Subject: Courthouse Server Room - AC Replacement
Engineering Services Proposal
Dear Charlie:
Here is our proposal to provide engineering services for this project.
Project Description
Replace two split system HVAC units serving the server room at the Courthouse. New unit will be same
size as the existing. Project will be publically bid.
Scope of Services
Design Phase: Provide field reviews, engineering, drawings, and specifications to allow for the work.
Construction cost estimates and updated schedules are included with each progress submittal. A 60%
progress set, 90% progress set, and final 100% (bid ready) set of submittals are included. We assume you will
provide us the Division 00 contract documents (bid form, contract, etc.).
Bid Phase: Attend the pre-bid meeting, respond to bidder questions, review substitution requests,
issue any required addenda, and review bids.
Construction Phase: Attend the pre-construction meeting, review product submittals, answer contractor
questions, conduct and attend virtual meetings during construction (assume 4), provide one site visit
during construction, review pay requests, provide one punchlist review, one punchlist back check, and
review project closeout documents (O&M manual, generator test reports, etc.).
Proposed Fee
We propose to provide our services on an hourly charge basis, not to exceed our authorized fee without
your prior permission. Fee summary:
Engineering:
Discipline Design Bid CA Totals
Mechanical $11,315 $2,095 $8,015 $21,425
Electrical $3,855 $485 $2,100 $6,440
Total $27,865
Reimbursable:
June 17, 2026
Kittitas County
Courthouse Server Room - AC Replacement
Engineering Services Proposal
Page 2
Mileage $ 800
Printing $ 100
Total Reimbursable $ 900
Reimbursable costs will be billed as incurred in accordance with County requirements.
Total not-to-exceed fee with Reimbursable: $ 28,765
See the attached for a list of expected engineering tasks and hours.
Preliminary Schedule
Assuming a notice to proceed by July 15th, here is a preliminary schedule.
Task/Activity Completion Date
NTP July 15, 2026
60% Submittal August 5, 2026
90% Submittal August 19, 2026
Final Bid Set August 29, 2026
Bid Set Released September 2, 2026
Bids Due September 23, 2026
Contractor NTP October 3, 2026
HVAC Equipment On-Site November 14, 2026
Substantial Completion December 5, 2026
Final Acceptance December 19, 2026
We appreciate this opportunity to work with you.
Sincerely,
Hultz|BHU Engineers Inc.
Rick Hultz, PE
Principal
Attached: Estimated Tasks/Hours, 2 pages
Hultz/BHU Engineers (253) 383-3257
Consulting Engineers
Project:Kittitas County Courthouse Server AC Units
Work:Mechanical Engineering Page 1
- Assoc Senior Senior Project Project Senior CAD .-
Task Principal Principal Engr Proj Mgr Engr Mgr Designer Tech Clerical
Design Phase Kick-Off Meeting 0.5 0.5
Site Visit 0.5 6
Develop ACAD Background 1 6
G#-Cover Sheet 1 1
M#-Legend/Notes 2 1
M#-Schedules 0.5 2 2
M#-HVAC Plan 0.5 12 8
M#-Details 4 2
Specifications - Technical 0.5 6 4
Coordination 2
Project Schedule 1
Meetings 2
QC Review 0.5 2
Progress Submittal(s) 0.5 2 2
Cost Estimate(s) 3
Respond to Review Comments 0.5
Permit Forms 1
Hour Total 3.5 0 0 0 48 0 0 22 4
Labor Hourly Rate $250.00 $225.00 $190.00 $175.00 $160.00 $150.00 $130.00 $110.00 $85.00
Labor Cost Sub-Totals $875 $0 $0 $0 $7,680 $0 $0 $2,420 $340
DESIGN PHASE TOTAL:$11,315
- Assoc Senior Senior Project Project Senior CAD .-
Task Principal Principal Engr Proj Mgr Engr Mgr Designer Tech Clerical
Pre-Bid Meeting 6
Substitution Request Review 2
Bidder Questions 1
Addenda 1 2 1
Hour Total 1 0 0 0 11 0 0 0 1
Labor Hourly Rate $250.00 $225.00 $190.00 $175.00 $160.00 $150.00 $130.00 $110.00 $85.00
Labor Cost Sub-Totals $250 $0 $0 $0 $1,760 $0 $0 $0 $85
BID PHASE TOTAL:$2,095
- Assoc Senior Senior Project Project Senior CAD .-
Task Principal Principal Engr Proj Mgr Engr Mgr Designer Tech Clerical
Pre-Con Meeting 0.5 5
Submittal Reviews 1 8 4
Submittal Re-Reviews 2 1
Meetings (Virtual) 1 6 1
Site Visi (1) 5
RFI's ` 2 1
Pay Reviews 2
Punchlist 0.5 5 1
Backcheck 5
Closeout Review 1
Hour Total 3 0 0 0 41 0 0 1 7
Labor Hourly Rate $250.00 $225.00 $190.00 $175.00 $160.00 $150.00 $130.00 $110.00 $85.00
Labor Cost Sub-Totals $750 $0 $0 $0 $6,560 $0 $0 $110 $595
CONSTRUCTION PHASE TOTAL:$8,015
TOTAL ALL PHASES:$21,425
- Assoc Senior Senior Project Project Senior CAD .-
Principal Principal Engr Proj Mgr Engr Mgr Designer Tech Clerical
$250.00 $225.00 $190.00 $175.00 $160.00 $150.00 $130.00 $110.00 $85.00
NIC = Not Included
6/17/2026
E N G I N E E R I N G H O U R S
BID PHASE
CONSTRUCTION PHASE
Hourly Rates
DESIGN PHASE
Hultz/BHU Engineers (253) 383-3257
Consulting Engineers
Project:Kittitas County Courthouse Server AC Units
Work:Electrical Engineering Page: 2
- Assoc Senior Senior Project Project Senior CAD .-
Task Principal Principal Engr Proj Mgr Engr Mgr Designer Tech Clerical
Site Visit See Mechanical
Confirm Loads 3
E#-Legend/General Notes 1 1
E#-Power Plan(s) 0.5 2 1
E#-New Panel Schedules 1 1
E#-New One Line Not Included
Specifications - Technical 3 1
Coordination 2
Meetings 1
QC Review 1 1 1
Progress Submittal(s) 1 1
Cost Estimate(s) 0.5 2
Hour Total 2 0 0 0 17 0 0 5 1
Labor Hourly Rate $250.00 $225.00 $190.00 $175.00 $160.00 $150.00 $130.00 $110.00 $85
Labor Cost Sub-Totals $500 $0 $0 $0 $2,720 $0 $0 $550 $85
DESIGN PHASE TOTAL:$3,855
- Assoc Senior Senior Project Project Senior CAD .-
Task Principal Principal Engr Proj Mgr Engr Mgr Designer Tech Clerical
Pre-Bid Meeting Not included
Substitution Request Review 0.5
Bidder Questions 1
Addenda 1 1
Hour Total 0 0 0 0 2.5 0 0 0 1
Labor Hourly Rate $250.00 $225.00 $190.00 $175.00 $160.00 $150.00 $130.00 $110.00 $85.00
Labor Cost Sub-Totals $0 $0 $0 $0 $400 $0 $0 $0 $85
BID PHASE TOTAL:$485
- Assoc Senior Senior Project Project Senior CAD .-
Task Principal Principal Engr Proj Mgr Engr Mgr Designer Tech Clerical
Pre-Con Meeting 1
Submittal Reviews 4 2
Submittal Re-Reviews 1
Correspondence Review 1
Meetings (Virtual) 2
Site Visits Not Included
RFI's 0.5 1 0.5
Punchlist See Mechanical
Backcheck See Mechanical
Closeout Review See Mechanical
Hour Total 0.5 0 0 10 0 0 0 0.5 2
Labor Hourly Rate $250.00 $225.00 $190.00 $175.00 $160.00 $150.00 $130.00 $110.00 $85.00
Labor Cost Sub-Totals $125 $0 $0 $1,750 $0 $0 $0 $55 $170
CONSTRUCTION PHASE TOTAL:$2,100
TOTAL ALL PHASES:$6,440
- Assoc Senior Senior Project Project Senior CAD .-
Principal Principal Engr Proj Mgr Engr Mgr Designer Tech Clerical
$250.00 $225.00 $190.00 $175.00 $160.00 $150.00 $130.00 $110.00 $85.00
NIC = Not Included
E N G I N E E R I N G H O U R S
Hourly Rates
DESIGN PHASE
BID PHASE
CONSTRUCTION PHASE