AGENDA STAF'T REPORT
AGENDA DATE:March 17,2026
ACTION REQUESTED: Request Board of County Commissioners' approval to sign Change
Order No. 9 on the Jail Renovation Project.
BACKGROUIID:The County has been working on the renovations and improvements
to the existing Kittitas County Jail and as part of that will be moving
Probation to the Courthouse. The move will require installing a
secure counter and entrance to the new area.
INTERACTION:Knit Architects, and Corrections Staff
RECOMMENDATION:Recommend Boards approval to for Facilities and Waste operation
Director to sign Change Order No. 9 for Kittitas County Jail Facilities
Renovation.
HANDLING:Original - Clerk of the Board
ATTACHMENTS:
LEAD STAFF:
Change Order 9
Patti Stacey
Docqslg n E nvelope I D: 26606884-397 1 -&33'€7 97'.983D81 2 FDC06
Change Order
.WAIA Document G7o{' - 2017
PROJECT: (Nane and ad*ess)
230076 Kittitas Couty Jail Faciliries
Rpnwation Task I
205 West Sth Avenue
Ellensburg, WA 98926
CONTRACT NFORIIAIION:
Cootract For; Renovation
Date:04-30-2025
CHANGE ORDER I}IFORMATION:
Change Ordet Nurnbet 009
Date:02-26-2026
CONTRACTOR (Name and address)
Belsaas & $mith Constuction, lnc,
103 East 4th Aveuue, Ste: 209
Ellensburc^ WA 98926
OW,IER: (Name and ad&ess)
Kiuitas County
2205 West 5thAveouo
E[eosbuc. WA 98926
ARCHITECT: (Name and address)
KMT
7826 Leary WayNE #200
Redmond^ WA 98052
The original Contract Sumwas
1Xe n61 6hange by previously authorized Cbange Orders
The Cootract Sumpriortothis Change Orderwas
The Cortract Sumwill be increased by this Change Order in lhe amount of
The uerv Contract Sum including this Change Order rvill be
TI{E CONTRACT IS CHANGED AS FOLLOWS:
Snsert a detailed ducription of the chmge and, if applicable, attach or reference speciJic mhibits. Also include agreed upon
a{justments anributable to elrecuted Construction Change Directives,)
This change order includes General Cotrtrsctor's change order proposals COP #17 - Cornrnissionet's Office.
2,457,000.00
t.244.972.36
3,701,972.36
28-482.39
3.730,454.15
The Contract Time will be unchalged by Zero (0) days.
The new date of Substantial Completioa will be Unchanged
NOTE: This Change Ordet does aot include adjustments to fhe Contract Sum or Guarauteed Maximum Friceo or the Contract Time,
tbat bave beefl authorized by Constuctiou Change Directive until the cost and time bave been agreed upon by both the Orvner and
Contractor, in which case a Change Order is executed to supersede the Construction Change Directive.
NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER.
by:gignsd by:
hl,,rn ilwhnow 6.0( C-o.l.so,t Pgp M.".0-'*frgS*,
BYI John Anderson, Principal
(Signature)
BY: Scott Carlson, Project Manager BY: Patti Stacey,Waste
(Printed name, title, and license
number ifrequired)
3/L0/2026
(Printed nane and title)Operations Director
3/s/2026
(Printed name and title)
/8 Zaz
Date
Date Date
1
Docueisn Envelope lD: 26606884-3971-4833€797€B3D812FDC06
alLSttcoSEor{
p.o. Box 926 / 700 EAST MOUNTAIN VIEW AVE, SUIrE 504
ELLENSBURG, WA 98926
Or 509-925-9747 Ct 6t9-278'8554
scottc@belsmith.com
February L9,2026
Re: Commissioners Office
Per your request, we are pleased to offer the following change order proposal #L7 (COP 17)
lf approved, Belsaas and Smith's onsite team will renovate the Commissioners Office and
prepare it for the Probation Department. This will include:
o Constructing two walls in the front entry space
o lnstalling two transaction windows
o Replacing the glass in the existing front counter with MDF and staining to match
o Replacing the countertop in the existing front counter
o lnstalling a locking door into the Probation space
Total cost of proposal: Twenty-Eight Thousand Four Hundred Eighty-Two Dollars 5Zg,qgZ.39 +
WSST
Time extension required: 0 days
Sincerely,
Scott Carlson
Belsaas & Smith Construction
Docusign Envelope I D: 2660688A-3971 -48338797-9B3D81 2FDCG
BELSAAS & SMITH CONSTRUCTION
CHANGE ORDER PROPOSAL BREAKDOWN SHEET
TOTALS
SHEET 1 of 2 c.o.P.#17
$00
$
$
$
$
$
$
$
$
$ 2.750.00
$
$
$
$
$
$
$ 1,200.00
$ 3.500.00
$ 2,500.00
$
$
$ 850.00
$
$ 1.800.00
$
$ 750.00
$
$
$
LABOR
COST
$ 3,500.00
$
$
$
s
$
$
$
$
$ 200.00
$ 2.200.00
$
$
$
$
$
$
$
$
$
$ 2,891.00
$
$
$
$
$
$
MATERIAL
COST
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$ 2.626.40
$
$
$
$
$
$
$ 2.626.40
SUB
COST
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
s
$
$
$
$
$
$
EQUIP
COST
$
$
$
$
$
$
$
$
$
$
2.750.OO
850.00
1.800.00
750.00
LABOR
3.500.00
1.200.00
3.500.00
2.500.00
EQUIP
UNIT COSTS
Mat.
200.00
2.200.00
2.891.00
LS
UNIT
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS1
1
QUAN
1
1
1
1
1
1
1
1
1
Doors and Hardware
Door and Trim Stain
Securitv Glass
Caroentrv
Cleanino
DESCRIPTION
Probabtion Office
General Conditions
Demo and Dispoal
Framinq
Drvwdll
Paint
lnsulation
#
Docusign Envelope lD: 2660688A€97 1483+8797-9B3D812FDCS
BELSAAS & SMITH CONSTRUCTION
CHANGE ORDER PROPOSAL BREAKDOWN SHEET
TIME EXTENTION REQUIRED:
NOTICE TO PROCEED REQUIRED BY:
SHEET 2 of 2 c.o.P.#17
WE RESERVE OUR RIGHTS UNDER THE CONTRACT TO ACCESS THIS CHANGE
CUMULATIVELY AS IT AFFECTS TIME AND AMOUNT.
$ 16,850.00
$ 286.37
$
$ 1,735.55
s 19.377.42
$ 19.377.42
s 19.377.42
$ 6.084.62
$ 3.020.35
$ 28,482.39
$ 28,482.39
LABOR
COST
$ 505.50
$ 5.291.00
89.92s
$ 544.97
$ 6.084.62
MATERIAL
COST
s 158.73
$ 6,084.62
$ 2.626.40
$ 270.52
44.64$
SUB TOTAL
TOTAL
SUB
COST
$ 78.79
$ 3.020.35
$ 3.020.35
$
$
EQUIP
COST
$
$
$
$
MATERIAL
EQUIPMENT
SUBCONTRACTORS
SUB TOTAL
PREVIOUS COALLOWANCE
GRAND TOTAL
TOTALS FROM PREVIOUS PAGE
OVERHEAD 3%
PROFIT 1O%
BONDING 1.5%
SUB TOTAL
SUB TOTAL
LABOR
IIIIIIII
-
I