HomeMy WebLinkAboutChange Order 9 Fully ExecutedKITTITAS COT]NTY Board of County Commissioners AGENDA STAF'T REPORT AGENDA DATE:March 17,2026 ACTION REQUESTED: Request Board of County Commissioners' approval to sign Change Order No. 9 on the Jail Renovation Project. BACKGROUIID:The County has been working on the renovations and improvements to the existing Kittitas County Jail and as part of that will be moving Probation to the Courthouse. The move will require installing a secure counter and entrance to the new area. INTERACTION:Knit Architects, and Corrections Staff RECOMMENDATION:Recommend Boards approval to for Facilities and Waste operation Director to sign Change Order No. 9 for Kittitas County Jail Facilities Renovation. HANDLING:Original - Clerk of the Board ATTACHMENTS: LEAD STAFF: Change Order 9 Patti Stacey Docqslg n E nvelope I D: 26606884-397 1 -&33'€7 97'.983D81 2 FDC06 Change Order .WAIA Document G7o{' - 2017 PROJECT: (Nane and ad*ess) 230076 Kittitas Couty Jail Faciliries Rpnwation Task I 205 West Sth Avenue Ellensburg, WA 98926 CONTRACT NFORIIAIION: Cootract For; Renovation Date:04-30-2025 CHANGE ORDER I}IFORMATION: Change Ordet Nurnbet 009 Date:02-26-2026 CONTRACTOR (Name and address) Belsaas & $mith Constuction, lnc, 103 East 4th Aveuue, Ste: 209 Ellensburc^ WA 98926 OW,IER: (Name and ad&ess) Kiuitas County 2205 West 5thAveouo E[eosbuc. WA 98926 ARCHITECT: (Name and address) KMT 7826 Leary WayNE #200 Redmond^ WA 98052 The original Contract Sumwas 1Xe n61 6hange by previously authorized Cbange Orders The Cootract Sumpriortothis Change Orderwas The Cortract Sumwill be increased by this Change Order in lhe amount of The uerv Contract Sum including this Change Order rvill be TI{E CONTRACT IS CHANGED AS FOLLOWS: Snsert a detailed ducription of the chmge and, if applicable, attach or reference speciJic mhibits. Also include agreed upon a{justments anributable to elrecuted Construction Change Directives,) This change order includes General Cotrtrsctor's change order proposals COP #17 - Cornrnissionet's Office. 2,457,000.00 t.244.972.36 3,701,972.36 28-482.39 3.730,454.15 The Contract Time will be unchalged by Zero (0) days. The new date of Substantial Completioa will be Unchanged NOTE: This Change Ordet does aot include adjustments to fhe Contract Sum or Guarauteed Maximum Friceo or the Contract Time, tbat bave beefl authorized by Constuctiou Change Directive until the cost and time bave been agreed upon by both the Orvner and Contractor, in which case a Change Order is executed to supersede the Construction Change Directive. NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER. by:gignsd by: hl,,rn ilwhnow 6.0( C-o.l.so,t Pgp M.".0-'*frgS*, BYI John Anderson, Principal (Signature) BY: Scott Carlson, Project Manager BY: Patti Stacey,Waste (Printed name, title, and license number ifrequired) 3/L0/2026 (Printed nane and title)Operations Director 3/s/2026 (Printed name and title) /8 Zaz Date Date Date 1 Docueisn Envelope lD: 26606884-3971-4833€797€B3D812FDC06 alLSttcoSEor{ p.o. Box 926 / 700 EAST MOUNTAIN VIEW AVE, SUIrE 504 ELLENSBURG, WA 98926 Or 509-925-9747 Ct 6t9-278'8554 scottc@belsmith.com February L9,2026 Re: Commissioners Office Per your request, we are pleased to offer the following change order proposal #L7 (COP 17) lf approved, Belsaas and Smith's onsite team will renovate the Commissioners Office and prepare it for the Probation Department. This will include: o Constructing two walls in the front entry space o lnstalling two transaction windows o Replacing the glass in the existing front counter with MDF and staining to match o Replacing the countertop in the existing front counter o lnstalling a locking door into the Probation space Total cost of proposal: Twenty-Eight Thousand Four Hundred Eighty-Two Dollars 5Zg,qgZ.39 + WSST Time extension required: 0 days Sincerely, Scott Carlson Belsaas & Smith Construction Docusign Envelope I D: 2660688A-3971 -48338797-9B3D81 2FDCG BELSAAS & SMITH CONSTRUCTION CHANGE ORDER PROPOSAL BREAKDOWN SHEET TOTALS SHEET 1 of 2 c.o.P.#17 $00 $ $ $ $ $ $ $ $ $ 2.750.00 $ $ $ $ $ $ $ 1,200.00 $ 3.500.00 $ 2,500.00 $ $ $ 850.00 $ $ 1.800.00 $ $ 750.00 $ $ $ LABOR COST $ 3,500.00 $ $ $ s $ $ $ $ $ 200.00 $ 2.200.00 $ $ $ $ $ $ $ $ $ $ 2,891.00 $ $ $ $ $ $ MATERIAL COST $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ 2.626.40 $ $ $ $ $ $ $ 2.626.40 SUB COST $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ s $ $ $ $ $ $ EQUIP COST $ $ $ $ $ $ $ $ $ $ 2.750.OO 850.00 1.800.00 750.00 LABOR 3.500.00 1.200.00 3.500.00 2.500.00 EQUIP UNIT COSTS Mat. 200.00 2.200.00 2.891.00 LS UNIT LS LS LS LS LS LS LS LS LS LS1 1 QUAN 1 1 1 1 1 1 1 1 1 Doors and Hardware Door and Trim Stain Securitv Glass Caroentrv Cleanino DESCRIPTION Probabtion Office General Conditions Demo and Dispoal Framinq Drvwdll Paint lnsulation # Docusign Envelope lD: 2660688A€97 1483+8797-9B3D812FDCS BELSAAS & SMITH CONSTRUCTION CHANGE ORDER PROPOSAL BREAKDOWN SHEET TIME EXTENTION REQUIRED: NOTICE TO PROCEED REQUIRED BY: SHEET 2 of 2 c.o.P.#17 WE RESERVE OUR RIGHTS UNDER THE CONTRACT TO ACCESS THIS CHANGE CUMULATIVELY AS IT AFFECTS TIME AND AMOUNT. $ 16,850.00 $ 286.37 $ $ 1,735.55 s 19.377.42 $ 19.377.42 s 19.377.42 $ 6.084.62 $ 3.020.35 $ 28,482.39 $ 28,482.39 LABOR COST $ 505.50 $ 5.291.00 89.92s $ 544.97 $ 6.084.62 MATERIAL COST s 158.73 $ 6,084.62 $ 2.626.40 $ 270.52 44.64$ SUB TOTAL TOTAL SUB COST $ 78.79 $ 3.020.35 $ 3.020.35 $ $ EQUIP COST $ $ $ $ MATERIAL EQUIPMENT SUBCONTRACTORS SUB TOTAL PREVIOUS COALLOWANCE GRAND TOTAL TOTALS FROM PREVIOUS PAGE OVERHEAD 3% PROFIT 1O% BONDING 1.5% SUB TOTAL SUB TOTAL LABOR IIIIIIII - I