June 10, 2026
Kittitas County
205 W 5th Avenue, Suite 105
Ellensburg, WA 98926
Attention: Charlie Smith
Subject: Sheriff’s Office – Generator Replacement
Engineering Services Proposal
Dear Charlie:
Here is our proposal to provide engineering services for this project.
Project Description
Replace two propane generators serving the Sheriff’s office with a new one. Generator loads will be
revised to add items not currently on the generator. Panels and transfer switch arrangement will be
reviewed and revised to suit the new generator and new loads. Propane fuel tank and piping will be
reviewed and revised as needed to accommodate the new generator sizing and configuration. Project
will be publically bid.
Scope of Services
Design Phase: Provide field reviews, engineering, drawings, and specifications to allow for the work.
Construction cost estimates and updated schedules are included with each progress submittal. A 60%
progress set, 90% progress set, and final 100% (bid ready) set of submittals are included. We assume you will
provide us the Division 00 contract documents (bid form, contract, etc.).
Bid Phase: Attend the pre-bid meeting, respond to bidder questions, review substitution requests,
issue any required addenda, and review bids.
Construction Phase: Attend the pre-construction meeting, review product submittals, answer contractor
questions, conduct and attend virtual meetings during construction (assume 4), provide one site visit
during construction, review pay requests, provide one punchlist review, one punchlist back check, and
review project closeout documents (O&M manual, generator test reports, etc.).
Proposed Fee
We propose to provide our services on an hourly charge basis, not to exceed our authorized fee without
your prior permission. Fee summary:
Engineering:
Design Bid CA Totals
$19,780 $1,735 $10,375 $31,890
June 10, 2026
Kittitas County
Sheriff’s Office – Generator Replacement
Engineering Services Proposal
Page 2
Reimbursable:
Mileage $ 900
Printing $ 200
Total Reimbursable $ 1,100
Reimbursable costs will be billed as incurred in accordance with County requirements.
Total not-to-exceed fee with Reimbursable: $ 32,990
See the attached for a list of expected engineering tasks and hours.
Preliminary Schedule
Assuming a notice to proceed by June 24th, here is a preliminary schedule.
Generator ordered by the low bid contractor:
Task/Activity Completion Date
NTP June 24, 2026
60% Submittal August 8, 2026
90% Submittal September 4, 2026
Final Bid Set September 25, 2026
Bid Set Released September 29, 2026
Bids Due October 20, 2026
Pre Con Meeting November 3, 2026
Generator On-Site February 23, 2027
Substantial Completion April 9, 2027
Final Acceptance April 23, 2027
We appreciate this opportunity to work with you.
Sincerely,
Hultz|BHU Engineers Inc.
Rick Hultz, PE
Principal
Attached: Estimated Tasks/Hours, 2 pages
Hultz/BHU Engineers (253) 383-3257
Consulting Engineers
Project:Kittitas County
Work:Electrical Engineering Page: 1
- Assoc Senior Senior Project Project Senior CAD .-
Task Principal Principal Engr Proj Mgr Engr Mgr Designer Tech Clerical
Site Visits 0.5 11
Create Panels/One-Line 2
Confirm Loads/Gen Adds 1 6
Create ACAD Backgrounds 2 6
Propane Sizing 0.5 4
G#-Cover Sheet 2 2
E#-Legend/General Notes 1 2
E#-Site Plan 2 2
E#-Power Plan(s) 0.5 8 8
E#-Propane Tank/Piping 1 5 3
E#-New Panel Schedules 4 2
E#-New One Line 0.5 4 2
Catalog Cuts & Revisions NIC
System Narratives NIC
Specifications - Technical 1 8 3
Obtain Div 00 Docs--Format/Revise 0.5 2
Coordination 4
Schedule Review 1
Meetings ` 3
QC Review 2 1 1
Progress Submittal(s) 0.5 1 1 1
Cost Estimate(s) 1 8
Permit Submittal 1
Hour Total 9 0 0 80 0 0 0 29 4
Labor Hourly Rate $250.00 $225.00 $190.00 $175.00 $160.00 $150.00 $130.00 $110.00 $85
Labor Cost Sub-Totals $2,250 $0 $0 $14,000 $0 $0 $0 $3,190 $340
DESIGN PHASE TOTAL:$19,780
- Assoc Senior Senior Project Project Senior CAD .-
Task Principal Principal Engr Proj Mgr Engr Mgr Designer Tech Clerical
Pre-Bid Meeting 5
Substitution Request Review 1
Bidder Questions 1
Addenda 1 1 1
Hour Total 1 0 0 8 0 0 0 0 1
Labor Hourly Rate $250.00 $225.00 $190.00 $175.00 $160.00 $150.00 $130.00 $110.00 $85.00
Labor Cost Sub-Totals $250 $0 $0 $1,400 $0 $0 $0 $0 $85
BID PHASE TOTAL:$1,735
E N G I N E E R I N G H O U R S
DESIGN PHASE
BID PHASE
6/10/2026
Project:Kittitas County
Work:Electrical Engineering Page: 2
- Assoc Senior Senior Project Project Senior CAD .-
Task Principal Principal Engr Proj Mgr Engr Mgr Designer Tech Clerical
Pre-Con Meeting 0.5 5
Submittal Reviews 0.5 12 2
Submittal Re-Reviews 2
Correspondence Review 2
Meetings (Virtual) 8
Site Visits 6
RFI's 0.5 2 1
Changes/COP/CP Reviews 0.5 1 1
Pay Reviews 2
Punchlist 0.5 6
Backcheck 5
Closeout Review 2 1
Hour Total 2.5 0 0 53 0 0 0 2 3
Labor Hourly Rate $250.00 $225.00 $190.00 $175.00 $160.00 $150.00 $130.00 $110.00 $85.00
Labor Cost Sub-Totals $625 $0 $0 $9,275 $0 $0 $0 $220 $255
CONSTRUCTION PHASE TOTAL:$10,375
TOTAL ALL PHASES:$31,890
- Assoc Senior Senior Project Project Senior CAD .-
Principal Principal Engr Proj Mgr Engr Mgr Designer Tech Clerical
$250.00 $225.00 $190.00 $175.00 $160.00 $150.00 $130.00 $110.00 $85.00
NIC = Not Included
Hourly Rates
CONSTRUCTION PHASE
6/10/2026