HomeMy WebLinkAboutChange Order 03PROJECT NAME: Ellensburg Rodeo Arena Completion
OWNER: Kittitas County
CONTRACTOR: Cascade Central Construction
PROJECT NO: 2025-009
Amount
$7,573.49
$65,888.37
$41,806.43
Total This Change Order:$115,268.29
$5,065,000.00 *
$221,986.49
$5,286,986.49 By:
$115,268.29 Date
$5,402,254.78
7/20/2026
By:
3
Date
7/20/2026
7/23/2026 By:
8/22/2026 Date
COP 11 - RFI 028 - Buckaroo Seating Switch
Previously Approved Increases in Time:
Completion Date Prior to This Change Order:
Accepted by Contractor:
Revised Contract Sum:
COP 12 - RFP 02 - Hydrant Adds & Concourse Revisions
Revised Final Acceptance Date:
Approved by Owner:
ALSC Architects, P.S.
Net Amount of Previously Approved Changes:
Revised Substantial Completion Date:
CHANGE ORDER NO. 3
PAGE 1 of 12
DESCRIPTION OF CHANGE:
Contract Sum is increased by This Change Order:
Contract Sum Prior to This Change Order:
Original Contract Sum
COP 17 - RFP 04 - Civil City Comments
*Does not include State or Local Sales Tax ALSC Architects | We bring our clients’ stories to life.
Recommended By:
Original Contract Completion Date:
Contract time will be changed by 0
Calendar Days This Change Order
PROPOSAL
P.O. Box 119
Wenatchee, WA. 98807-0119
Phone 509-662-7119
Fax 509-662-6380
To:PROJECT:Ellensburg Rodeo Arena Improvements
Kittitas County Commissioners COP#11
205 West 5th Ave, Suite 108 DATE:January 27, 2026
Ellensburg, WA 98926 TITLE:RFI 028 - Buckaroo Seating Switch Rev.1
Date DESCRIPTION QUANITITY UOM UNIT PRICE AMOUNT
1/27/2026
1 LS 12,313.00$ $6,378.00
$382.68
6,760.68
1/27/2026
0 HR 128.18$ $0.00
2 HR 161.54$ $323.08
2 HR 116.25$ $232.50
0 HR 210.00$ $0.00
$83.34
638.92
7,399.60
$70.30
$103.59
TOTAL $7,573.49
MAKE CHECKS PAYABLE TO:
Cascade Central Construction, LLC
P.O Box 119
Wenatchee, WA. 98807-0119
THANK YOU FOR YOUR BUSINESS!
Schedule Impact:
None if approved by 1/9/25.
General Contractor - Sub Total
Subtotal
Bond
B&O Tax
15% Mark-up
Project Engineer
Surveyor
Cascade Central Construction Cost
Project Management & Coordination
Supervision
Subcontractor Cost
Electrical Subcontractor - See attached Back-up
Subcontractor - Sub Total
6% Mark-up
None if approved by 2/6/26
Project Name:COP-12R1
Project No.1/27/2026
Description:
a.2,780.70$
b.-$
c.-$
DIRECT LABOR SUBTOTAL 2,780.70$
d.
e.55.61$
2,836.00$
a.2,502.70$
b.
2,503.00$
a.-$
b.
-$
a.141.80$
142.00$
5,481.00$
a.876.96$
b.-$
877.00$
a.
b.
c.
d.-$
-$
a.-$
-$
-$
a.0.15 % of 1 4.25$
b.0.25 % of 1-7 15.90$ 20.15$
a.0.03 % of 1-8 -$
6,378.00$ Form Revised 04/25/15
6. SUB-SUBCONTRACTORS
TOTAL COST
bond
payroll driven liability insurance
volume driven liability insurance 8. INSURANCE
9. BOND
9. BOND
small tools (NTE 5% of 1a & b)
7. OVERHEAD & PROFIT ON SUB-SUBCONTRACTORS
NTE 15% of Line 6 up to $50,000 for each sub
8. INSURANCE
5. OVERHEAD & PROFIT
6. SUB-SUBCONTRACTORS
SUBTOTAL 1 thru 4
7. OVERHEAD & PROFIT ON SUB-SUBCONTRACTORS
owned equipment (per spec approved source)
5. OVERHEAD & PROFIT
4. SMALL TOOLS
rental equipment (per invoices attached)
2. MATERIAL COSTS
3. EQUIPMENT COSTS
4. SMALL TOOLS
material costs
Jack McGann
Contractor:
Ellensburg Rodeo Arena Improvements RFI-028
McGann Electric
Source Documents:
Provide and install 1 - 1.5" UG conduit from MDPL to 100A event switch location at buckaroo seating section.Only requesting
length from MDPL to L1TB. Provide and install 100A added breaker in panel MDPL. Provide and install 100A added feeder
without Neutral in updated one-line drawing and MDPL panel schedule per RFI-028 response. All conduit, fittings, supports,
hardware, wire, disconnect switch, fuses included. Exclusions: trenching and backfill.
Itemize all costs on attached COP Cost Breakdown form.
crew (apprentices, journeymen, & laborers)
foreman
superintendent
Direct Labor Costs:
1. CRAFT LABOR COSTS
safety (NTE 2% of lines 1a, b, & c)
direct supervision (NTE 15% of 1a)
Supervision:
1. CRAFT LABOR COSTS
3. EQUIPMENT COSTS
NTE 15% portion of 1, 2, 3, & 4 up to $50,000
CCC
Contractor Breakdown Summary
McGann Electric
freight costs (itemize)
2. MATERIAL COSTS
Date:
Contractor Ref. No.
https://mcgannelectric-my.sharepoint.com/personal/jackmcgann_mcgannelectric_com/Documents/McGann Electric/2025 Ellensburg Rodeo 9.30/COPs/COP 12 100amp
feeder added rfi 28/Ellensburg Rodeo Arena COP-12 - Copy Summary Issued 1/27/2026
Project Name:COP-12R1
Project No.1/27/2026
Contractor:
Unit Labor Material Equipment Total
Description Quantity Type Unit $Cost Unit $Cost Unit $Cost Cost
-$ -$ -$ -$
-$ -$ -$ -$
Electrician Labor 26 HR $106.95 2,780.70$ -$ -$ 2,780.70$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
100A 3P PDD23G0100 breaker 1 EA -$ $1,490.00 1,490.00$ -$ 1,490.00$
100A 3pole MDPL provisions 1 LT -$ $300.00 300.00$ -$ 300.00$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
1.5" PVC 70 EA -$ $1.12 78.40$ -$ 78.40$
1.5" PVC coupling 7 EA -$ $2.10 14.70$ -$ 14.70$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
#1 thwn 200 FT -$ $2.65 530.00$ -$ 530.00$
#6 thwn 80 FT -$ $1.12 89.60$ -$ 89.60$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
Labor Subtotal 2,780.70$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
2,780.70$ 2,502.70$ -$ 5,283.40$ Subtotal Cost of Work
Ellensburg Rodeo Arena Improvments RFI-028
Cost Breakdown
McGann Electric
2/1/2017
Contractor Ref. No.
Date:
https://mcgannelectric-my.sharepoint.com/personal/jackmcgann_mcgannelectric_com/Documents/McGann Electric/2025 Ellensburg Rodeo 9.30/COPs/COP 12 100amp feeder added rfi 28/Ellensburg Rodeo Arena COP-12 - CopyCost Breakdown Issued 1/27/2026
83
,5
,
5
+:
+:
+
-
/7%
(9(1732:(5
&211(&7,2132,17
&:),%(5)255()(('
2)$5(1$),%(55,1*72
*5$1'67$1'6
35(66%2;
'(0$5&32,17$1'&)25
)$&211(&7,2172
$1181&,$725,135(66%2;
%8&.$522
6 ($7,1*
6(&7,21
7($1$:$< 807$180+$//+,6725,&0$,1*5$1'67$1'
6287+($67
$5(1$6($7,1*
*2/'
%8&./(
&/8%
3(16
*5$9(/3$7,2
1257+($67$5(1$6($7,1*
%8&.,1*&+87(6
&21&(66,216
52'(2$5(1$
*1(
1(:3$)86('
6:,7&+(9(17$9
(
8*)(('(5)25
(9(17$96:,7&+
The event switch was not
shown on the 1line nor
panel schedules originally-
thus we interpreted this
drawing to depict the event
switch being fed via L1TB
and not MDPL- that is why
we are requesting some
feeder costs.
ALSC Architects \\ We bring our clients’ stories to life.
REQUEST FOR PROPOSAL NO: 01
Project Name: Ellensburg Rodeo Arena Completion
Owner: Kittitas County
Contractor: Cascade Central Construction
Job Number: 2025-009
Page 1 of 10
TO: Cascade Central Construction, Contractor, please furnish your proposal for performing the changes outlined
below and/or detailed on the attachments referred to:
• Addition of 3 yard hydrants for RV/ Vendor spots.
• Revision to concourse slabs at stadia stairs.
ALSC Architects, P.S. By Todd Keller Date: 12/11/25
PROPOSAL:
To the Owner: We propose to perform all changes described in the above request for a total ADDITION/DEDUCTION
(cross out one) to the contract sum of:
$
(not including Sales Tax)
We have attached cost estimate detail sheets, and the foregoing amount covers all direct and indirect costs related to
this proposal and to the effect of the proposal on the remainder of the project. All other provisions of the contract
remain in full force and effect. We request the completion date be EXTENDED/REDUCED (cross one out) ________
calendar days because of this work. The Contractor agrees to be bound to this proposal quotation for sixty (60) days
after this date.
By Date
Contractor
RECOMMENDATION:
TO: Owner, we have examined the foregoing proposal and find it to be appropriate for the request. We recommend
its acceptance.
ALSC Architects, P.S. By Date:
PROPOSAL ACCEPTANCE:
The Owner hereby accepts the foregoing proposal. This instrument, when signed below, constitutes the conditions
upon which a Change Order will be issued.
By Date
Owner
02
Sixty Five Thousand Eight Hundred Eighty-Eight Five and 37/100 Dollars
0
See attached proposal for conditions.
KC Carroll 1/27/26Cascade Central Construction, LLC.
$65,888.37
PROPOSAL
P.O. Box 119
Wenatchee, WA. 98807-0119
Phone 509-662-7119
Fax 509-662-6380
To:PROJECT:Ellensburg Rodeo Arena Improvements
Kittitas County Commissioners COP#12
205 West 5th Ave, Suite 108 DATE:January 27, 2026
Ellensburg, WA 98926 TITLE:RFP 02 Hydrant Adds & Concourse SOG Rev. Rev.2
Date DESCRIPTION QUANITITY UOM UNIT PRICE AMOUNT
1/27/2026
1 LS 24,850.00$ $24,850.00
1 LS 24,850.00$ $32,900.00
3,465.00
61,215.00
1/27/2026
4 HR 128.18$ $512.72
2 HR 161.54$ $323.08
2 HR 116.25$ $232.50
8 HR 210.00$ $1,680.00
412.25
3,160.55
64,375.55
$611.57
$901.26
TOTAL $65,888.37
MAKE CHECKS PAYABLE TO:
Cascade Central Construction, LLC
P.O Box 119
Wenatchee, WA. 98807-0119
THANK YOU FOR YOUR BUSINESS!
Schedule Impact:
None if approved by 2/2/26.
General Contractor - Sub Total
Subtotal
Bond
B&O Tax
Subcontractor Cost
Earthwork Subcontractor - See attached Back-up
Concrete Subcontractor - See attached Back-up
Subcontractor - Sub Total
6% Mark-up
15% Mark-up
Project Engineer
Surveyor - hydrants only
Cascade Central Construction Cost
Project Management & Coordination
Supervision
CCC's surveyor will give Concrete subcontractor the slab
points but concrete subcontractor has additional time
setting forms to the extra elevation points.
t
P.O. Box 119 Wenatchee, WA 98807
Phone: (509)662-7119 Fax: (509)662-4465
Bid Items Quantity Unit Unit Price Amount
1 RFP 02 - 1" Copper Water Service Piping & 3 Yard Hydrants 110 LF 175.00$ $19,250.00
RFP 02 - Flat Stair Pads 8 EA 1,400.00$ $11,200.00
$30,450.00
$30,450.00
Qualifications: Please Read Carefully
1. Washington State Sales Tax has been not been included in proposal.
2. Prevailing Wage has been accounted for in proposal.
3.
4.
5. Excludes Water System Support.
6. Exludes Construction Survey.
7. Engineering & Professional Surveying Services are Excluded.
8.
9.
10.
11.
12.
13. Any scope of work not specifically included as a line item in this proposal is excluded.
14.
15.
16.
Sincerely,
SELLAND CONSTRUCTION, INC.
Ron Zerr III
(509) 961-7825
Bid Date: January 13, 2026
Ellensburg Rodeo Arena Improvements - RFP 02 COP
Erosion Control Inspections, Reporting, Monitoring & Maintenance are Excluded. Stormwater Permit by others.
Rock excavation (i.e. Solid Rock, Caliche, Hard Pan, Cemented Soils and/or Boulders larger than 1 Cubic Yard) have not been included. Price Negotiation will be
required if these materials are encountered.
Subtotal
Over Excavation of Unsuitable Material has not been accounted for, price negotiation will be required if these materials are encountered.
Actual quantities installed shall be tracked/measured and the basis of payment at the unit prices included in this proposal unless otherwise agreed.
Due to global supply chain disruptions and market volatility we reserve the exclusive right to adjust our proposal for material escalation.
Proposal is valid for 30 days. This proposal shall be made part of any subcontract.
Total
If you have any questions or need additional information with regard to our proposal please give us a call.
Dust control has been provided while we are actively working the site. No permanent or sustained dust control or mitigation has been included.
Fees for Utilities, County, City, Etc. are not included. Cultural Resource Services are not covered in our scope.
Hazardous Materials Abatement, Removal, Handling, Disposal, etc. are not expected onsite and are therefore Excluded.
Watering & Dust Control are Included for Selland's scope of work and duration only. No OT Dust Control or beyond our work.
SELLAND
INC.
CONSTRUCTION
General Contractors
Page 1 of 1
Where is this coming
from? Flatwork shall
conform to the
requirements of the
specifications with
regard to tolerance.
Would be more cost effective to pour
extra concrete at landings with gravel
grading consistent through out.
Revise
Regarding Flat Stair Pads: Because the stadium contractor needs each of the stair pad ares to
be perfectly flat with no allowable variance, the added cost is for laborers to hand grade each
pad area and ensure they are perfectly flat. This is going to take more time and labor
throughout the concourse slab than originally anticipated from the bid documents.
revise this to 8 EA at $700
each for total of $5,600.00
TOTAL: $24,850
Yes, thank you. Pricing
revised to reflect this.Confrimed.
Item Quantity Unit Unit Price
1
180 HR 94.00$
132 HR 94.00$
1 EA 3,572.00$
32,900.00$
0.00% 0.00
32,900.00$
Additional 11 Hours x 12 Guys x 1 Additional Pour 12,408.00$
Additional 5 Hours x 12 Guys x 3 Original Pours (Additional Time for Hand Screed)16,920.00$
Jones Concrete & Excavation
Estimator - Carson Chester
Sub Total
TOTAL
541-861-8060
SALES TAX
Ellensburg,
Project
Ellensburg Rodeo Improvements
ATTN: General Contractor
Concrete Proposal - RFP #2
Date: 1/19/2026
Project Location
Washington
Amount (US $)Work Description
3,572.00$
Flat Stair Pads Below Grandstands to Include:
Concrete Pump Truck for Additional Pour
Customer:
Authorized Signature:____________________
Name:___________________________
Date of Acceptance:________________
Includes additional time to identify stair locationsusing provided survey points, maintain boundries of flatness &
additional finishing time to confirm proper elevations at each stair pad location. A roller screed provides flat
concrete with less labor. There are too many elevations to be met for a roller screed to be practical. Originally,
there was a ridge along the seating-retaining wall, 5 catch basins to meet, & forms along the outside of the slab.
This has added 32 elevation points that must be met within the center of the slab. This was not a small change.
www.JonesConcrete.pro 1/1
Originally Jones was planning to roller screed the entire slab but these flattened areas
are too small to roller screed and must be done by hand. Please review last
comments and proposal as well. Concrete proposal specified switch from roller
screed to hand screed, not the other way around which seems like was a
misunderstanding during the last review comments.
The first item captures additional manpower required due to the change in screed styles for the crew as a whole. Screeding by hand requires
an additional pour. Screeding by hand will increase truck spacing, pour out time, and screed time for all pours at the concourse slab. The
second item captures additional finishing time at each stair location. The third item is associated with the pump truck for the separate pour.
Concrete contractor time to layout flat boundaries is in addition to the survey time. CCC survey will locate the corners of each
flat area but concrete subcontractor will still need to do the work of setting up forms, setting up string lines, set grade rods, and
confirm exact elevations.
ALSC Architects \\ We bring our clients’ stories to life.
REQUEST FOR PROPOSAL NO: 04
Project Name: Ellensburg Rodeo Arena Completion
Owner: Kittitas County
Contractor: Cascade Central Construction
Job Number: 2025-009
Page 1 of 11
TO: Cascade Central Construction, Contractor, please furnish your proposal for performing the changes outlined
below and/or detailed on the attachments referred to:
• Revisions to Civil drawings per City review comments.
ALSC Architects, P.S. By Todd Keller Date: 1/21/26
PROPOSAL:
To the Owner: We propose to perform all changes described in the above request for a total ADDITION/DEDUCTION
(cross out one) to the contract sum of:
$
(not including Sales Tax)
We have attached cost estimate detail sheets, and the foregoing amount covers all direct and indirect costs related to
this proposal and to the effect of the proposal on the remainder of the project. All other provisions of the contract
remain in full force and effect. We request the completion date be EXTENDED/REDUCED (cross one out) ________
calendar days because of this work. The Contractor agrees to be bound to this proposal quotation for sixty (60) days
after this date.
By Date
Contractor
RECOMMENDATION:
TO: Owner, we have examined the foregoing proposal and find it to be appropriate for the request. We recommend
its acceptance.
ALSC Architects, P.S. By Date:
PROPOSAL ACCEPTANCE:
The Owner hereby accepts the foregoing proposal. This instrument, when signed below, constitutes the conditions
upon which a Change Order will be issued.
By Date
Owner
41,806.43Forty-One Thousand Eight Hundred Six and 43/100 Dollars
0
See attached proposal for qualifications.
Cascade Central Construction KC Carroll 1/25/26
See attached proposal for qualifications.
Todd Keller 1/28/26
PROPOSAL
P.O. Box 119
Wenatchee, WA. 98807-0119
Phone 509-662-7119
Fax 509-662-6380
To:PROJECT:Ellensburg Rodeo Arena Improvements
Kittitas County Comissioners COP#17
205 West 5th Ave, Suite 108 DATE:January 25, 2026
Ellensburg, WA 98926 TITLE:COP 17 - RFP 04 - Civil City Comments Approved Set
Date DESCRIPTION QUANITITY UOM UNIT PRICE AMOUNT
1/25/2026
1 LS 38,534.47$ $38,534.47
2,312.07
40,846.54
1/25/2026
0 HR 128.18$ $0.00
0 WD 925.00$ $0.00
0 HR 161.54$ $0.00
0 HR 116.25$ $0.00
0 HR 63.08$ $0.00
0 HR 119.00$ $0.00
0.00
0.00
40,846.54
$388.04
$571.85
TOTAL 41,806.43
MAKE CHECKS PAYABLE TO:
Cascade Central Construction, LLC
P.O Box 119
Wenatchee, WA. 98807-0119
THANK YOU FOR YOUR BUSINESS!
Schedule Impact:
None if approved by 1/28. Water utility installation is scheduled to begin 2/2/26
and we need time to order materials.
Qualifications:
Pricing assumes existing fire line can be abandoned in place per RFI 053.
Subcontractor Cost
Civil Subcontractor - See attached back-up
General Contractor - Sub Total
Subcontractor - Sub Total
Cascade Central Construction Cost
Project Management & Coordination
Laborer
Carpenter
6% Mark-up
Supervision
General Conditions
15% Mark-up
Subtotal
Bond
B&O Tax
Project Engineer
t
P.O. Box 119 Wenatchee, WA 98807
Phone: (509)662-7119 Fax: (509)662-4465
Bid Items Quantity Unit Unit Price Amount
1 RFP 04 - Utility Changes
-Production Adjustment for 8" C900 to 8" DI Pipe (Bid @ $61.35/LF, Now @ $88.08)225 LF 26.73$ $6,014.25
-Production Adjustment for 4" C900 to 4" DI Pipe (Bid @ $59.31/LF, Now @ $86.04)214 LF 26.73$ $5,720.22
-Material Cost Difference: C900 Water to Ductile Iron 1 LS 19,000.00$ $19,000.00
-Furnish & Install Catch Basins 3 EA 2,600.00$ $7,800.00
$38,534.47
$38,534.47
Qualifications: Please Read Carefully
1. Washington State Sales Tax has been not been included in proposal.
2. Prevailing Wage has been accounted for in proposal.
3.
4.
5. Excludes Water System Support.
6. Exludes Construction Survey.
7. Engineering & Professional Surveying Services are Excluded.
8.
9.
10.
11.
12.
13. Any scope of work not specifically included as a line item in this proposal is excluded.
14.
15.
16.
Sincerely,
SELLAND CONSTRUCTION, INC.
Ron Zerr III
(509) 961-7825
Bid Date: January 22, 2026
Ellensburg Rodeo Arena Improvements - RFP 04 COP
Erosion Control Inspections, Reporting, Monitoring & Maintenance are Excluded. Stormwater Permit by others.
Rock excavation (i.e. Solid Rock, Caliche, Hard Pan, Cemented Soils and/or Boulders larger than 1 Cubic Yard) have not been included. Price Negotiation will be
required if these materials are encountered.
Subtotal
Over Excavation of Unsuitable Material has not been accounted for, price negotiation will be required if these materials are encountered.
Actual quantities installed shall be tracked/measured and the basis of payment at the unit prices included in this proposal unless otherwise agreed.
Due to global supply chain disruptions and market volatility we reserve the exclusive right to adjust our proposal for material escalation.
Proposal is valid for 30 days. This proposal shall be made part of any subcontract.
Total
If you have any questions or need additional information with regard to our proposal please give us a call.
Dust control has been provided while we are actively working the site. No permanent or sustained dust control or mitigation has been included.
Fees for Utilities, County, City, Etc. are not included. Cultural Resource Services are not covered in our scope.
Hazardous Materials Abatement, Removal, Handling, Disposal, etc. are not expected onsite and are therefore Excluded.
Watering & Dust Control are Included for Selland's scope of work and duration only. No OT Dust Control or beyond our work.