April 15, 2026
Re: J Mod Modifications
Per your request, we are pleased to offer the following change order proposal #19 (COP 19).
If approved, Belsaas and Smith’s onsite team will make the requested upgrades to the J Mod
space. This will include:
•Installing a new porcelain wall-hung toilet in the restroom
•Cleaning and sealing the floor tile grout in the restroom
•Installing a new 3/0 x 7/0 18ga flush door and associated hardware
•Cutting and grinding the supports for the tables and seating and patching the flooring
smooth
•Installing the selected carpet squares throughout the entire room
•Making all the requested electrical modifications
•Painting all the walls and the new door to the restroom
Total cost of proposal: Forty-One Thousand Four Hundred Seventy-Nine Dollars $41,479.32
+ WSST
*Note: Door lead time is 8 weeks from change order approval unless a wood or spare door is
approved
Sincerely,
Scott Carlson
Belsaas & Smith Construction
Docusign Envelope ID: C25FA4F8-E33D-86B7-827D-CBC596D54968
BELSAAS & SMITH CONSTRUCTION
SHEET 1 of 2 C.O.P. #19
CHANGE ORDER PROPOSAL BREAKDOWN SHEET
UNIT COSTS EQUIP SUB MATERIAL LABOR
#DESCRIPTION QUAN.UNIT Mat.EQUIP LABOR COST COST COST COST
J Mod Modifications
Project Management 20 HRS 102.00 -$ -$ -$ 2,040.00$
-$ -$ -$ -$
Demo (2 Carpenters x 8 Hrs @ $102)16 HRS 102.00 -$ -$ -$ 1,632.00$
-$ -$ -$ -$
Grout 10 EA 20.00 -$ -$ 200.00$ -$
-$ -$ -$ -$
Flooring 1 LS 3,959.00 -$ 3,959.00$ -$ -$
-$ -$ -$ -$
Electrical 1 LS 1,360.00 18,272.00 -$ 19,632.00$ -$ -$
-$ -$ -$ -$
Paint 1 LS 4,500.00 -$ 4,500.00$ -$ -$
-$ -$ -$ -$
Door and Door Hardware 1 LS 2,383.00 -$ -$ 2,383.00$ -$
-$ -$ -$ -$
Door Installation 4 HRS 102.00 -$ -$ -$ 408.00$
-$ -$ -$ -$
Dump Fees and Trailer 1 LS 200.00 200.00$ -$ -$ -$
-$ -$ -$ -$
Tile Grout 2 HRS 102.00 -$ -$ -$ 204.00$
-$ -$ -$ -$
Toilet (Kohler 84325)1 LS 180.00 731.13 -$ -$ 180.00$ 731.13$
-$ -$ -$ -$
New Flush Valve w/Sensor - add $347 -$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
*TOTALS 200.00$ 28,091.00$ 2,763.00$ 5,015.13$
Docusign Envelope ID: C25FA4F8-E33D-86B7-827D-CBC596D54968
BELSAAS & SMITH CONSTRUCTION
SHEET 2 of 2 C.O.P. #18
CHANGE ORDER PROPOSAL BREAKDOWN SHEET
EQUIP SUB MATERIAL LABOR
COST COST COST COST
TOTALS FROM PREVIOUS PAGE 200.00$ 28,091.00$ 2,763.00$ 5,015.13$
OVERHEAD 3%6.00$ 842.73$ 82.89$ 150.45$
PROFIT 10%20.60$ 2,893.37$ 284.59$ 516.56$
BONDING 1.5%3.40$ 477.41$ 46.96$ 85.23$
SUB TOTAL 230.00$ 32,304.51$ 3,177.44$ 5,767.37$
SUB TOTAL 230.00$ 32,304.51$ 3,177.44$ 5,767.37$
LABOR 5,767.37$
MATERIAL 3,177.44$
EQUIPMENT 230.00$
SUBCONTRACTORS 32,304.51$
SUB TOTAL SUB TOTAL 41,479.32$
PREVIOUS CO ALLOWANCE
GRAND TOTAL TOTAL 41,479.32$
TIME EXTENTION REQUIRED:
NOTICE TO PROCEED REQUIRED BY:
WE RESERVE OUR RIGHTS UNDER THE CONTRACT TO ACCESS THIS CHANGE
CUMULATIVELY AS IT AFFECTS TIME AND AMOUNT.
4/21/26