Exhibit A – Scope of Work
On-Call Engineering Services
Kittitas Valley Event Center RV Park
Ellensburg, WA
Prepared For: Kittitas County
Prepared By: Diana Jones, P.E.
Dan Ireland, P.E.
Date Prepared: August 13, 2026
Introduction:
This Phase/Task was previously “Phase 7 - Feasibility Study” under the 2022 On-Call Engineering Services
Contract; since then, the project has evolved into preliminary and environmental processes. The County is
committed to advancing the project toward a permit submittal and completed Construction Documents as it
strategizes construction funding.
SCJ has prepared this amendment to the On-Call contract to continue advancing the design of the RV Park
located at the corner of Alder Street and University Way within the City of Ellensburg and the Kittitas Valley
Event Center.
The purpose of this amendment is to update the contract to the new 2026 On-Call Engineering Services
Contract, develop a permit plan set to be processed through the City of Ellensburg, and include permitting and
final design in the scope, now that the preliminary plans and the drainage report are complete. This also
includes vacation of the right-of-way that crosses the site, a boundary line adjustment, and the preparation and
coordination of easements.
This scope of work includes the following:
Phase 1 – Project Management
Phase 2 – Boundary Line Adjustment
Phase 3 – 90 Percent Construction Documents
Phase 4 – Permitting
Phase 5 – Environmental Services (GG)
Phase 6 – Cultural Resources
Phase 7 – 100 Percent Construction Documents
Phase 8 – Stormwater Drainage Report
Phase 9 - Cost Estimate
Phase 10 – Specifications
Phase 20 – Underground Electrical Project
Phase 98 - Additional Services
Phase 99 - Expenses
KVEC RV Park
August 13, 2026
Page 2 of 9
25 N Wenatchee Ave, Suite 238 Wenatchee, WA 98801 Office 509.886.3265 Fax 360.352.1509 scjalliance.com
Phase 1 Project Management
Task 1 Project Management
1) General project communication
2) Monthly billing and contract administration
3) Subconsultant scoping (survey only)
Phase 2 Boundary Line Adjustment - Subconsultant Services
1) This phase includes subconsultant surveying services required to complete a Boundary Line
Adjustment, right-of-way vacation, preparation of easement documents, and legal descriptions
for the project. The fee associated with this task is based on the subconsultant’s direct cost
proposal; see attached. In addition, SCJ applies a 10% markup to subconsultant fees to account
for applicable taxes and administrative costs.
Phase 3 90 Percent - Construction Documents
This phase is to complete the documents into a permit-level plan set for processing by the City of Ellensburg. It
is assumed documents will be ready for submittal within 3 months.
Task 1 90 Percent Level
1) Boundary Line Adjustment Support – CADD incorporation
2) 90% Civil Plan Set: Plan set will include the following sheets;
a) Cover Sheet with General Notes
b) Existing Conditions
c) Demolition Plan
d) Temporary Erosion Control Plan and Details
e) Site Plan
f) Site and Paving Details
g) Overall Grading Plan
h) Detailed Grading Plans
i) Stormwater Plan and Profile
j) Stormwater Details
k) Overall Water and Sewer Plan
l) Water Plan and Profile
m) Water Details
n) Sewer Plan and Profile
o) Sewer Details
p) Gas and Electrical Plan
q) Gas and Electrical Details
r) Landscape Architecture Planting & Restoration Plans
s) Landscape Architecture Details
t) Irrigation Plans
KVEC RV Park
August 13, 2026
Page 3 of 9
25 N Wenatchee Ave, Suite 238 Wenatchee, WA 98801 Office 509.886.3265 Fax 360.352.1509 scjalliance.com
u) Irrigation Details
v) Traffic Control Plans
w) CXT Building Plans
Phase 4 Permitting
Task 1 Land Use - City of Ellensburg
1) SEPA Checklist: Develop the SEPA Checklist and reply to public comments.
2) Permit Application: Prepare City of Ellensburg Land Use Application.
3) Permit Submittal: Compile documents, including documents prepared by subconsultants, into a
single permit package and submit to City of Ellensburg.
4) Review Meeting: Meeting with the design team and client to review the City comments.
5) Comment Response Letter: Prepare comment response letter addressing City comments.
Task 2 Building Permit – City of Ellensburg
1) Building Permit Application
2) Building Permit Submittal: Coordination and document compilation of CXT pre-fab building
drawings for submittal to the City.
Task 3 Department of Ecology
1) Construction Stormwater General Permit: SCJ will assist the client with filing the notice of intent
with the Washington State Department of Ecology and transferring permit responsibility to the
contractor after one is selected.
2) UIC Registration: SCJ will help register the proposed UIC facilities online with Ecology, which
requires registration to be submitted 60 days prior to well construction.
Phase 5 Environmental Services (GG)
This Phase represents the remaining budget from the 2022 On-Call services. There is $7,109 of
remaining budget for GG to complete their scope of work that will be transferred to this
contract.
Phase 6 Cultural Resources
This phase represents the remaining budget for the remaining services from the 2022 On-Call
services contract. The remaining budget for these services is $14,163 and will be transferred to
this contract.
KVEC RV Park
August 13, 2026
Page 4 of 9
25 N Wenatchee Ave, Suite 238 Wenatchee, WA 98801 Office 509.886.3265 Fax 360.352.1509 scjalliance.com
Phase 7 100 Percent – Construction Documents
Task 1 Final Construction Plan Set
1) Updates to the overall plan set after the 90% design coordination meeting with the
County/City. This plan set will also be used as part of the construction bid set.
Phase 8 Stormwater Drainage Report
Task 1 Finalize Drainage Report
1) Update preliminary drainage report to match final design, which includes updates to the basin
map, sizing calculations, and report narrative.
Task 2 O&M Manual:
1) Prepare an operation and maintenance manual for stormwater components and BMPs (i.e.
catch basins, piping, etc.). The O&M manual will provide recommended maintenance
procedures, maintenance intervals, and describe conditions that warrant maintenance or
replacement of infrastructure.
Task 3 Construction Stormwater Pollution Prevention Plan (CSWPPP):
1) Prepare CSWPPP for submittal with Washington Department of Ecology General Stormwater
Construction Permit.
Phase 9 Cost Estimate
Task 1 90% Estimate:
1) Estimate of quantities and unit costs.
Task 2 100% Estimate:
1) Estimate of quantities and unit costs.
Phase 10 Specifications
Task 1 90% Specifications:
1) Development of specifications using the WSDOT Specifications for Road and Bridge
Construction as the basis of the project.
2) Development of project-specific and general special provisions for the project.
Task 2 100% Specifications:
1) Formatted to APWA and WSDOT Standard Specifications. Front-end contracting documents are
to be provided by the County.
KVEC RV Park
August 13, 2026
Page 5 of 9
25 N Wenatchee Ave, Suite 238 Wenatchee, WA 98801 Office 509.886.3265 Fax 360.352.1509 scjalliance.com
Phase 20 Underground Electrical Project
Task 1 Underground Electrical Construction Services
1) Project Management
a) Weekly project updates and correspondence on progress.
b) Resource loading project and scheduling
2) Pre-Construction
a) Inspector Plans and Specification review.
b) Field record and project documentation preparation.
(a) Photos/video of the existing site.
c) Pre-construction meeting preparation.
d) Pre-construction meeting (1 in person).
3) Office Engineering
a) Documentation of prevailing wages
b) Review sub-contractor requests.
c) Contractor schedule submittal review.
d) Develop working day statements. Estimate 2 statements.
e) Review of traffic control plans.
f) Material submittal reviews. Estimate materials
g) Monthly Pay Estimates
(a) Pay Estimate setup for the project.
(b) Review of field pay notes
(c) Pay Estimate review (office materials back check).
(d) Revisions based on Contractor responses.
(e) Requests to the contractor for additional information for payment.
(f) Estimate 3 pay estimates for the project duration.
h) Request for Information (RFI’s)
(a) Setup tracking
(b) Review an estimate of 3 based on project size and complexity.
(c) Response to RFI’s.
i) Change Order(s)
(a) Setup tracking
(b) Review or develop and RFP.
(c) Estimate 1 based on the size and complexity of the project.
4) Construction Observation
a) Project field observation
(a) Estimate 5 onsite field observation days.
(b) Observing contractor’s compliance with contract documents
KVEC RV Park
August 13, 2026
Page 6 of 9
25 N Wenatchee Ave, Suite 238 Wenatchee, WA 98801 Office 509.886.3265 Fax 360.352.1509 scjalliance.com
(c) Monitoring/inspection of traffic control
(d) Measuring items for payment.
b) Record of Materials review of field items
c) Finalizing of Inspection Daily Reports outside of inspection time.
d) Field quantity measurement preparation of pay note documents.
e) Construction meetings. Estimate 3 meetings.
f) Pay Estimate review (office materials back check). Estimate 3 pay estimates.
5) Contract Closeout
a) Final review of materials documentation for closeout. Includes a complete file of material
approvals, documentation requirements, and test results.
b) Punchlist development.
c) Site visit for punch list back review (1 trip onsite).
d) Review certified prevailing wages.
e) Record Drawing review.
f) Substantial Completion notification.
g) Physical completion notification.
h) Final Project Documentation to the Client via PDF.
Deliverables for Undergrounding Electrical Project:
1) Construction Services will occur between April and June 2025.
2) Bid Ready Construction Plans
3) Bid Ready Construction Specifications and Special Provisions
4) Project Cost Estimate
5) Land Disturbance Application
6) Right of Way application
7) Bid Advertisement
8) Recommendation of Award Letter
Understanding for Undergrounding Electrical Project:
1) Existing site data or environmental work is not required to gain approval from the City to
construct the Undergrounding Project.
2) Small Works project delivery that the County will supply to the three contractors of their
choice.
3) We have set up this contract as a Time and Materials effort to better prepare multiple revisions
with the Team to “right-size” and “right-style” the layout.
Phase 98 Additional Services
Often during a project, additional services are requested that were not part of the original scope. We have set
up this Additional Services phase for those requests. No work will be performed under this phase without prior
notification to and authorization from the Client.
KVEC RV Park
August 13, 2026
Page 7 of 9
25 N Wenatchee Ave, Suite 238 Wenatchee, WA 98801 Office 509.886.3265 Fax 360.352.1509 scjalliance.com
Phase 99 Expenses
Expenses will be invoiced on a time and material basis and include items such as mileage, plan reproduction,
submittal delivery, copies, etc.
Understanding/Assumptions
1) No offsite improvements (i.e. transportation, utility, etc.) are included in this scope of work.
2) It is assumed the SEPA will not be appealed by the public.
3) SEPA/permit fees will be paid by the applicant.
4) We have budgeted one resubmittal to the City based on their review of the 90% documents.
Additional submittals will be billed under Phase 98 on a time and materials basis.
5) Changes to the site layout initiated or approved by the Client will be tracked via time and
materials to Phase 98
6) Bid advertisement, including bid proposal sheet development, and Construction Support are
not part of scoped services. Upon County readiness, we can prepare an amendment for
additional services.
7) Assume only one submittal for the building permit.
8) UIC Registration is for one facility only.
9) Irrigation point-of-connection??
10) No off-site frontage landscape, street tree, sidewalk, or frontage restoration design unless
required by the City during permit review.
KVEC RV Park
August 13, 2026
Page 8 of 9
25 N Wenatchee Ave, Suite 238 Wenatchee, WA 98801 Office 509.886.3265 Fax 360.352.1509 scjalliance.com
Estimated Amendment Fee - Time and Materials Not to Exceed without prior authorization
Phase # Phase Title SCJ Hours Total Cost
SCJ Labor
PHASE 1 Project Management
Task 1 Project Management 54 $11,385
Phase Total: 54 $11,385
PHASE 3 90% Construction Docs
Task 1 90% Level 408 $62,237
Phase Total: 408 $62,237
PHASE 4 Permitting
Task 1 Land Use - City of Ellensburg 44 $7,810
Task 2 Building Permit - City of Ellensburg 6 $1,266
Task 3 Department of Ecology 12 $1,920
Phase Total: 62 $10,996
PHASE 7 100% Construction Docs
Task 1 Final Construction Plan Set 136 $19,780
Phase Total: 136 $19,780
PHASE 8 Stormwater Drainage Report
Task 1 Finalize Drainage Report 24 $4,044
Task 2 O&M Manual 4 $640
Task 3 CSWPPP 4 $640
Phase Total: 32 $5,324
PHASE 9 Cost Estimate
Task 1 90% Cost Estimate 36 $4,520
Task 2 100% Cost Estimate 28 $3,652
Phase Total: 44 $8,172
PHASE 10 Specifications
Task 1 90 Perc Specifications 36 $6,340
Task 2 100 Perc Specifications 18 $3,210
Phase Total: 38 $9,550
PHASE 20 Underground Electrical Project
Task 1 PM 4 $1,140
Task 2 PreConstruction 8 $2,280
Task 3 Office Engineering 32 $6,200
Task 4 Construction Observation 46 $9,706
Task 5 Contract Closeout 17 $3,661
Phase Total: 107 $22,987
Subtotal: $150,431
Subconsultants
PHASE 2 Survey - Cruise and Associates $15,000
PHASE 5 Environmental - GG Environmental $7,109
KVEC RV Park
August 13, 2026
Page 9 of 9
25 N Wenatchee Ave, Suite 238 Wenatchee, WA 98801 Office 509.886.3265 Fax 360.352.1509 scjalliance.com
PHASE 6 Cultural Resources - Plateau $14,163
Subconsultant Markup: $3,627.20
Subtotal: $39,899.20
Reimbursable Expenses
Phase 99 Reimbursable Expenses:
Copies, Printing, etc. $752.16
Mileage $1,235.40
Expenses Markup: 10% $198.76
Subtotal: $1,987.56
Management Reserve Fund (MRF)
Phase 98 Additional Services $0
Total: $192,516.52
Previous 2022 On-Call Contract Not Spent and transferred to this contract: $49,313
KVEC RV Park
Phases 1,2,3,4,5,6,7,8,9,10,99: $169,530
Underground Electrical Project: $22,987
Phase 20