February 19, 2026
Re: Commissioners Office
Per your request, we are pleased to offer the following change order proposal #17 (COP 17).
If approved, Belsaas and Smith’s onsite team will renovate the Commissioners Office and
prepare it for the Probation Department. This will include:
•Constructing two walls in the front entry space
•Installing two transaction windows
•Replacing the glass in the existing front counter with MDF and staining to match
•Replacing the countertop in the existing front counter
•Installing a locking door into the Probation space
Total cost of proposal: Twenty-Eight Thousand Four Hundred Eighty-Two Dollars $28,482.39 +
WSST
Time extension required: 0 days
Sincerely,
Scott Carlson
Belsaas & Smith Construction
Docusign Envelope ID: 26606B8A-3971-4833-8797-9B3D812FDC06
BELSAAS & SMITH CONSTRUCTION
SHEET 1 of 2 C.O.P. #17
CHANGE ORDER PROPOSAL BREAKDOWN SHEET
UNIT COSTS EQUIP SUB MATERIAL LABOR
#DESCRIPTION QUAN.UNIT Mat.EQUIP LABOR COST COST COST COST
Probabtion Office
General Conditions 1 LS 3,500.00 -$ -$ -$ 3,500.00$
-$ -$ -$ -$
Demo and Dispoal 1 LS 1,200.00 -$ -$ -$ 1,200.00$
-$ -$ -$ -$
Framing 1 LS 3,500.00 -$ -$ -$ 3,500.00$
-$ -$ -$ -$
Drywall 1 LS 2,500.00 -$ -$ -$ 2,500.00$
-$ -$ -$ -$
Paint 1 LS 2,750.00 -$ -$ -$ 2,750.00$
-$ -$ -$ -$
Insulation 1 LS 200.00 -$ -$ 200.00$ -$
-$ -$ -$ -$
Doors and Hardware 1 LS 2,200.00 850.00 -$ -$ 2,200.00$ 850.00$
-$ -$ -$ -$
Door and Trim Stain 1 LS 1,800.00 -$ -$ -$ 1,800.00$
-$ -$ -$ -$
Security Glass 1 LS 2,891.00 -$ -$ 2,891.00$ -$
-$ -$ -$ -$
Carpentry 1 LS -$ 2,626.40$ -$ -$
-$ -$ -$ -$
Cleaning 1 LS 750.00 -$ -$ -$ 750.00$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
*TOTALS -$ 2,626.40$ 5,291.00$ 16,850.00$
Docusign Envelope ID: 26606B8A-3971-4833-8797-9B3D812FDC06
BELSAAS & SMITH CONSTRUCTION
SHEET 2 of 2 C.O.P. #17
CHANGE ORDER PROPOSAL BREAKDOWN SHEET
EQUIP SUB MATERIAL LABOR
COST COST COST COST
TOTALS FROM PREVIOUS PAGE -$ 2,626.40$ 5,291.00$ 16,850.00$
OVERHEAD 3%-$ 78.79$ 158.73$ 505.50$
PROFIT 10%-$ 270.52$ 544.97$ 1,735.55$
BONDING 1.5%-$ 44.64$ 89.92$ 286.37$
SUB TOTAL -$ 3,020.35$ 6,084.62$ 19,377.42$
SUB TOTAL -$ 3,020.35$ 6,084.62$ 19,377.42$
LABOR 19,377.42$
MATERIAL 6,084.62$
EQUIPMENT -$
SUBCONTRACTORS 3,020.35$
SUB TOTAL SUB TOTAL 28,482.39$
PREVIOUS CO ALLOWANCE
GRAND TOTAL TOTAL 28,482.39$
TIME EXTENTION REQUIRED:
NOTICE TO PROCEED REQUIRED BY:
WE RESERVE OUR RIGHTS UNDER THE CONTRACT TO ACCESS THIS CHANGE
CUMULATIVELY AS IT AFFECTS TIME AND AMOUNT.