AGENDA STAFF REPORT
March 17,2026
Request to Approve a Resolution Authorizing the Chair's
Signature on the Local Agency Federal Aid Project
Prospectus for the Horizontal Curve Safety Project CRP
3t9-23.
BACKGROUND:The Horizontal Curve Safety Project was selected to
receive Federal Funding through the Highway Safety
Improvement Program (HSIP). Kittitas County Public
Works has inventoried horizontal curves countywide and
selected ten (10) roadway segments for implementation of
improved roadside signing, including advisory speeds,
chevron affow signs, and the addition of flexible guideposts
to increase driver awareness. All the improvements are
focused on helping reduce accidents and injuries on the
road system.
This project is eligible for one hundred percent (100%)
Federal Funding for all phases authorized prior to April 30,
2026. This Project Prospectus covers the Federal Funding
for the Construction phase of the project.
Public Works is finalizing construction documents
targeting a May 21,2026, advertisement.
INTERACTION:Public Works
RECOMMENDATION: Approve the Resolution Authorizingthe Chair's signature
on the Local Agency Federal Aid Project Prospectus for the
Horizontal Curve Safety Project CRP 319-23.
HANDLING:
ATTACHMENTS:
LEAD STAFF:
Return one original to Public Works
Resolution, Local Agency Federal Aid Project Prospectus
Josh Fredrickson, Public Works Director
BOARD OF COI.]NTY COMMISSIONERS
COUI\TY OF KITTITAS
STATE OT'WASHINGTON
RESOLUTION NO. 2026 -o58
AUTHORIZING THE CHAIR'S SIGNATURE ON THE LOCAL AGENCY FEDERAL
AID PROJECT PROSPECTUS CONSTRUCTION PHASE FOR THE HORIZONTAL
CURVE SAFETY PROJECT CRP 319-23
WIIEREAS: The Horizontal Curve Safety Project was awarded Federal Funding through the
2023Highway Safety Improvement Program; and
WIIEREAS: The Funding will be used for the construction phase to implement the
improvements on ten (10) identified roadway segments chosen; and
WHEREAS: In preparation to begin work, Kittitas County Public Works is requesting the
Washington State Department of Transportation release the Federal Funds for
construction; and
WHEREAS:A Local Agency Federal Aid Project Prospectus must be executed by the Chair
of the Board of County Commissioners acknowledging the project has been
reviewed and is consistent with the County's comprehensive plan for community
development;and
NOW, THEREFORE BE IT RESOLVED that the Board of County Commissioners, in the best
interest of the public, does hereby approve the Chair's signature on the Local
Agency Federal Aid Project Prospectus for the Horizontal Curve Safety Project
cRP 319-23.
DATED on this 17th day of March 2026, at Ellensburg, Washington.
BOARD OF COTINTY
COMMISSIONERS
KITTITAS TON
of the Board- Julie Kjorsvik
ice-Chairman
n Deputy Clerk of the,Board- Mandy Buchholz
o Commissioner
Prefix Route )
FederalAid
Proiect Number
HSIP 000s 678
Local Agency
Project Number
RC 2298
^-W Ys;llffitlli ?l"*i.n
"oorrarion
Local Agency
Project
Federal Aid
Prospectus
WSDOT
0nlyUse )
Date 0310212026
DUNS Number 0r-020-2547
Federal Employer
Tax lD Number 9r-601349
Federal Program Title
Vza.zos X otner
CAAgency
[Z Yes ! ruo
Agency
Kittitas County Public Works
Start Longitude W -120.954167
w -120.012574End Lonqitude
Start Latitude n 47 .1817 26
End Latitude rt47.165419
Project Title
Horizontal Curve Safety Project
Project Zip Code (+4)
98926-7989
Nearest City Name
Ellensburg
Project Termini From-To
countywide countywide
Award Type
M t-ocat! tocat Forces f, state ! Railroad
Length of Project
countywide
End Mile Post
countywide
Begin Mile Post
countywide
County Name
Kittitas
County Number
19
End Mile Point
countywide
City NumberRoute lD Begin Mile Point
countywide
Urban Area NumberCongressional District(s)
8
Legislative District(s)
13
WSDOT Region
South Central Region
Phase
Total
Estimated Cost
(Nearest Hundred Dollar)
Local Agency
Funding
(Nearest Hundred Dollad
Federal Funds
(Nearest Hundred Dollar)
Phase Start
Date
Month Year
P.E.125,000.00 125,000.00 November 2023
R^/v
Const.543,000.00 543,000.00 Apm2026
Total 668,000.00 668,000.00
of Existing Facil (Existing Design and Present Condition)Descri
Number of Lanes
varies
Roadway Width
varies
Many roads havehazardous curves and non standard or non-existent delineation.
Descri on of Proposed Work
Description of Proposed Work (Attach additional sheet(s) if necessary)
Collect data and instal[upgrade signing for horizontal curves (such as advisory speeds, chevrons, delineation).
Local Agency Contact Person
Darren Case
Title
Construction Manager
Phone
509-962-70r9
Mailing Address
411 N. Ruby, Suite I
City
Ellensburg
State
WA
Zip Code
98926
By
Project Prospectus
T1s Director, Public Works Date
Revised 0112022 Previous Editions Obsolete
Agency
Kittitas County Public Works
Project Title
Horizontal Curve Safety Project
Date
0310212026
Type of Proposed Work
Project Type (Check all that Apply)
! t tew Construction n Path / Trail n g-n
! Reconstruction ! Pedestrian / Facilities n Z-n
I Railroao ! Parking Z otner
! arioge
Roadway Width
varies
Number of Lanes
varies
Geometric Design Data
Description Through Route Grossroad
Federal
Functional
Classification
M uroan
M Rural
n ruHs
I PrincipalArterial
Z Minor Arterial
f, collector
f tr,talor Collector
M tvtinor Collector
M Local Access
Z urnan
f, Rural
E runs
n PrincipalArterial
f, MinorArterial
E Collector
Z tvtajor Collector
M Vtinor Collector
f, Local Access
Terrain n rt"t Roll Mountain flrtut nnott nMountain
Posted Speed varles
Design Speed varles
Existing ADT vanes
Design YearADT
Design Year
Design Hourly Volume (DHV)
Performance of Work
Preliminary Engineering Will Be Performed By
County
Others
otto
Agency
100 o/o
Conshuction Will Be Performed By
Contract
Contract
100 %
Agency
otto
Environmental Classification
! Ctass I - Environmental lmpact Statement (ElS)
n Project lnvolves NEPA/SEPA Section 404
lnteragency Agreement
n Ctass lll - EnvironmentalAssessment (EA)
I Project lnvolves NEPA/SEPA Section 404
I nteragency Ag reements
Z Class ll - Categorically Excluded (CE)
! Projects Requiring Documentation
(Documented CE)
Environmental Considerations
Revised 0112022 Previous Editions Obsolete
Agency
Kittitas County Public Works
Project Title
Horizontal Curue Safety Project
Date
0310212026
Right of Way
Z No Right of Way Needed
* All construction required by the
contract can be accomplished
within the existing right of way.
n night of Way Needed
flruo Relocation n Relocation Required
Utilities Railroad
Z llo utility work required
tr nl utility work will be completed prior to the start
of the construction contract
nrut utility work will be completed in coordination
with the construction contract
Z No railroad work required
n rut railroad work will be completed prior to the start of
the construction contract
f] rut the railroad work will be completed in coordination
with the construction contract
Description of Utility Relocation or Adjustments and Existing Major Structures lnvolved in the Project
Utilities will be located and if conflicts are identified, Kittitas County will require relocation prior to the
construction project.
FAA lnvolvement
ls any airport located within 3.2 kilometers (2 miles) of the proposed project? n Yes Z ruo
Remarks
This project has been reviewed by the legislative body of the administration agency or agencies, or it's
designee, and is not inconsistent with the agency's comprehens
Agency
Date obltTlpu
DOT Form 140-101
Revised O1l2O22
By
Previous Editions Obsolete