HomeMy WebLinkAboutResolution_TO3_ArdurraGroup_HungryJunctionRoadKITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
AGENDA STAFF REPORT
AGENDA DATE: May 5, 2026
ACTION REQUESTED: Request to Approve a Resolution to Authorize the Chair's
Signature on Ardurra Group, Inc. Task Order No. 3 — Hungry
Junction Road Project
BACKGROUND: Kittitas County was awarded funds through the County Road
Administration Board (CRAB) Rural Arterial Program (RAP) for
the design and construction of road improvements on Hungry
Junction Road. The design of the improvements includes a
structure replacement at the intersection of Hungry Junction and
Faust Road, as well as widening and improving the existing
vertical curves on the roadway between Highway 97 and Reecer
Creek Road.
Public Works staff has been leading the design efforts of the
project including project management and civil design.
Consultant services are needed to advance the design to
completion.
Public Works previously solicited proposals and selected on -call
civil support and selected Ardurra Group Inc. as an on -call
consultant. Public Works has requested a scope and fee from
Ardurra Group, Inc., for design and construction support for the
project. The task order amount proposed is for $315,000.00 and
Ardurra would be under contract through the end of 2028.
At the April 27, 2026, Study Session, the Board of County
Commissioners provided staff with direction to proceed with
presenting enabling documents at a future agenda session.
INTERACTION: Public Works
RECOMMENDATION: Approve a Resolution to Authorize the Chair's Signature on
Ardurra Group, Inc. Task Order No. 3 — Hungry Junction Road
Project.
HANDLING: Return one original to Public Works
ATTACHMENTS: Resolution; Task Order No
LEAD STAFF: Josh Fredrickson
Public Works Director
BOARD OF COUNTY COMMISSIONERS
COUNTY OF KITTITAS
STATE OF WASHINGTON
RESOLUTION NO.2026-
AUTHORIZING CHAIR SIGNATURE ON ARDURRA GROUP, INC. TASK ORDER NO.3 —
HUNGRY JUNCTION ROAD PROJECT
WHEREAS: The Department of Public Works procured on -call professional engineering services from
Ardurra Group, Inc. consistent with state law and county code in July 2025; and
WHEREAS: Ardurra Group, Inc. is being provided with 60% plans that were developed by County
Staff; and
WHEREAS: Ardurra Group, Inc. prepared a scope of work and fee proposal to provide bid ready plans,
estimates, and specifications for said Project; and
WHEREAS: The value of Task Order No. 3 exceeds the contract authorization amount currently
provided to the Public Works Director;
NOW THEREFORE, BE IT RESOLVED The Board of County Commissioners of Kittitas County,
Washington, in the best interest of the public, does hereby authorize Chair signature on
Ardurra Group, Inc. Task Order No. 3 — Hungry Junction Road Project.
DATED this 51 day of May 2026, at Ellensburg, Washington.
Attest:
❑ Clerk of the Board- Julie Kjorsvik
❑ Deputy Clerk of the Board- Mandy Buchholz
BOARD OF COUNTY COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
Cory Wright, Chairman
Brett Wachsmith, Vice -Chairman
Laura Osiadacz, Commissioner
��o���CpSCppGS ... 7'p !yF(,olGy 9
KITTITAS COUNTY
KZTTZT'AlS COUNTY
DEPARTMENT OF PUBLIC WORKS
Formal Task Order Document
Ardurra Group, Inc.
Task Order Number 03
Maximum Amount Payable $315,000 Completion Date 12/31/2028
The general provisions and clauses of the Master Professional Services Agreement for On -
Call Civil Engineering executed on November 11, 2025, shall be in full force and effect for
this Task Order.
Location of Project: Kittitas County
Project Title: Hungry Junction Road
Description of Work: See Attached Exhibit B
Ardurra Group, Inc. (Consultant) shall perform design and develop bid ready plans, estimates
and specifications for said Project. Ardurra Group, Inc. will continue with the 60% plans
prepared by the County and Ardurra Group, Inc. will advance the project through several
iterations of design review to bid documents, along with bidding assistance.
Consultant shall complete all tasks as directed by and report to the Public Works Director and/or
County Engineer. The level of detail of such tasks shall be performed by CONSULTANT
commensurate with the level of effort allocated in the agreed upon budget.
Cost Breakdown: See Attached Exhibit B
Completion Date: 12/31/2028
Agency Signature:
Consultant Signature:
Date:
010
Date: 4-28-2026
Ardurra Group, Inc.
15. N Chelan Avenue
Wenatchee, WA 98801
ARDURRA
Exhibit B
Scope of Work
Kittitas County Public Works
On -Call Transportation Engineering
Ardurra Group Inc., Project No. 250426
Task Order No. 03
HUNGRY JUNCTION ROAD
April 2026
Master Agreement Description
The following scope of work is structured as an individual task order under the On -Call
Transportation Engineering master agreement between Kittitas County Public Works (county)
and Ardurra Group, Inc. (Ardurra)
Task Order Background and Introduction
The county has requested Ardurra perform design and develop bid ready plans, estimates,
specifications for approximately 1.7 miles of county roadway along Hungry Junction Road
beginning at US 97 and ending approximately 200 feet west of Reecer Creek Road.
The project generally consists of re -construction and widening of the existing roadway, re-
alignment of the vertical profile to correct deficiencies, installing guardrail where required,
replacement of a substandard culvert crossing with a box culvert, re -grading of driveways to
address driveway grading challenges associated with the vertical re -alignment, and new
roadway slopes, ditches, and driveway culverts etc.
Preliminary scoping discussion between Ardurra and the county indicated that the objective of
the project for the Ardurra team to pick up where the county left off with their in-house design
which is currently at approximately a 60% level design. Ardurra's task will be to will advance the
project through several iterations of design review to bid documents and provide bidding
assistance.
Project Understanding:
The county has provided Ardurra with their current CAD files, plans, estimates and other project
documentation that supports the following understanding of the scope of work:
Page 1 of 10
Transportation On -Call
Ardurra Group, Inc.
Environmental: Environmental documentation tasks have been mostly completed by
the county with assistance from Jacobs Engineering. Finalization of all environmental
documentation will be completed by the county and/or Jacobs. This scope of work does
not include completion of environmental documentation or any other
environmental/permitting tasks. Ardurra will support the county and other consultants
environmental efforts by providing design data, figures, and other information needed
for the JARPA and other permit requirements.
Box Culvert Structure: The project includes removal of two existing culverts on
Reecer Creek near the intersection of Hungry Junction Road and Faust Road.
Preliminary coordination regulatory agencies performed by the county has indicated
that the new structure will a box culvert designed according to WSDOT Standard Plans.
The county, in conjunction with Jacobs, has established concurrence from the Army
Corps of Engineers and Washington Department of Fish and Wildlife on the approach
described above.
This scope of work does not include structural engineering. Structural design is
provided by WSDOT standard plans. The box structure will be included in the project
per the guidance in the document provided by the county entitled "Structure
Justification_ Hungry Junction Road Over Reecer Creek"
Finalization of all environmental documentation and agency concurrence for the box
culvert replacement will be completed by the county with assistance as needed from
Jacobs. This scope of work does not include completion of environmental
documentation or permitting tasks.
The county with assistance from another consultant, Natural Waters, will provide the
hydrologic and hydraulic modeling required to design the structure geometry. This
scope of work does not include completion of hydrologic or hydraulic modeling.
The county with assistance from Geosyntec has completed geotechnical work related
to the structure. This scope of work does not include additional geotechnical work for
the box culvert structure.
• Irrigation and Utilities. It is anticipated that irrigation (both piped systems and ditch
systems) will be impacted by the project. It is anticipated that Ardurra will identify
conflicts between the project and existing irrigation and utility facilities, attempt to find
design solutions to minimize conflict, and identify irrigation and utility facilities that will
need to be relocated.
It is assumed that the county will lead coordination with effected irrigation districts and
utility providers to have these facilities relocated ahead of the project. Ardurra will
support the counties efforts by providing design information as needed.
Page 2 of 10
Transportation On -Call
Ardurra Group, Inc.
This scope of work is limited to identifying geometric conflicts and identifying potential
locations for irrigation and utilities to relocate to and limited design coordination. This
scope does not include significant irrigation or utility planning or design work such as
system evaluation, inspection, modeling, load calcs, construction plans and details,
relocation oversight, detailed coordination with utility owners etc.
• Stormwater: The county provided Ardurra with an internal memo identifying that the
stormwater requirements for this project will be met by BMP 6.42. Per the county's
memo:
"The Stormwater Management Manual for Eastern Washington (SWMMEW) indicates
this project falls under the definition of a Redevelopment project as defined in Chapter
2.6. Following the guidance provided in the Flow Chart for Determining Applicable Core
Elements for Redevelopment Projects (Figure 2.2), all Core Element 5 is required for
new and replaced PGIS, and Core Element 6 is only required for the new PGIS. The
County proposes utilizing BMP 6.42: Full Dispersion. Runoff will be required to be
concentrated in some locations through cut slopes and driveway locations, but through
use of Dispersion Trenches, Full Dispersion can still be met."
It is assumed that no additional stormwater calculations, reports, or other
documentation are included in this scope of work. Ardurra will review the geometric
requirements in BMP 6.42 and utilize those geometric requirements as a design
parameter. No additional treatment or infiltration BMPs are included in this scope of
work. If additional stormwater design or documentation is needed Ardurra may request
authorization of management reserve funds.
Schedule: In scoping discussions, the county identified that the fish window for in -
creek work associated with the box culvert is between August and the end of
September. Irrigation flows will also be a consideration. Additionally, lead times for pre-
cast structures are anticipated to require advertisement of the project no later than the
February preceding the fish window.
It is understood that the county's goal is to construct this project in 2027. However, it
is acknowledged that multiple factors including but not limited lead times for precast
structures, in water work windows, permitting approvals, funding approvals, the need
for additional geotechnical work to support retaining wall design, right of way needs,
etc. could push the project into the 2028 construction year. Ardurra will initiate this
project targeting 2027 construction with the understanding that, with the county's input
and approval, we may need to pivot to 2028. It is further understood that the project
cannot slip beyond 2028 without jeopardizing the project funding.
Other Identified Challenges: The county has identified that right of way and/or
permanent easements as well as temporary construction easements may be needed to
support the proposed roadway prism and to support reconnection of driveways. The
Page 3 of 10
Transportation On -Call
Ardurra Group, Inc.
project does not currently have an identified right of way phase, however right of way
work may be required. It is anticipated that the Ardurra team will identify areas of
concern and work with the county to identify a solution which might consist of a right of
way phase, retaining walls, or both. A design objective will be to design right of way
needs "out of the project" as much as possible.
This scope of work does not include right of way acquisition or related tasks. However,
Ardurra will generate proposed right of way, easement, and temporary construction
easement line work, produce figures for property owner meetings, and attend property
owner meetings as needed (Up to 6). It is assumed that property owner meetings will
be led by the county.
Proiect Approach:
Ardurra's general approach for the following scope of work will include:
• Independently re-establishing the 60% design using the county's 60% as a basis.
Effectively this means re -doing the work that's been done by the county from 30% to
60%.
• The new iteration of the 60% design will verify the county's assumptions and design
intent, identify new ways to optimize the design, verify the extents of right of way
challenges, and identify solutions to be implemented in subsequent design submittals.
Typical 90%, 100%, and Bid Document design submittal iterations will proceed after re-
establishing the 60%.
A management reserve has been included in the scope of work to provide for currently
unidentified project needs including but not limited to additional civil design not already identified
below, right-of-way services, geotechnical design, structural design, or other
consultant/subconsultant design needs. The following is Ardurra's specific scope of services.
Page 4 of 10
Transportation On -Call
Scope of Services
Ardurra Group, Inc.
Task 1.0 Project Management
Ardurra will manage internal resources, invoicing, project delivery schedule, and project related
coordination. Specific tasks include:
Consultant Responsibilities:
• Task 1.1: General Project Coordination and Management: General coordination,
communication, scheduling of work, and meetings. Management of internal resources,
project delivery schedule, and budget trajectory tracking.
• Task 1.2: Invoicing, Progress Reports, and Contract Administration: Prepare,
review, and finalize monthly invoices, progress reports, and perform general contract
administration and labor tracking tasks.
Task Specific Assumptions:
• The duration of this task order will be no more than 12 months. Additional hours for
project management may be needed via supplement if the project extends to 2028
construction.
• The project is state funded. The county will coordinate funding agency requirements.
• Ardurra is not leading any formal stakeholder coordination meetings or public meetings.
• See assumptions and exclusions below.
Deliverables:
Meeting agendas/notes
Monthly invoices and progress reports
Task 2.0 Independently Re -Establish the 60% Design
The county will provide Ardurra with the topographic survey, right of way delineation, design
files, cost estimate, and other supporting documentation associated with the county's 60%
design. Using the county's 60% design as a basis, Ardurra will independently develop a new
60% design.
Consultant Responsibilities:
Task 2.1: Review County Performed 60% Design. Ardurra will review the county's
60% design, meet with the county, and get familiar with the design and assumptions that
the county used.
Page 5 of 10
Transportation On -Call Ardurra Group, Inc.
• Task 2.2: Update Files and Standards and Create a new Sheet Set. Ardurra will
create a new sheet set for the Ardurra 60% design and transfer survey and design
documents over to the new design file.
• Task 2.3 Weekly Meetings with the County (Up to 10 Total). Ardurra will coordinate
and lead up to 10 informal weekly meetings with the county during this task to get input
from the county on work to help inform design decisions for the new 60% design.
Task 2.4 Independently Re -Establish the 60% Design. Ardurra will independently re-
establish the 60% design using the county's 60% as a basis. The new iteration of the
60% design will verify the county's assumptions and design intent, check for new ways
to optimize the design, verify the extents of right of way challenges, and identify
solutions to be implemented in subsequent design submittals.
Task Specific Assumptions:
• The county will perform all survey work and provide all survey files. If additional survey
needs are identified, the county will perform that work.
• The county will provide the 60% design and supporting documentation.
• The county will attend regular meetings and provide design feedback.
• No Ardurra survey work is included in this scope.
• See assumptions and exclusions below.
Deliverables:
• Meeting agendas and notes
• New 60% Review Plans and Construction Cost Estimate
Task 3.0 Design
Ardurra will progress through multiple design iterations with the ultimate goal of delivering bid
ready plans, specifications, and estimate (PS&E)
Consultant Responsibilities:
Task 3.1 — 90% Design
Task 3.1.1 Incorporate Final 60% Design Comments. Ardurra will respond to final
comments provided by the county on the 60% Review Submittal.
• Task 3.1.2. 90% Plans. Ardurra will develop 90% design level plans.
• Task 3.1.3 90% Cost Estimate. Ardurra will develop 90% construction cost estimate
based on the design files.
Page 6 of 10
Transportation On -Call
Ardurra Group, Inc.
• Task 3.1.4 Internal QC. Ardurra will provide an internal review of the draft 90%
submittal and update the deliverables before final submittal.
• Task 3.1.5 Contract and Specification Documents. Ardurra will develop the 90%
contract and specification package to accompany the 90% design deliverable.
• Task 3.1.6 Submit for Review (PS&E). Ardurra will assemble and backcheck
documents and formally submit to the county for review.
Task 3.2 — 100% Design
• Task 3.2.1 Incorporate Final 90% Design Comments. Ardurra will respond to final
comments provided by the county on the 90% Review Submittal.
• Task 3.2.2. 100% Plans. Ardurra will develop 100% design.
• Task 3.2.3 100% Cost Estimate. Ardurra will develop 100% construction cost estimate
based on the design files.
• Task 3.2.4 Internal QC. Ardurra will provide an internal review of the draft 100%
submittal and update the deliverables before final submittal.
• Task 3.2.5 Contract and Specification Documents. Ardurra will develop the 100%
contract and specification package to accompany the 100% design deliverable.
• Task 3.2.6 Submit for Review (PS&E). Ardurra will assemble and backcheck
documents and formally submit to the county for review.
Task 3.3 — Bid Documents
• Task 3.3.1 Incorporate 100% Design Comments. Ardurra will respond to final
comments provided by the county on the 100% Review Submittal.
• Task 3.3.2. Bid Document Plans. Ardurra will develop Bid Document design level
plans based on the previous design iteration.
• Task 3.3.3 Bid Document Cost Estimate. Ardurra will develop Bid Document
construction cost estimate based on the design files.
• Task 3.3.4 Internal QC. Ardurra will provide an internal review of the draft Bid
Document submittal and update the deliverables before final submittal.
Page 7 of 10
Transportation On -Call
Ardurra Group, Inc.
• Task 3.3.5 Contract and Specification Documents. Ardurra will develop the Bid
Document contract and specification package to accompany the Bid Document design
deliverable.
• Task 3.3.6 Submit for Review (PS&E). Ardurra will assemble and backcheck
documents and formally submit Bid Documents to the county.
Task Specific Assumptions:
• The county will provide the survey basemap and any subsequent survey needs.
• The county will provide their internal 60% design and documentation.
• Hydraulic modeling will be provided by the county and is not included in this scope
• Geotech work has been completed for the structure but more may be needed as a
supplement.
• Right of way services are not included in this scope of work but may be needed as a
supplement.
• Right of way plans and legal exhibits are not included in this scope of work.
• Structural design is not included in this scope of work.
• Environmental will be handled by the county and is not included in this scope.
• See additional assumptions and exclusions below.
Deliverables:
Meeting Agendas and Notes
• 90% Plans, Specs, and Estimate
• 100% Plans, Specs, and Estimate
• Bid Document Plans, Specs, and Estimate
Task 4.0 Bid Phase Support
Ardurra will address bidder questions, issue addendums if needed, and facilitate the bid review
process.
Consultant Responsibilities:
• Task 4.1 Respond to Bidder Questions & Addendums: Ardurra will review and
respond to bidder questions, document responses, and issue addendums as needed.
• Task 4.2 Bid Opening: Ardurra will attend the bid opening, and assist the county as
needed.
• Task 4.3 Bid Tabulation and Bid Review: Ardurra review the bid packages, develop a
bid tabulation, provide a recommendation for award letter as needed.
Page 8 of 10
Transportation On -Call
Ardurra Group, Inc.
Task 4.4 Bid Award: Ardurra will develop a notice of award letter on behalf of the
county as needed.
Assumptions:
• See general assumptions and exclusions below.
• County will lead the bid opening.
Deliverables:
• Bid Tabulation
• Recommendation for Award Letter
• Notice of Award Letter
Task 5.0 Construction Services
The Client may elect to retain the services of Ardurra to provide construction services, including
but not limited to construction management, observation, inspection, and support. At the
request of the Client, Ardurra will provide a supplemental scope of services for this work.
Page 9 of 10
Transportation On -Call Ardurra Group, Inc.
General Assumptions and Exclusions
The following are a list of assumptions that apply to this scope of work and services that are
specifically excluded from this agreement, but may be added by written authorization of the
Client:
Ardurra Design:
• Exclusions and/or Additional Services:
• Master Planning and/or Capital Improvement Planning.
• Ordinance preparation.
• Any other review submittals not specifically identified in the list of deliverables.
• Funding Applications
• Construction management.
• Environmental permitting and documentation.
• Cultural Resources work.
• Geotechnical work.
• Structural work.
• Topographical surveying or base mapping.
• Right of way delineation
• Title reports.
• Environmental mitigation or cleanup.
• Traffic control
• Legal services.
• Agency submittal fees, review fees or permit fees.
• Client inspired changes or unforeseen changes arising due to regulatory decisions.
• Any services, product or professional responsibility not specifically described above.
Page 10 of 10
Exhibit B
Project Budget
Kitthas County Public Works
On -Call Transportation Engineering
Ardurra Group, Inc. Project No 250426
Task Order No 03
HUNGRY JUNCTION ROAD
Aorii 2026
ITEM
N'O,
DESCRIPTION'OF WORK
"fetal Hours
by Task
Project
Manager
Project
Engineer
Dedgn
Engineer
CAD Tech. 67
Project
Accountant
Total Prime
an
Csultane Labor
Cost Computation by
Task
Anticipated Staff Member
Iu.+b Fedora
Mtchelll
Ryan Peri
Th xhy Fisch
Ililiary S.
Direct Salary Rate
S 235.00
S 210.00
S 140.00
S 130.00
$ 105.00
1.0
1 Project Management
1.1
Gencml Pni act Coordination and Mans xucrt
25
25
$ 7,125.00
1.2
Invoici , Prrercss Revorts, and Contract Administration
25
10
15
S 4,425.00
Subtotal Estimated Hours and Fee
50
35
0
0
0
15
s 11550.00
2.0
Independently Re -Establish the 60 % Design
2.1
Review Cuun Performed 60% Desi r
30
10
10
10
$ 6350.00
2.2
U ate'Recreate Files & Stds & Create New Sheet Set
135
20
35
40
40
$ 23,850.00
2.3
Weekly Mectirw with Counry (Up to 10 Total)
40
20
20
1
$ 9,900.00
2.4
Inder-dently Develop aNew 60% Submittal(Plans&mat Estie)
170
30
40
60
40
$ 30550.00
m Subtota Estiated Hours and Fee
375
80
ins
Ito
80
0
s 70,650.00
3.9
Design
3.1
90%Design
3.I.1
General Conrdintion
50
IS
15
IS
5
$ 10,175.00
3.1.2
Plans (Draft)
150
25
25
60
40
$ 25.975.00
3.1.3
Coat Estimate
60
20
25
15
$ 11050.00
3.1 A
30
10
10
10
$ 6,350
3.1,5
Contract and Does
on
65
40
15
10
$ 15,9 50,00
3.1.6
Submit for Review(PS&E)
20
10
10
$ 4950.00
Subtotal Estimated Hours and Fee
375
120
too
Ito
45
0
s 76,450.00
32
100% Design
3.2.1
General Coordination
50
IS
15
15
5
$ 10,175.00
3.2.2
Plans (Draft)
130
IS
IS
60
40
$ 21.025.00
3.2.3
Cost Estimate
35
i5
10
10
$ 7,775.00
32.4
A
30
10
10
10
$ 6350.00
3.2.5
Contract and Spor Docs
45
25
10
10
$ 10625.00
3.2.6
Submit fo Review IPS&E
10
5
5
$ 2,475.00
Subtotal Estimated Hours and Fee
300
85
65
Ins
45
0
s 58,425.00
3.3
Iffid Documents
3.3.1
General Coordination
35
10
10
10
5
$ 7000.00
3.3.2
Plans Draft
90
IS
15
40
20
$ 15,625.00
3.3.3
Cost Estimate
30
10
10
10
$ 6.350,00
33q
30
10
to
10
$ 6.35000
3.3.5
Contract end Src, Does
45
25
10
10
$ 10,625600
3.3.6
Final Submittal PS&E
20
10
10
$ 4,950.00
Subtotal Estimated Hours and Fee
250
80
65
80
25
0
s 501900.00
Subtotal Estimated Hours and Fee
925
285
230
295
115
0
$ 195,775.00
4.0
Bid Phase Support
4.1
Bidder 0ucstions and Addends
t0
5
5
$ 2,475.00
4.2
Bid Ope.i.v
5
5
$ 1425'00
4.3
Bid Tabulation and Bid Review
5
5
$ 1A25.00
4A
Bid Award
5
5
$ 1,425.00
Task Total
25
20
5
0
0
0
s 6,750.00
5.0
Construction Support
5.1
To Be Sco ed as a Supplemental A cement
0
$ -
Task Total
0
0
0
0
0
0
$0.00
TOTAL OF ESTIMATED HOURS & FEE (PRIME)
1375
4204340
405
195
15
$ 274,725.00
Subconsuttants
N/A
$
Subtotal
$
Administrative Charge
$
Total Subconsubust Expense
$ -
Reimbursable Direct Non -Salary Costs
Dmign Team Mileage; 12 trips (. 150 mile RT x$0.725/mi
$ 1.305.00
'Foral Reimbursible Expense
$ 1,305.00
Budget Summary
Subtotal Estimated Budget (Total Ardurra Group Fee+Total Subcomultant Expeme+Tom! Reimburaible Expense)
S 276,030.00
Management Reserve
$ 38,970.00
Total Estimated Project Budget
$ 315,000.00
Ardurra Group, Inc. Page t of I