provide more
informed feedback.
• If the NWS updates the flood risk categories, we recommend reaching out to
Easton Reach area residents to inform them about the availability of river forecast
and information.
BACKGROUND:
The U.S. Bureau of Reclamation maintains a river gage at Easton (EASW) that measures
the Yakima River's water level. The Northwest River Forecast Center (National Oceanic
and Atmospheric Administration, National Weather Service) displays observed river
levels and develops and displays a 7-day river forecast. The National Weather Service
(NWS) also shows flood risk categories to help identify and communicate the anticipated
severity of a forecasted flood event.
The Elk Meadows, Elk Meadows II, Pine Glen, and Sun Island communities are our most
at -risk flood communities. While river forecasting is available at the EASW gage, this
area currently lacks flood risk categories. After the December 2025 flood, the National
Weather Service requested that Kittitas County provide input on flood risk categories.
The NWS utilizes the following flood risk categories:
Page 1 of 4
PUBLIC WORKS BOARD OF COUNTY CONMSSIONERS WORK SESSION STAFF REPORT
• Action Stage: The level which, when reached by a rising stream, represents the
level where the NWS or a customer/partner needs to take some type of
mitigation action in preparation for possible significant hydrologic activity.
• Minor Flood Stage: Minimal or no property damage, but possibly some public
threat.
• Moderate Flood Stage: Some inundation of structures and roads near the
stream.
• Major Flood Stage: Extensive inundation of structures and roads. Significant
evacuations of people and/or transfer of property to higher elevations.
The NWS has also indicated that reported flooding suggests the river levels used to
identify the Action Stage and Minor Flood Stage should be lowered. Recent hydraulic
modeling conducted by the Flood Control Zone District, which shows how water is
expected to move through the area during a flood, suggests that both the Action Stage and
Minor Flood Stage thresholds should be lowered. This hydraulic modeling has also been
used to identify potential moderate and major flood designations. The FCZD has
developed initial recommendations, which are shown in Exhibit 1. Exhibit 2 shows how
forecast and flood risk information is displayed by the NWS Northwest River Forecast
Center.
DISCUSSION:
These Easton Reach communities are our most at -risk flood communities. While river
forecasting is available at the EASW gage, this area currently lacks flood risk categories
for moderate and major flood stages. The lack of these flood designations risks
miscommunicating the potential impacts of upcoming flood events.
The flood risk categories are intended to serve as a communication tool for residents
living in these flood -prone communities and to help inform their flood response
decisions. If the flood risk categories are updated, FCZD funding for public outreach
could be used to inform Easton Reach area residents about the availability of forecast
information. We recommend coordinating with the Sheriff's Office on messaging for
outreach efforts.
FISCAL IMPACTS:
FCZD technical review, ongoing monitoring, and potential outreach efforts fall within
our annual budget for these items.
ATTACHMENTS:
Exhibit 1: Recommended river state height for NWS flood risk categories.
Exhibit 2: Example hydrographs at the Yakima River at Easton and Yakima River at
Umtanum with flood risk categories shown.
Page 2 of 4
PUBLIC WORKS BOARD OF COUNTY CONMSSIONERS WORK SESSION STAFF REPORT
EXHIBIT 1: RECOMMENDED RIVER STAGE HEIGHT FOR NWS FLOOD RISK CATEGORIES
Fvictina Prnn-1
Category
GH o
GH
Q
Notes regarding proposed
We will monitor and work to observe flooding at GH 48.7 - 48.9 to verify this action stage. Our hydraulic
modeling indicates that at 1,230 cfs, the channel capacity has met capacity and minor yard minor yard
Action
50
48.9
1,230
inundation in the Elk Meadows Subdivision. USBR stage and discharge records from over the winter
suggests this flow is associated with a stage height of 48.9'. Recent correspondence with Elk Meadows
property owners indicates yard flooding at about GH 49.0'
Property within the Elk Meadows Subdivision is expected to see backyard flooding up to 0.5 ft and the
Minor
51.3
49.9
1,483
Pine Glen Subdivision begins to see minor yard inundation and channel capacity being met.
Elk Meadows Subdivision roads past the bridge become inundated and lots along Elk Meadows road
Moderate
N/A
50.7
2,530
become inundated. Pine Glen Subdivision to see additional yard inundation. Sun Island Subdivision
begins to see minor yard inundation and channel capacity being met.
Major
N/A
53.75
5,572
1 Extensive inundation of structures and roads.
GH Gauge Height (feet)
Q Discharge (cubic feet per second)
Page 3 of 4
PUBLIC WORKS BOARD OF COUNTY COMMISSIONERS WORK SESSION STAFF REPORT
EXHIBIT 2: EXAMPLE HYDROGRAPHS AT THE YAKIMA RIVER AT EASTON
AND YAKIMA RIVER AT UMTANUM WITH FLOOD RISK CATEGORIES
SHOWN
Page 4 of 4
PUBLIC WORKS BOARD OF COUNTY CONIMSSIONERS WORK SESSION STAFF REPORT
Exhibit 2: Example hydrographs at the Yakima River at Easton and Yakima River at Umtanum with flood risk categories shown.
Yakima River at Easton rm wo ctwa. womagso atlwwnes menettm ro ao6 area.
ofiW Foreean Enwmble F-1 NaOonel Yhln Mo
r" UPSTREAM GN1fE1(kEWq
DOWNSTRE" GAUGE rrllAlhl -e
Yakinu RlW et Easton
.NW FAS%1 Read, IO 24126tar
56
5e 6917
am �
M1W- =I,e
21U
623
12M 12" 12M 12 pm 12M 12 pm 12pm 12 pm 12M 12M
Sp7 5ep6 Sp9 Sp to S'n Sp 12 Sp 13 Sp14 Sep is Sp16
sae 11— IMTi
CATEGORY STAGE
,} Yrterree o %l.an Flood Impacts C
Minim& or no property damage, but possibly some public Weal
Action 5o n 51.3 - Flooding of yards and low Mng areas In the Elk Meadows subdivision.
The level which, when reached by a rising stream, represents the level where the NWS ora wsfan7 eryporiner "ds fo
take some type ofmRlgation action M prepamtlon for possible significant hydrologic acilvity.
m rbnRruiswmr �lsn�,se�e w: sx.,lm rasc�neama. av,o,eaeb E�.,K w:<oxm�suam Rmwces ,wwn x ('io
'.'1pR PDT'UMrti.:
Yakima River at Umtanum
tmRup6ortE Spm. %36 t36' 4N
09ilivrut Ens�rob rwww IbYeiW WWrWMI
a- UKTRiI�m 6rUGEMIwrR pQM/jTR[�Ai l'iWEpwRWq +
Yak11n RIYOIR Itmbn,00
MV5Lt u11M1ti' Frnq 2n2515J
% JGfrt10.7�! '
% t!6
aye
� 2s,
12.
&pf 16p9 Sp fO sw It £rpII Sp» 9p 1! 3p fi Bm,i SpM
sx.+wtron
CAT EGO W STAGE
FlRatl Import
M.Wrb." 7�.R
Sgrificam evocuouons ofpeop,e and or transfer ofpropenyto Mgher
�.�""`"1 pio0ib•"1O�RJ°°"'Rorisnw�om urnca�meRu amw ngtr aK ana cmm.o rtom Tww.vor awww.ommErenswiy. avcxvwmlr+m.na
Ewens/ve exrndahon ofsbuctums ondroods.
T.-
elevabcna
IMRElmt. F-dbv X A
Y-MNb WN.Ilaedn6 MraoCr ab RSNiva+ n tlm NcnwattlK Met Mtlat'ar. TFe Elknvxup Mn tuaply WniPbm b MremenM
some inundatbn orv—tare9 and roads nem sbeom.
%5-TRwe will be riwEYq In paWes dorq p:ernay.
M1nHtgl or no prapenydamage, but possibly some pufNk threat.
Aamn aas
The level wh/ch, when reached by a r/sag streom, represents the lever where the NWs or coslomeupartnerneeds to
take same type ofmitgotion action in preparation fm possible signt7conthydrologic octiOry.
KITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
PUBLIC WORKS — BOARD OF COUNTY COMMISSIONERS
STUDY SESSION STAFF REPORT
STUDY SESSION DATE: September 14, 2026
TOPIC: Portion of 1' Street Ronald Road Vacation Request
ACTION REQUESTED: Direct Staff to Prepare Enabling Documents and to
Schedule a Public Hearing
LEAD STAFF:
Joshua Fredrickson
RECOMMENDATION:
Prepare enabling documents and schedule the required public hearing regarding the
proposed right-of-way vacation.
BRIEFING SUMMARY:
• First Street in Ronald was established in the Northern Pacific Railway Company,
Ronald Townsite
• Prior to 1964, Block 11 and Block 13 had boundary line adjustments, which
created an extension of First Street, also known as First Place
• A plat recorded in 1964 identifies the public right-of-way
• Adjacent Lot owner desires vacation of a portion of the right-of-way
• Kittitas County Code Chapter 12.10 and RCW 36.87 identifies road vacation of
County Roads
BACKGROUND:
First Street in Ronald was established in Ronald and prior to a 1964 plat a boundary line
adjustment created an extension of First Street, also known as First Place. A plat recorded
in 1964 (Exhibit 1) identifies the public right of way. The roadway has a paved surface
maintained by the County. The roadway provides access for adjacent business and
property owners.
DISCUSSION:
An application to vacate a portion of 1" Street in Ronald right-of-way was received by
Public Works (Exhibit 2). The location of the proposed vacation is depicted in the
vicinity map (Exhibit 3). Kittitas County Code 12.10 indicates that a Public Hearing
would be used to consider the road vacation request. At the Public Hearing a Director's
Report would be presented. The Director's Report is to include the following:
1. Whether the County Road should be vacated and abandoned
2. Whether the same is in use or has been in use
3. The condition of the road
Public Works Study Session Staff Report 2026
4. Whether it will be advisable to preserve it for the County Road system in the
future
5. Whether the public will benefit by its vacation and abandonment
6. A determination by appraisal of the fair market value of the area sought to be
vacated
7. The classification of the road area according to the type and amount of
expenditures made and the nature of the County's interest therein
8. Whether the proposed area to be vacated contains utilities
9. All other matters which will be of interest to the Board
The area sought for vacation is currently a paved roadway, open to the public. The
roadway provides access to SR903. The vacated roadway would typically go to the
adjacent property. Based on the existing lot layout, one of the parcels currently with
access to I" Street would become land locked. A boundary adjustment may be needed to
maintain access to each lot.
FISCAL IMPACTS:
The applicant has paid PW's road vacation application fee of $3,888.00
ATTACHMENTS:
Exhibit 1: Recorded Plat
Exhibit 2: 1"Street (Ronald) Vacation Request
Exhibit 3: Vicinity Map
Public Works Study Session Staff Report 2026
EXHIBIT 1: Recorded Plat
Public Works Study Session Staff Report 2026
NORTHERN PACIFIC RAILWAY COMPANY
RONALD TOWNSITE
KITTITAS COUNTY, WASHINGTON
3119j x
DESCRIPTION DEDICATION
s• Thai phi of In.SE}SW} B fractional *is**of Section 7, T. 20 N.- Know all men by these presass that the NorthernFocifnc Ro,lway
R isEat the Willomeite Meridlon in Willies County,Woshinptan Comparry,a Wisconsin corporation, and Thomas G. SIalkoHch and Mar
'9 described by metes and bounds as (allows: Storkonch, the rdersiW d,wirrs in fee simple of the land herspy p'Nltad,
BRp'nring al In. outhm Mr of said Section 7; thence hereby declwa this plat end dedicate to the use of Me Public foreva,all
\�. N.O.13 41 E. along the end Nn• of soap Section T a distance of streets and avMuts ,a r/ataver public popery dery is sMnn on the plat
sy\ 2027.a4 feet to n point an the sowhrwlerly right of eruy, line of and the use Ihertof for arty and oil public purposes rot inconeelem with
i Me Northern Pod is Rall—y Campony I Roslyn Branch I : thence glory the use thereof far public high" purposes; else, the riphf to make ell
ti S spice right oe,.ay Its ins la Wrfnnpp fAurwS and dlsh•nces III'nce necewary slopes for cute or fills on lots, blocks, tracts ,etc. shorn an IN%
m along a S.31 curve to Ind right g15.l3 feet; thence 5.40•b2 E. Olot it, the reosorabls ariginai grading of ail streets, avenues,ploces,stc
457.77 feet; thence along a rig cure• to 111e left 143.23 feet sham horeon;sulyect,ho—er,fo its nirwal reservation not faith in the
a •r " to an ofloort in said right of my lase ;thence along tad offset description.
5.40• �'D W 4902 font; tMeKe S: 99' IOC E SS 1.27 (set t(henct along IN WiTNfSS WHEREOF,re have hit—wo sel our hods and
a II.40 cwve to the right 326.E fret; ihtnp S. II•116 E. 367.45 seab thle 25 'Il day o1 February ,AA. 1964.
tart i thence gbrw a Sf curve b Me left 43(117 lest 1� a NOIt PACIFIC iWLWAY S'JMPA.NY
poln� I. the set p liar w aid Section 7; thence N BYS)32 W.
kk flo", �0 / P �.�, piano sold south Hitt 1343.41 feel to the pow of btgkrwg. 9y 1 f in —
Ex Wing and reserving from the lands hereby dedicated all minerals In Pretence Of M Q.
♦ty fl� J .� ,hwsoswr, inWding tad, iron, rofwel gas and oil, rind the riot of entry n sf '—
r¢•' sold bode beMOM 1M u tope, to spore, dewlap, mine ad rwnow
't • ''fr aE rlrbtwale; provided,ltorewr, Mot suet entry and rgrk and every Dare / _ n
/• Mersof stroll of all t,mn M mad• pad cmrled on without SntaMrtnce b o- '/.•i __. . ..
t\ e� i \_ Y r '-'W" the pudic us• and occupancy for street purposes of Me bets dedicated.07
-'" J herby or disturbance of the surface support thereof. STATE OF M
COUNTY OF RAMSRAMSEY EY se
ki 1 HEREBY CERTIFY that the plat of Ronald loafrlte Is boned an
•�;, ,x tot; ` 4 rckral •rveY and ssrbdivielen of Section 7, TowasNp 20 North, Reps 13 On this ZL�loy of fo AD H964 , before me consent-
( = I
corEaa,WM., shot the distac•s and ill~ and angles oni Morn thirteen ally gpsorad ES.Stan. m kr9t ben nd Ku -nr ofIo M eA—d
rectly; ttat the 1—imem► heve net aa been d fat d dck oa the corporalion that owout•d the ett%m end forgoing ,na humwt
i O(+aw an the giond. and ardrowl•dgetl tit. send Insaumeet b M the ties are ,awnnry
) .f. 6' Yd. act and ••ae w said crpdrwirt .far the ales and pu'p— mnrin
a w \ ✓ t . yi 6 x`* �• 1 1 t�. "- marNand on.d aan Olson staled that tit was ouNrKi3ed to e- ..1e and SHGhED: r .--I(/�. .✓ /'r� #s .a 1i,, instrunent and "I He uol affixed is the corpora!, set, co sdN
Its k Jack G. Wytbd, Professional fond Sswyor ( t rar0orptian.
g ., $- 'lit- q4a• ®\x UAificaM NraJer 7405 f IN WITNESS WHEREOF I Mse Mre unto see awn,; pr.n
kfY F o al/ixW my official seal OneCoy and ye If t bone^,w+hen
w\ y_.��Sltel`.aA
LA
41 4fagf• `A ' �xf�h .fr k in • r :ti S1a11 f
—
i ResidLW w dyer iILL
STATE OF WASHWOTON
on
i x des4i"., COUNTY OF KITTITAS
VACQUOR THIS IS TO CERTIFY THAT on this S .a;v
- - r !!J �8—$0 AD s.f.ra me , the a d Mary Sl, a h to ee � , P.
` p i _ gprretl ale a G. utod the
and May S dosdi b me Morn ro a 'be
gyp- IRxeae rho exoftoted the (ertthe •io; Go. if as free oaedgtl ro ere
J I v 't5 ��,sti a4 tW d•'�fa rM useof and s on purposes thenirmelfiioned "olwniory
WITNESS my Ia,d and oMdpl etas tM day snr
Ivan above rrlt%n.
Na1arY R,tlle In end ter the
0. �� W �� - -
g - do �'Ei EKAMINEO A. APPROVED
Z R�L
KNutian This day of A.A' 19"
i '.�
cls
,p �tbfi Resolution up
SORENSEN, claatrresh
u t' 8. / C J a �� 66-6i ATTESTR,sewn �rV
MARION CARTER, Clerk of the Board
HEREBY CERTIFY Chef all State orhe County
-,s an an the property doscrilyd hereon has bean
10
54 _
19
,,yyy__,,,��� is /rt �` o f]► LUCILLE VEENHUIS, County 7msu—
T.
Lt
EXAMIN AND APPROVED
This 1961
7 a
�F- ! D.E.AKINS, by Engineer, Ki tt— mty
'L ��� J �� �� r JJ as vlop.
`
i�a � 1 4a FILED FOR RETARD AT THE REQUEST OF THE
ri J �} fti� � BOARD OF KITTITAS COUNTY COMMISSIONERS
is -�� P AJ day w PiesA AD. 1964
Off ' D \ idD +, Ace on s' 1vI AND RECORDED IN VOLUME __I OF PLATS,
J -/ ON RAGE _ZC., RETARDS OF KITTITAS
CDUNTY, SNINGTW /--
/.t
� IA.ARfON TITER ,Coadyy Audits
�16D1 /J $ • A Vacfllion f nWillitl0il
�i�V�yA Y-00 cep all / / a- DPW-68-6O
Yam? sga�
J/
'a�
/'Is
/ �� 0
SCALE lin-000ft. r.
C,
w /' .� J ,¢ =1 .$ ��`\ •. s . I ran lien. aft
® Con —to rrlp--I I
J �^i /I�� � ..\•`ts � ,� � / � is t5 ..�
17 d
43..41 -. .w.
EXHIBIT 2: 1" Street (Ronald) Vacation Request
Public Works Study Session Staff Report 2026
I .. I3ITTZTglS CDiTNT7�
DEPARTMENT OF PUBLIC WORKS
ROAD VACATION APPLICATION ��
Application for: U Road Vacation $3,888.00 Payment Method: eCheck � ❑Cash
y ❑ Credit Card
Applicant Name N- Permit # Kt) - ab -
Mailing Address ft LPJ 1 LD k l Q0 & uD S;'w
S-5 S,
Phone Number
Email Address^1��1�
EFT
i irk,. ♦ �,t
S e i ' `j - Uri'- DATE STAMP
Please be as accurate as possible. For assistance with the Location or Legal Description of the requested County
Road Right -of -Way Vacation, Applicants or Designated Agents may request Kittitas County Public Works to assist
in this process.
Location of requested Road VacatioC7C,j ee� t �'r v'd ij___' i� 5-]
cvy,d -T-4g pc,--AJ<in$ Io#U $3q I S f— 903
Legal Description:
Vacated from Mile Post
Vacated from end of Driveway at 3S3
to Mile Post
?-S44C� to Driveway at 9 O
Reason for Request:To o fie' ak:, e— cx�v O L
SJ
Additional Comments:
l
I have attached a site map with details of the requested County Road Right -of -Way to be vacated.
❑ I have attached the required signatures of ten (10) freeholders residing in the vicinity of the
requested County Road Right -of -Way Vacation, pursuant to Kittitas County Code 12.10.030.
Applicant Signature Date 2 20 Z ._ _ —
Dept. of Public Works
Prover(Owners named below are requesting to vacate Couny" Right-of-WaN .
Attach a se oarate sheet if needed to provide additional information
Kittitas County Code 12.10.030 requires ten (10) freeholders residing in the vicinity of the requested County
Road Right -of -Way Vacation.
By signing this Petition, I acknowledge the requested County Road Right -of -Way to be useless as part of the
County Road system and the Public will benefit by its vacation and abandonment.
Name Parcel No. Mailing Address Phone Signature
1 eacc- go o0 13� �� a53, gY,3oj3 (�41,4r O"q�-
2
3
4
5
6
7
8
9
10
Reviewers' Notes:
�� Astn fS...Tp rhF p KITTITAS COUNTY
PUBLIC WORKS
4�
R
411 N. Ruby Street, Suite 1
Ellensburg, WA 98926
K1TTITAS COU.NTV. 509-962-7523 / www.co.kittitas.wa.us/public-works /
Payer/Payee: Bailey, Lauri
8381 State Route 903
Ronald WA 98940
Fee Description
Road Vacation
Receipt Number: PW26-00438
Cashier: KRISTIN KINSLEY
Payment Type: CHECK (431)
RD-26-00002 TOTALS:
TOTAL PAID:
Date: 06/25/2026
Fee Amount Amount Paid Fee Balance
$3,888.00 $3,888.00 $0.00
$3,888.00 $3,888.00
$3,888.00
$0.00
Printed 06/25/2026 14:09:00 by Kristin Kinsley Page 1 of 1
EXHIBIT 3: Vicinity Map
Public Works Study Session Staff Report 2026
N
1st STREET (RONALD) ROAD VACATION 2026
0L
BMp 0.00
It
O15�x
CF�S Fs..r �h
__. 0
KITTITAS COUST1 L
EMP 0. 4
a Un
rq
a Ix
x z
a o
IN N
H H
1st Street (Ronald) R(A- AI f"
0.01 0.03 Miles
KittitasrNvIty GIS
This map is for informational purposes only
KITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
PUBLIC WORKS — BOARD OF COUNTY COMMISSIONERS
STUDY SESSION STAFF REPORT
STUDY SESSION DATE: September 14, 2026
TOPIC: Stone Road Speed Revision
ACTION REQUESTED: Direct Staff Prepare Enabling Documents to
Schedule a Public Hearing Receiving the Engineer's
Report on the Speed Reduction of Stone Road
LEAD STAFF:
Joshua Fredrickson
RECOMMENDATION:
Direct staff prepare enabling documents to Schedule a public hearing receiving the
County Engineer's report on the speed reduction on Stone Road
BRIEFING STUVIlVIARY:
• Stone Road is 0.64 miles in length on the west side of Canyon Road
• The County has acquired the property on the west side and south end of Stone
Road for floodplain and habitat purposes
• A project is proposed to meet the floodplain design intent by raising the elevation
of Stone Road
• A reduction in speed will allow for the design to fit within right of way on the east
side of Stone Road and continue to provide access to the parcels
BACKGROUND:
Stone Road is a public road serving both private and public parcels. The roadway begins
at the connection to Canyon Road and does not have an outlet. Beginning in 2019 the
County acquired property on the west side and south end of the roadway. The posted
speed for this dead-end road is currently 50 mph.
DISCUSSION:
Stone Road serves parcels on the west side of Canyon Road. Property on the east side of
the road is privately owned, and parcels on the west side of the road are owned by Kittitas
County. The County acquired the parcels for floodplain management and habitat
restoration. One of the allowed uses is passive recreation. As part of the floodplain
management project, a berm was to be constructed parallel to the roadway. This berm
would limit the ability to provide access. Public Works is proposing to elevate the
roadway. An elevated roadway will meet the purposes of the berm and continue to
provide property access. There is currently 40-feet of right-of-way. With the current use
Public Works is proposing to reduce the posted speed from 50 mph to 35 mph. This
better represents the possible recreation use to the west.
Traffic data was last collected in May 2025. At the time, the 85' percentile speed was
36.75 mph. This is within the industry standard of plus or minus 5 mph of the proposed
posted speed.
FISCAL IMPACT:
Posted sign revision accounted for within the annual Road Fund budget
ATTACHMENTS:
Exhibit 1: Vicinity Map
Exhibit 1: Vicinity Map
N
c
r
KIT r I r S l•QS' ti Tl
Store Road Speed Reduction Map 2026
STONE ROAD
0 0,03 0.05 0.1 Miles
I I f T I I I I
This reap is for informational purposes only
WOODHiOUSE LOOP
i A 5 V A
I•ILLENISBd Nt-,
Kittitat C.tninty OS
KITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
PUBLIC WORKS — BOARD OF COUNTY COMMISSIONERS
STUDY SESSION STAFF REPORT
STUDY SESSION DATE: September 14, 2026
TOPIC: BEAD Broadband Project Update
ACTION REQUESTED: Informational Only
LEAD STAFF:
Josh Fredrickson
RECOMMENDATION:
Informational briefing — no action required by the Board
BRIEFING SUMMARY:
• Kittitas County has previously been awarded two projects for broadband
development
• Federal funding through the Broadband Equity Access and Deployment (BEAD)
program is being made available to Kittitas County for broadband expansion
• Kittitas County is being awarded seven project areas for broadband expansion
through the BEAD program and State funding match
• The County uses private broadband partners to build, operate and maintain the
networks.
• The County also received long-term public infrastructure value.
BACKGROUND:
The COVID-19 pandemic exposed major weaknesses in rural broadband. As work,
school, health care, and daily services moved online, many households in Kittitas County
did not have infrastructure capable of supporting multiple simultaneous users. In
response, the County Commissioners made broadband expansion a priority and pursued
state and federal funding opportunities beginning in 2021.
Early federal recovery funding moved relatively quickly and supported two major County
projects administered through the Washington State Public Works Board (PWB) and the
Washington State Broadband Office (WSBO). Funding for these projects is $3.6 million
and $11.4 million, respectively.
Additional funding for deployment of broadband services to areas within the County has
been made available through the National Telecommunications and information
Administration (NTIA) Broadband Equity Access and Deployment (BEAD) Program.
BEAD is administered by the Washington State Broadband Office (WSBO) within the
Washington State Department of Commerce. The BEAD process moved more slowly
than the earlier recovery -funded programs and required Kittitas County to submit
separate applications, business plans, and construction cost estimates for each project
area. Washington State also made state funding available to cover the required public
match for eligible public -entity applicants.
DISCUSSION:
Kittitas County does not intend to operate these networks as a retail internet service
provider. Instead, the County has contracted with experienced broadband companies to
support construction, operations, and service delivery:
• Lightcurve - selected for the existing PWB and WSBO fiber projects.
• Inland Cellular, LLC - selected as the County's broadband partner for the seven
BEAD project areas.
A small number of broadband -serviceable locations in six BEAD project areas were
provisionally assigned to low -earth -orbit satellite providers, including Amazon Kuiper
and SpaceX, where Inland Cellular could not serve the location through the County's
proposed fiber or wireless design.
Area
Applicant
BEAD Outlay
State Match Private
Match Total Cost
21
Kittitas County
$3,945,167
$1,315,056
$5,260,223
112
Kittitas County
$2,961,092
$981,031
$3,948,123
156
Kittitas County
$3,619,809
$1,206,603
$4,826,412
177
Kittitas County
$4,667,329
$1,555,776
$6,223,105
199
Kittitas County
$4,740,174
$1,580,058
$6,320,232
22
Kittitas County
$1,591,668
$530,556
$2,122,224
227
Kittitas County
$3,156,018
$1,052,006
$6,118,700
Final design adjustments are underway for the BEAD project. Contracts with WSBO are
to be executed and returned to WSBO by October 8, 2026. Project areas are reviewed
under the NEPA, Section 106 of the National Historic Preservation Act and Governor's
Executive Order 21-02. WSBO has contracted with a consultant to conduct these reviews
for the BEAD projects. With the state -funded match included, the seven County BEAD
project areas represent more than $34 million in broadband investment.
The County's broadband strategy provides value beyond extending retail internet service
to rural homes and businesses. As part of the negotiated arrangement with Inland
Cellular, Kittitas County will receive 12 strands of fiber throughout the project network
for public use. These strands can support public safety, telemetry, communications,
intergovernmental connectivity, and other future County applications.
The current briefing estimates the value of this County fiber at approximately $10 million
to $15 million, with a more precise appraisal to be completed after final design and
construction costs are known. Inland Cellular is expected to maintain the fiber for its
useful life under the negotiated Irrevocable Right of Use (IRU) arrangement.
FISCAL IMPACT:
BEAD grant and State Match funding includes an allocation for administrative and
consultant services.
ATTACHMENTS:
None
KITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
PUBLIC WORKS — BOARD OF COUNTY COMMISSIONERS
STUDY SESSION STAFF REPORT
STUDY SESSION DATE: September 14, 2026
TOPIC: 6-Year Transportation Plan Update
ACTION REQUESTED: Informational Only
LEAD STAFF:
Josh Fredrickson
RECOMMENDATION:
Informational briefing — no action required by the Board
BRIEFING SUMMARY:
• Public Works updates the Transportation Improvement Plan (TIP) each year to
address transportation needs within projected funded amounts
• Per RCW 36.81.121 Public Works is required to publish a 6-Year Transportation
Improvement Plan prior to the adoption of the budget.
• Public comment was solicited July 15 through August 5, 2026
• Project funding sources include Road Fund and grant sources
BACKGROUND:
Public Works has been working to update the 6-Year Transportation Plan, as required by
RCW 36.81.121. The Plan highlights capital improvement projects Public Works is
planning through the year 2032. The Plan is broken down by design and construction
phases, as well as local and grant funding. Funding sources are identified to help
calculate the impact to the road fund.
Public Works solicited public comment on the six -year plan between July 15 and August
4, 2026. This was done with a press release, posting information on the Public Works
website as well as social media post.
DISCUSSION:
Public Works has updated the 6-Year Plan to better represent the County's ability to fund
road improvement projects. Last year, projects were not included in the plan if funding
was not secured and was instead included on a Capital Improvements List to show needs
which would be completed if funding became available. In addition to funded projects,
this year Public Works has included placeholders for projects with grant funding
opportunities that are on a regular funding cycle. These placeholders identify the funding
source and type of project which meets funding criteria. Only funding opportunities that
are utilized each cycle have been included.
Public comment received during the solicitation period included requests for
improvements at the intersection of Kittitas Highway and No. 6 Road; pavement
improvement on Passmore Road; and a request for no roundabouts on County Roads.
The County Road Safety Plan identifies improvements for Kittitas Highway and No. 6
Road as priority 1 in the plan. The Road Safety Plan is the basis for application to the
State for funding through the Highway Safety Improvement Plan (HSIP). Project funding
is based on State allocation to the HSIP. The six -year plan includes projects for funding
received through the HSIP. Passmore Road is currently identified as a Primitive
Roadway with a gravel surface. Primitive roads are not part of the County's primary road
system. Maintenance is performed including grading the roadway on an annual basis.
FISCAL IMPACT:
The 6-Year Transportation Plan will help set the Public Works budget for 2027.
ATTACHMENTS:
Exhibit l: Draft 6-Year Transportation Improvement Plan for 2027-2032
Exhibit 1: Draft Six -Year Transportation Improvement Plan 2027-2032
■ME
KITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
PUBLIC WORKS — BOARD OF COUNTY COMMISSIONERS
STUDY SESSION STAFF REPORT
STUDY SESSION DATE: September 14, 2026
TOPIC: Bowers Field Airport Update
ACTION REQUESTED: Information Only
LEAD STAFF:
Josh Fredrickson
RECOMMENDATION:
Informational briefing — no action required by the Board
BRIEFING SUMMARY:
• Bowers Field is a County owned public use airport
• Capital projects are underway and proposed for the airport
• Funding to the airport includes grants, lease payments and County General Fund
transfers
BACKGROUND:
Bowers Field (ELN) is a County -owned public -use airport serving Kittitas County,
Central Washington University, local businesses, emergency -service operations,
recreational aviation, and the broader regional transportation system. Public Works is
responsible for airport administration including lease administration, regulatory
compliance, and coordination with Federal and State aviation agencies and supporting the
County Airport Advisory Committee (AAC). Public Works has been coordinating several
projects and lease updates, an update to the Board of County Commissioners is being
presented.
DISCUSSION:
Kittitas County entered an interlocal agreement on September 17, 2024 with City of
Ellensburg and Central Washington University for the exchange of real property. The
exchange includes a hangar owned by the County, a building at the airport owned by the
City and a parcel near Helena and 181h St. The exchange of real property benefits long-
term local and regional public interests of all parties. Documentation has been prepared
and closing on the exchange is anticipated mid -September.
Capital projects are funded primarily through funding allocated by the Federal Aviation
Administration (FAA). The current project is the construction of a hangar taxilane project
V
which will allow for hangar space to be developed. The recent completion of a wetland
mitigation site met the requirement for mitigation of wetland impacts of a proposed
project. Future work will include items on the Capital Improvement Plan. The largest
capital project proposed is the parallel taxiway project. This project has an estimated
design and construction cost of $15 million. Funding for capital projects is typically
supported by the Federal Aviation Administration (FAA) through an annual allocation.
This allocation is programmed. For larger projects the FAA may use discretionary
funding. A local match, typically 10%, is required. The parallel taxiway is proposed to be
designed in 2027 and construction beginning in 2029.
In addition to the capital plan, work supporting ongoing maintenance and operations
continues. Efforts to evaluate the current wetland and determine boundaries are
underway. This will help inform permitting and permitted work to help manage habitat.
In addition, the County leases land for hangar development as well as business
development. Agricultural grazing leases have been in place to help support the airport.
The current agricultural grazing leases will expire this year. A call for bids is being
prepared and has been discussed and supported by the AAC.
FISCAL IMPACT:
No fiscal action is requested with this update.
ATTACHMENTS:
None
KITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
PUBLIC WORKS — BOARD OF COUNTY COMMISSIONERS
STUDY SESSION STAFF REPORT
STUDY SESSION DATE: September 14, 2026
TOPIC: Flood Control Zone District 2027 — 2032 Capital
Improvement Plan
ACTION REQUESTED: Informational
LEAD STAFF: Arden Thomas
RECOMMENDATION: Informational.
BRIEFING SUMMARY:
• Each year, the Flood Control Zone District (FCZD) updates its 6-year Capital
Improvement Plan (CIP). This 6-year Capital Improvement Plan informs annual
budget development, the FCZD work program, and longer -term planning efforts.
• The FCZD CIP is also incorporated into County comprehensive planning
documents, and each annual update is posted on the FCZD website.
• Key FCZD projects that are underway include the Whiskey Creek Siphon Project,
the Lower Kittitas Reach Floodplain Reconnection Project, and the Mercer Creek
Flow Conveyance Restoration Project.
• The FCZD works to strategically leverage grant funding. Local funding has also
been critical for advancing local flood -risk reduction priorities.
BACKGROUND:
In 2020, Kittitas County prepared its first 6-year Capital Facilities Plan for the Flood
Control Zone District (FCZD CIP). The FCZD CIP is updated annually. This planning
document informs annual budget development, funding request applications, the FCZD
work program, and longer -term planning efforts. The FCZD CIP includes a project map,
project information sheets, and a six -year funding plan. Projects are identified through
hazard mitigation planning, reach- and subbasin-scale assessments, flood hazard
modeling efforts, and staff recommendations.
Key FCZD projects that are underway include the Whiskey Creek Siphon Project
(implementation), the Lower Kittitas Reach Floodplain Reconnection Project (design,
with site cleanup and building demolition underway), and the Mercer Creek Flow
Conveyance Restoration Project (design).
DISCUSSION:
In 2027, the Flood Control Zone District forecasts capital expenditures of approximately
$3.3 million, with just over 47% of these costs funded through grants. Projects with
Page 1 of 3
PUBLIC WORKS BOARD OF COUNTY CON IISSIONERS WORK SESSION STAFF REPORT
strong salmon and steelhead benefits, such as the Lower Kittitas Reach Floodplain
Reconnection Project, are very successful in securing external grant funding. To date, this
project has been nearly fully grant funded. Additionally, funding made available by the
Washington Military Department, Emergency Management Division, in response to the
2025 flood event is being used to advance the Repetitive Loss Area Analysis (Project
#la) and address flow conveyance needs along Naneum Creek (Project #14d).
Local funding has also been critical for advancing local flood -risk reduction priorities,
including providing funding to the City of Ellensburg for its Reecer Creek levee project
and funding the design and construction of the Whiskey Creek Siphon Project.
Effective project partnerships help enable the FCZD to advance a robust project portfolio.
These partnerships have included the Kittitas County Conservation District (Whiskey
Creek Siphon), Mid -Columbia Fisheries Enhancement Group (Lower Kittitas Reach
Floodplain Reconnection and Mercer Creek Flow Conveyance Restoration), and the City
of Ellensburg (Whiskey -Mercer Remapping and Whiskey Reroute for Flood Control and
Fish Passage).
FISCAL IMPACTS:
The 6-Year Work program is used to formulate our annual work program and budget.
ATTACHMENTS:
Exhibit 1: Flood Control Zone District 2027-2032 Capital Improvement Plan.
Page 2 of 3
PUBLIC WORKS BOARD OF COUNTY CONM4ISSIONERS WORK SESSION STAFF REPORT
EXHIBIT 1: FLOOD CONTROL ZONE DISTRICT 2027-2032 CAPITAL
IMPROVEMENT PLAN
Page 3 of 3
PUBLIC WORKS BOARD OF COUNTY CONMSSIONERS WORK SESSION STAFF REPORT
0
z,
I ..
FLOOD COi, ROL
ZONE DISTRICT
CAPITAL IMPROVEMENT
PLAN
�
k ,
61 It ; -
2027=2032
IfTiTli=S COUNTY Kittitas County Public Works
INTRODUCTION
Every year, the Kittitas County Flood Control Zone District ("District") updates the 6-year Capital Improve-
ment Plan. Given the complexity of flood hazard planning, engineering, environmental permitting, and con-
struction, the Flood Control Zone District schedules projects an additional five years behind the first budget
year. The planning schedule includes programmed funding amounts and sources along with project forecast
expenses. The schedule identifies the various projects beginning in the first budget year (2027) extending to
the last year in program (2032).
This plan is organized into three major components:
1. Map identifying the various projects located around the County.
2. Project specific sheets listing specific project information including title, project description, project status,
photos and funding sources.
3. The six -year funding plan.
ACRONYMS
AOP
Aquatic Organism Passage (Federal Highways)
CIP
Capital Improvement Project
CRS
Community Rating System
CTP
Cooperating Technical Partners Program Washington
DOE
State Department of Ecology
EWC
Ellensburg Water Company
EMD
Washington State Emergency Management Division
FCAAP
Flood Control Assistance Account Program
FCZD
Flood Control Zone District
FEMA
Federal Emergency Management Agency
SRFB
Salmon Recovery Funding Board
WNC
Wilson-Naneum-Cherry Watershed
YBIP
Yakima Basin Integrated Plan
A
Kittitas County
2027 - 2032
Sic Year Floodplains Improvement Plan
Rt)IVALD
47
RO YN 4 r ([ UM ;2lf.S
21 16
C'LE ELUA1T .
., SOUTH
C: LE
ELUA1ax,t.
f ry
G►a Fr'JIi C; F rf
-� Et
ff It-*Rf PR?f•- IF
� ' :• r,f � � L' � is
GI
,r
Projects
la- Flood Hazard Risk & Repetitive Loss Program
5- Lower Kittitas Reach Floodplain Reconnection
8- CTP Flood Studies (Multiple Locations)
10- Whiskey Creek at EWC Siphon
12- Whiskey Creek Reroute
14b- Flow Conveyance Restoration, Mercer Creek
14c- Flow Conveyance Restoration, Whiskey Creek
14d- Flow Conveyance Restoration, Naneum Creek
16- Crystal Creek Conveyance Project
18- Hazard Mitigation Plan Update N
21- CRS Critical Facility Compliance
22- Wilson Creek Reroute
23- Wilson-Naneum Alluvial Fan
73BLE gfOLINTAIN rtiy f J .
Y }
�Z
C A S C A 0 E %P-
t _ r
Tla }
t. 23
14 �
BIORP��,� It
i \T I\T A S v L L E Y
14c
97.1 0 ►. ;r f' q S V .A L L
`= 12 2 14d
on
Tl14bNSBtTRG
i
05
,0 1 2 4 6 8Miles
Basis for Project: Kittitas County Hazard Mitigation Plan
PROJECT DESCRIPTION
Unincorporated Kittitas County has 7 repetitive loss areas. Four of these areas are along the Yakima River,
two are along the Teanaway River, and one is along the Middle Fork Teanaway River. The Repetitive Loss
Area Analysis will focus on the individual parcel and structure level and enable Kittitas County to provide site
-specific information to private landowners about potential property protection measures and their suitability
given site -specific flood risk (such as building relocation, building elevation, building retrofit, and property
acquisition and building demo), and collect information from property owners about their interested in these
protection measures.
FLOOD IMPACTS
Reduce impacts and costs associated with frequently flooded properties.
SCHEDULE FUNDING
• 2027: Repetitive Loss Area Analysis State: County Risk and Needs Assessment Grant
Program (EMD)
r44
+ i 1.
For more project information contact Arden Thomas @ 509-962-7523 or arden.thomas@co.kittitas.wa.us
Basis for Project: Yakima River Corridor Plan
PROJECT DESCRIPTION
The failing Hansen Pit Levee and private berm located on Flood Control Zone District acquired property will
be replaced by setback flood protection (berms and Stone Road elevation). Levee removal restores ecological
functions to the purchased properties, will reduce flood risks off -site and will reduce long-term District opera-
tion and maintenance costs associated with the unsustainable and ineffective levee and berm. This project will
also provide open space recreation and improve fish and wildlife habitat conditions.
FLOOD IMPACTS
Flood risk reduction and improved floodplain function
SCHEDULE
• 2027: Final Design & Permitting
• 2028: Construction
• 2029 - 2032: Adaptive Management
Ap
Ab
_ ... ,y
l il, i
FUNDING
• State: Floodplains by Design
• State: Yakima Basin Integrated Plan
• Local: FCZD Levy
For more project information contact Arden Thomas @ 509-962-7523 or arden.thomas@co.kitdtas.wa.us
Basis for Project: Kittitas County Hazard Mitigation Plan
PROJECT DESCRIPTION
Technical studies with updated hydrologic and hydraulic flood risk modeling will improve information about
flood risk and form the basis for floodplain management and flood risk reduction project design. Currently, the
Whiskey -Mercer flood risk model and FEMA map update request is being completed in partnership with the
City of Ellensburg. Future technical studies will also consider incorporating channel migration risk as part of
the technical assessment.
FLOOD IMPACTS
New construction built to appropriate flood risk reduction standards and landowners will have better flood risk
information.
SCHEDULE
• 2027: Complete Whiskey -Mercer
• 2030: Teanaway River
• 2032: Manastash Creek
i
FUNDING
• Federal: Community Technical Partnership
• Local: FCZD Levy
For more project information contact Arden Thomas @ 509-962-7523 or arden.thomas@co.kitdtas.wa,us
Basis for Project: Wilson-Naneum-Cher Assessment
PROJECT DESCRIPTION
Where the EWC canal crosses Whiskey Creek, the creek currently flows through a culvert beneath the canal.
The culvert does not have enough capacity to handle high flows, causing water to back up behind the canal.
The proposed EWC siphon project will change this configuration by routing the canal through a siphon be-
neath Whiskey Creek. The siphon will work with flow conveyance improvements at the upstream Bender
Road crossing to reduce flooding in the area. Together, these improvements increase flood conveyance, sepa-
rate the canal and creek, and remove a barrier to fish passage.
FLOOD IMPACTS
Decreased flooding along Whiskey Creek
SCHEDULE FUNDING
• 2027: Construction Local: FCZD Levy
• 2028/2029: plant maintenance
71 Z
cdip
<.
N__all
I-- _ 1- 1 i
'.w
n
For more project information contact Arden Thomas @ 509-962-7523 or arden.thomas@co.kittitas.wa.us
Basis for Project: Wilson-Naneum-Cher Assessment
PROJECT DESCRIPTION
This potential project proposes to reroute Whiskey Creek into Reecer Creek within the City of Ellensburg's
Reecer Creek floodplain and levee system by constructing a fish -passable bridge along the BNSF railroad with
adequate capacity to also convey flood flows at the 100-year flood event. This project will reduce flooding in
the West Ellensburg neighborhood and adjacent industrial areas, decreasing inundation along the fringes of the
floodplain near the BNSF railroad and provide fish passage into Whiskey Creek.
FLOOD IMPACTS
Reduced flooding in the West Ellensburg neighborhood and adjacent industrial areas.
SCHEDULE
• 2027-2028: Final Design & Permitting
• 2029: Construction
FUNDING
• Federal: Federal Highways (Grant Request)
• Local: FCZD Levy
�9b
•ram
'+
�
{�� ^ t
n1.
f
V � it Il 4
Legend
OModel Boundary
-1 Levee Failure
Vanr
Aft 2 Features
r
Rerouted Channel,
Culverts Maintained
Proposed Levee Design
Mill Ditch Grading
Flood Swale
0 i300 1,600
® Feet
For more project information contact Arden Thomas @ 509-962-7523 or arden.thomas@co.kittitas.wa.us
Basis for Project: Whiskey -Mercer Flood Modeling
PROJECT DESCRIPTION
This project, advanced in partnership with Mid -Columbia Fisheries Enhancement Group, will improve water
quality and stream habitat and reduce flood risk along a portion of Mercer Creek west of Railroad Avenue.
Project components include floodplain grading, invasive tree removal, and native plant restoration.
FLOOD IMPACTS
Decreased flooding extents upstream and downstream of the Railroad Avenue crossing on Mercer Creek.
SCHEDULE FUNDING
• 2026: Surveying, Modeling, Landowner Outreach • State: Centennial Clean Water
• 2027: Finalize Preliminary Designs • Local: FCZD Levy
• Construction: TBD
For more project information contact Christian Preszler @ 509-962-7523 or hristian.preszler@co.kittitas.wa.us
Basis for Project: Whiskey -Mercer Flood Modeling
PROJECT DESCRIPTION
An inset floodplain will be constructed and crack willow will be removed to improve flood storage and con-
veyance along approximately 2,300 linear feet of Whiskey Creek between Bowers Road and Bender Road
through the construction of an inset floodplain and removal of invasive crack willow plants. This project will
better manage flood risk within the City of Ellensburg Urban Growth Area and improve riparian and stream
conditions.
FLOOD IMPACTS
Decreased flood impacts at Bender Road and in developing area along Whiskey Creek.
SCHEDULE FUNDING
• 2027: Final Design & Permitting Local: FCZD Levy
• 2028:Implementation
For more project information contact Arden Thomas @ 509-962-7523 or arden.thomas@co.kittitas.wa.us
Basis for Project: Kittitas County Hazard Mitigation Plan & Wilson-Naneum-Cherry Assessment
PROJECT DESCRIPTION
Flood assessment and mitigation plan for approximately 3,100 feet of Naneum Creek between the Cascade
Irrigation District Canal and Vantage Highway, where significant flooding occurred during the 2023 and
December 2025 flood events.
FLOOD IMPACTS
Develop understanding of flood risk to guide future flood risk reduction efforts
SCHEDULE FUNDING
• 2026: Survey, LiDAR, Modeling State: County Risk and Needs Assessment Grant
• 2027: Assessment and Mitigation Plan Program (EMD)
�• - -- _ -
J�
-' Ap roximete Area of StudWn
l Vantage Hwy
1 .• ti. A;.
+ ■, Sri d c..+ �=•``ti. �A
For more project information contact Samantha Cox @ 509-962-7523 or samantha.cox@co.kittitas.wa.us
Basis for Project: 2019 Crystal Creek flood study
PROJECT DESCRIPTION
Crystal Creek flood conveyance will be increased so that flood risk is decreased. Project to be selected based
on evaluation of 2019 flood study and with input from Cities of Roslyn and Cle Elum.
FLOOD IMPACTS
Decreased flooding along Crystal Creek
SCHEDULE
FUNDING
• 2029: Project Selection • TBD
• 2030: Final Design and Permitting
• 2031:Implementation
Basis for Project: Kittitas County Hazard Mitigation Plan
PROJECT DESCRIPTION
Kittitas County last updated its Multi -Jurisdictional Hazard Mitigation Plan in 2025. This plan must be updat-
ed every 5-years. An up-to-date mitigation plan that has been approved by the Federal Emergency Manage-
ment Agency (FEMA) is required to be eligible for mitigation grants, such as FEMA's Pre -Disaster Mitigation
Grant Program (PDM) and Hazard Mitigation Grant Program (HMGP) .
FLOOD IMPACTS
Identify key flood needs and maintain eligibility for Federal funding sources.
SCHEDULE
FUNDING
• 2029-2030: Plan Update • State: Washington State Department of Military
• Local: FCZD Levy
For more project information contact Arden Thomas @ 509-962-7523 or arden.thomas@co.kitdtas.wa.us
Basis for Project: State & FEMA Community Assistance Visit
PROJECT DESCRIPTION
Address critical facility flood risk (Fire District No. 7 station No. 73) to secure long-term continuity of opera-
tions during flood emergencies and remaining in good standing with the Community Rating System (CRS)
and National Flood Insurance Program (NFIP).
FLOOD IMPACTS
Ensure emergency services can be provided during flooding conditions.
SCHEDULE FUNDING
• 2026: Update to include action in Hazard Mitiga- Local: FCZD Levy
tion Plan
• 2028: Additional feasibility investigation
For more project information contact Arden Thomas @ 509-962-7523 or arden.thomas@co.kitbtas.wa.us
City of Ellensburg Staff Recommendation
PROJECT DESCRIPTION
The west branch of Wilson Creek will be relocated from its current location as a stream -side ditch along Brook
Lane to Central Washington University property, which can accommodate both the stream and an associated
floodplain. This re -alignment will address frequent (50% annual chance) flooding, associated water quality
impacts, and improve aquatic and riparian habitat, while also providing opportunities for public engagement
and enjoyment.
FLOOD IMPACTS
Flood impacts will be reduced in the Brook Lane neighborhood of Ellensburg.
SCHEDULE FUNDING
• 2031: Project Design and Permitting • State: Centennial Clean Water Funding (Potential)
• 2032: Implementation • Local: FCZD Levy
Approximate
EzisWv ^--"----
Flood Un
E iM Ave
Wilson ere&
Alipnmem
Central
Washmoon
Unrvarsq
t.
one
Vdap
Apace
s
Flow Sd
For more project information contact Arden Thomas @ 509-962-7523 or arden.thomas@co.kittitas.wa.us
Basis for Project: Wilson-Naneum-Cher Assessment
PROJECT DESCRIPTION
Evaluate risks and identify mitigation and management strategies to address episodic sediment deposition
along Wilson-Naneum Alluvial Fan. This strategy will be informed by natural sediment transport processes,
feasibility of an ongoing sediment management program, the potential for capital flood alleviation project, and
the role of landowner stewardship.
FLOOD IMPACTS
Manage potential for infrastructure risk associated with flood related sediment mobilization and deposition.
SCHEDULE
• 2028: Assessment
• 2029: Landowner Outreach
• 2030: Project Design and Permitting
FUNDING
• State: FCAAP (Potential)
• Local: FCZD Levy
For more project information contact Arden Thomas @ 509-962-7523 or arden.thomas@co.kittitas.wa.us
FUNDING PLAN SUMMARY
(costs are shown as thousands)
SUMMARY: 6-YEAR PROGRAM REVENUE,
COSTS AND ENDING FUND AMOUNTS
2027
2028
2029
2030
2031
2032
FCZD CAPITAL PROGRAM PROJECT
COSTS
3,298
15,996
4,076
681
1,142
2,162
ADMINISTRATION AND
OPERATIONS COSTS
500
500
500
734
804
863
500
525
551
579608
638
_ADMINISTRATION
TECHNICAL ASSISTANCE
!SD
50
55�
55
�60
60
STREAMFLOW MONITORING
10
10
_
15
15
20
_ 20
LEVEE MAINTENANCE
_ _-- _
PROPERTY MAINTENANCE
10
15
_ 15
61
20
___,___,__M,__21
INFLATION _ _
0
-l10
18
39
86
113
TOTAL ANNUAL COSTS
3,798
16,496
4,1
734
1,946
3,025
TAX LEVY
1,000
1,000
1,000 1,000
47
11000
1,000
______.�50
OTHER INCOME
43
`
____ . _ 48
PERMITS
GRANTS / COST SHARE
_
25
1,533
_
26
14,616
27 27
3,085 330
28
603
1,6791
29
1,541
2,620
TOTAL ANNUAL INCOME
Z601
15,686
4,1S7 1,405
TOTAL (COST) INCOME FOR YEAR l -1,197
BEGINNING FUND AMOUNT 3,000
ENDING FUND AMOUNT 1,803
_ -_-810
1,803
993
-� -4143
993
574
574
1,244
- 267
2,244
977
_ _ -405
977
572
..
KITTITAS COUNTY FLOOD CONTROL ZONE 2027-2032
SIX YEAR CAPITAL IMPROVEMENT PLAN
a
° ° o
x z z z
n n m w m a o
N N o o 0 N N m m m
o 0 0 0 0 0 0
Y N N N N N N N Pe
z x
•n m m
o a o
N N N
111a
FLOOD HAZARD RISK & REPETITIVE LOSS PROGRAM c vmwi4e
9 91
203>: MO,M{« [caf b•, ltul 4.102t: h.•se 3 b[n,•M �,r,kpn•n[
05
LOWER KITTITAS FLOODPLAIN RECONNECTION Yakima AFer
SRFB/IP/FbD ILO 325 1 750 1 13900 50 1 1 50 1 1 50
zon-2axr m,r
RB
FLOOD STUDIESxm Gmegl
CTP 1 20 1 90 1 1 20 90 20 1 90
zozz:c>n9nn Wnnw+n«ce, aLvwaNaow:reuu..•rLi«r.2ozo: w,nn.>_�.zaaz:w
N•rvv
010
WHISKEY CREEK AT EWC SIPHON wit
Private 1275 20 10 10
m:n,w M1m,l ccnw«n:•. •!innnauc•ruil.n mrM:nt •rA,SM•n n,n «au;a airier
W r•gacmrcwnwt 9wcc.nnnea[wn�,kwcr••vvr:ma swn•n.
1112
WHISKEY REROUTE FOR FLOOD CONTROL AND FISH
PASSAGE
wx[
Federel Highways,
RCO
263
1DS2
800
�74P0
10
10
10
1aZ> fine! Mf�M artl P•rmMiry, 2029: Cm,s.un�m.2a3C-2033 M.Inun,n:e
_
N14b
FLOW CONVEYANCE RESTORATION - Mercer Creek
WNc
Ec.IDJV103 310 12 36 12 38 10
MCf-KC)Mf«nND-b4rt«•[x•lenagoie:[.m,M[nan[•,M N•n•rG«kvnncn[,ilr•W /v
ProHtt°•fitn
N14c
FLOW CONVEYANCE RESTORATION-IAi i- Crank wuc
SSS SW 20 20 20
wnuwrG..•rw.-w..r•e:•: t.w.. [•t•.•nwae. M3):fm•! ce,-tn.na P•.m:n:rq. zaa:
PnI•c[imqur+
N34d
FLOW CONVEYANCE RESTORATION - NoneumCrcek
wNc
EMD 64-5
Amwmcr.•k: zax>ceM.ov.N a.,isr.
1136
CRYSTALCREEKCONVEYANCE PROJECT
cw,Icreek
TBD 1 50 S00 20
!mpemn[arorer[ia«uue,nrwtncmencr«kcm n.q
N18
HAZARD MITIGATION PLAN UPDATE
counrywoe
Det. Of MII. 50 75
tn• Lw!iHwi:an:9n.i xan.a ue:«fwn n.n «,a, u w w•x•a •wy sy.m.
N21
CRITICAL FAOLTTY COMPLIANCE yakima Am,
50
zoxe: wstrwn a r.rnniu: vm»,
N22
WILSON CREEK REROUTE
Wiisvnoeek
Centennial Clean
Water
120
250
750
LeKK•u Winm Ge4i�trwa 4« nnM[r
N23
WILSON-NANEUM ALLUVIAL FAN Iu'N-
CTP or FCAAP 1 200 SO 200 100 1501 500 250
342t:N«vawe,, pr k,Yron•MfMmi,cK onJP3J hi•riry Irol«n, 2029:1v,lown,r
Sfew,nmlp lro3+wn. a930:Pre•a DeaFp.•n)PmmininL MllaC33:lmq,mn
TS
CAPITAL PROGRAM ANNUAL TOTAL (LOCAL AND NON -LOCAL AMOUNIDENTIFIED 1765
1532.5
1340
14190 935 2910
322
303 538
540 1340
CAPITAL PROGRAM COSTS WITH 3% ANNUAL INFLATION 1765
1532.5
1380.2
1461E 991.1 3084.E
350.98
.82
330.27 539.84 602.5E
621 1541
Lisa Godden
From: Kittitas County Commissioners Office
Sent: Monday, September 14, 2026 12:13 PM
To: Brett Wachsmith; Laura Osiadacz; Jeff Leichleiter; Josh Fredrickson
Cc: Lisa Godden
Subject: FW: Sep 14 2026 PW study sssion public comments
Public Works Study Session Comment for the record.
Lisa please include with your minutes. Thank you!
Office Administrator I Kittitas County Commissioners Office
Office Hours 7:30 — 4:00 pm
205 West Fifth Ave Suite #108
Ellensburg, WA 98926
509-962-7508 (Office)
509-962-7679(Fax)
htti�://www.co.kittitas.wa.us/
From: pat kelleher <psk98926@yahoo.com>
Sent: Monday, September 14, 2026 10:36 AM
To: Kittitas County Commissioners Office <bocc@co.kittitas.wa.us>; Josh Fredrickson
<josh.fredrickson@co.kittitas.wa.us>; pat kelleher <psk98926@yahoo.com>; Brian Kelly <bkelly@kvnews.com>
Subject: Sep 14 2026 PW study sssion public comments
CAUTION: This email originated from outside the Kittitas County network. Do not click links, open
attachments, fulfill requests, or follow guidance unless you recognize the sender and have verified the
content is safe.
DISCUSSION:
Stone Road serves Pare is on the west side: of Canyon Road. Pn)pert X can the cast side of
the road is privately owned, and parcels on the west side of the read are owned by Kittitas
County, The County acquired the parcels for floodplain nIanagemznt and habitat
restoration. One of the allowed uses is passive recreation, As part of the floodplain
management project, a berm was to be constructed parallel to the roadway. This bem..
would limit the ability to provide access. Public Works is proposing to elevate the
roadway. An elevated roadway will meet the purposes of the berm and continue to
Currently, there is no legal public access to the county -owned floodplain for passive recreation. Meanwhile, the
unauthorized crossing at Hanson Pits creates an attractive nuisance and a potential public -safety concern.
The elevated -roadway project should include:
• Gating and permanently closing the unauthorized crossing.
• A designated vehicle entrance from Stone Road.
• A safe, appropriately sized parking area.
• A marked trail connecting the parking area to Hanson Pits.
• Legal public access to the county -owned floodplain for walking, wildlife viewing, fishing, and other passive
recreation.
This approach would replace unsafe, unauthorized access with a controlled public -access point that protects the
floodplain while allowing the public to enjoy county -owned land
RIB FlNG L INI.� RY,
Kittitas County b&s r��viou �i been awarded mo projeci for �A dr�
vela nim
• edt*ra funding through the Broadband Lquity Access and DeP1oN-,n1cnt (13
warn Is being nude avaliiab to .ittitaN `aunt . or broadband ex a'r�si��t
• Kittitas County is- being avvardcd. seven project areas for broadband eNpansll
through the BLAD pr grarti and State funding match
he County uses private broadband. partners to build, operate and maintaln t
# 11w Countyalso received ong-teen public in structary � alue,
Kittitas County should never have entered the broadband business. Public utility districts are specifically authorized to
provide broadband infrastructure, and private companies are available to deliver broadband service.
The County's role in applying for and administering state and federal broadband grants risks becoming a "leaking
bucket" —absorbing staff time and public resources without those costs being clearly identified. In the age of Starlink and
other rapidly evolving technologies, publicly funded broadband infrastructure may no longer be competitive or cost-
effective under the traditional state and federal grant model.
Please provide a complete accounting of all direct and indirect costs currently incurred by Kittitas County in support of the
broadband program, including:
• County employee salaries and benefits attributable to the program
• Staff hours spent on grant applications, administration, reporting, contracting and oversight
• Legal, engineering and consulting expenses
• Travel, equipment, supplies and other administrative costs
• County funds advanced while awaiting grant reimbursement
• Required local matching funds
• Ongoing maintenance, operating or financial obligations
• Any County -owned infrastructure or property committed to the program
• Any grant expenses that have been disallowed or are not reimbursable
These costs should be reported separately from grant -funded construction expenditures so the public can clearly
understand how much County money and staff capacity are being used to support this program.
Number 6 Road
Public comment received during the solicitation period included requests for improvements at the intersection of Kittitas
Highway and No. 6 Road; pavement improvement on Passmore Road; and a request for no roundabouts on County
Roads. The County Road Safety Plan identifies improvements for Kittitas Highway and No. 6 Road as priority 1 in the
plan. The Road Safety Plan is the basis for application to the State for funding through the Highway Safety Improvement
Plan( HSIP). Project funding is based on State allocation to the HSIP. The six -year plan includes projects for funding
received through the HSIP. Passmore Road is currently identified as a Primitive Roadway with a gravel surface. Primitive
roads are not part ofthe County' s primary road system. Maintenance is performed including grading the roadway on an
annual basis.
Kittitas County has failed to perform even the most basic safety work at the intersection of Kittitas Highway and No. 6
Road, including clearing vegetation and other obstructions from the public right-of-way to improve sight distance.
Clearing the right-of-way should happen immediately, but it is not a complete solution. The County should begin planning
and securing funding for a roundabout to reduce vehicle speeds and lessen the severity of crashes. Roundabouts have
worked successfully on Bullfrog Road and in comparable traffic settings near Mattawa and Quincy.
The danger at this intersection is known and foreseeable. The County has been put on notice. If officials continue to delay
meaningful safety improvements, they must accept responsibility for the consequences of that decision.
AIRPORT
BRIEFING SUMMARY:
• Bowers field is a County owned public use airport
• Capital projects are underway and proposed for the airport
• Funding to the airport includes grants, lease payments and County General fund
transfers
Capital projects are funded primarily through funding allocated by the Federal Aviation Administration (FAA). The current
project is the construction of a hangar taxilane project which will allow for hangar space to be developed. The recent
completion of a wetland mitigation site met the requirement for mitigation of wetland impacts of a proposed project. Future
work will include items on the Capital Improvement Plan. The largest capital project proposed is the parallel taxiway
project. This project has an estimated design and construction cost of $15 million. Funding for capital projects is typically
supported by the Federal Aviation Administration ( FAA) through an annual allocation. This allocation is programmed. For
larger projects the FAA may use discretionary funding. A local match, typically 10%, is required. The parallel taxiway is
proposed to be designed in 2027 and construction beginning in 2029.
Kittitas County needs to get serious about Bowers Field
The County should place $1.5 million of distressed -area sales -tax revenue in reserve now to provide the anticipated local
match for the future $15 million FAA airport -improvement project. Securing the match would demonstrate that the County
is prepared to move forward when federal funding becomes available.
The County was legally gifted the airport incubator building more than two years ago, yet there is still no clear plan for its
use. That is not responsible management of a public asset.
Wetlands near an active airport runway create a potential wildlife -attraction and bird -strike hazard. The County should
determine which wetlands can legally be filled and mitigate those impacts by restoring or protecting wetlands elsewhere —
potentially as part of the County's Yakima River floodplain property acquisitions.
Waiting for a bird strike involving an aircraft flown by a student pilot is not an acceptable safety policy. The County must
act before a preventable accident occurs —not afterward, when condolences are all it has left to offer.