HomeMy WebLinkAbout2025-009_ Ellensburg Rodeo_Change Order 01PROJECT NAME: Ellensburg Rodeo Arena Completion
OWNER: Kittitas County
CONTRACTOR: Cascade Central Construction
PROJECT NO: 2025-009
Amount
$9,211.93
$1,182.24
$12,517.81
$24,059.39
$7,208.00
Total This Change Order:$54,179.37
$5,100,000.00 *
$0.00
$5,100,000.00 By:
$54,179.37 Date
$5,154,179.37
7/20/2026
By:
0
Date
7/20/2026
7/23/2026 By:
8/22/2026 Date
Revised Contract Sum:
COP 2 - Existing RV Oultet Jbox
COP 5 - Buckaroo Press Box Panel
COP 1 - Temporary Fiber
Previously Approved Increases in Time:
Completion Date Prior to This Change Order:
Contract time will be changed by 3
Calendar Days This Change Order
Revised Final Acceptance Date:
Approved by Owner:
ALSC Architects, P.S.
CHANGE ORDER NO. 1
PAGE 1 of 18
DESCRIPTION OF CHANGE:
Contract Sum is increased by This Change Order:
Contract Sum Prior to This Change Order:
COP 6 - Megaphone Removal
Original Contract Sum
COP 3 - Buckaroo Grandstand Receptacles
Net Amount of Previously Approved Changes:
Revised Substantial Completion Date:
Accepted by Contractor:
*Does not include State or Local Sales Tax ALSC Architects | We bring our clients’ stories to life.
Recommended By:
Original Contract Completion Date:
F)
15
KC Carroll
12/11/25
PROPOSAL
P.O. Box 119
Wenatchee, WA. 98807-0119
Phone 509-662-7119
Fax 509-662-6380
To:PROJECT:Ellensburg Rodeo Arena Improvements
Kittitas County Comissioners COP#1
205 West 5th Ave, Suite 108 DATE:November 21, 2025
Ellensburg, WA 98926 TITLE:Temporary Fiber
Date DESCRIPTION QUANITITY UOM UNIT PRICE AMOUNT
11/21/2025
1 LS 6,092.00$ $6,092.00
$0.00
$0.00
$0.00
6,457.52
11/21/2025
4 HR 128.18$ $512.72
1 WD 925.00$ $925.00
2 HR 161.54$ $323.08
0 HR 116.25$ $0.00
0 HR 63.08$ $0.00
0 HR 119.00$ $0.00
2,024.92
SUBTOTAL 8,482.44
Sales Tax Rate:8.60% 729.49
TOTAL $9,211.93
MAKE CHECKS PAYABLE TO:
Cascade Central Construction, LLC
P.O Box 119
Wenatchee, WA. 98807-0119
THANK YOU FOR YOUR BUSINESS!
Project Engineer
Schedule Impact:
One (1) Working Day - New Substantial Compeltion: Tuesday, 7/21/25
Subcontractor Cost
Electrical Subcontractor - See attached Back-up
General Contractor - Sub Total with 15% Mark-up
Subcontractor - Sub Total with 6% Mark-up
Cascade Central Construction Cost
Project Management & Coordination
Laborer
Carpenter
Supervision
General Conditions
7/21/26
Project Name:COP-1
Project No.11/19/2025
Description:
a.1,461.68$
b.-$
c.-$
DIRECT LABOR SUBTOTAL 1,461.68$
d.
e.29.23$
1,491.00$
a.1,082.99$
b.
1,083.00$
a.-$
b.
-$
a.74.55$
75.00$
2,649.00$
a.423.84$
b.-$
424.00$
a.1,115.68$
b.1,494.00$
c.
d.-$
2,610.00$
a.391.50$
-$
392.00$
a.0.15 % of 1 2.24$
b.0.25 % of 1-7 15.19$ 17.42$
a.0.03 % of 1-8 -$
6,092.00$ Form Revised 04/25/15
6. SUB-SUBCONTRACTORS
TOTAL COST
bond
payroll driven liability insurance
volume driven liability insurance 8. INSURANCE
9. BOND
9. BOND
small tools (NTE 5% of 1a & b)
7. OVERHEAD & PROFIT ON SUB-SUBCONTRACTORS
NTE 15% of Line 6 up to $50,000 for each sub
8. INSURANCE
5. OVERHEAD & PROFIT
6. SUB-SUBCONTRACTORS
ITG - 11/12
SUBTOTAL 1 thru 4
7. OVERHEAD & PROFIT ON SUB-SUBCONTRACTORS
owned equipment (per spec approved source)
5. OVERHEAD & PROFIT
4. SMALL TOOLS
rental equipment (per invoices attached)
2. MATERIAL COSTS
3. EQUIPMENT COSTS
4. SMALL TOOLS
material costs
Wyatt Haller
Contractor:
Ellensburg Rodeo Arena Improvements
McGann Electric
Source Documents:
Provided and installed temporary plastic handhole at new construction entrance where we intercepted existing fiber from
armory and pulled back and routed under handhole and surface mounted fiber cable to south perimeter fence where we
utililzed exsitng fiber nema3r Jbox and splice enclosure we removed from demoed grandstands. Routed existing fiber from
teanaway/umtaneum hall to splice Jbox and re-spliced on 11/5 with data sub (ITG). Tested work completed and WI-FI
connection confirmed. The fiber from the second splice box on the southern woodpole that fed east underground to the other
fiber splice box to the south of goldbuckle club would not reach to the southern fence splice box of teanaway hall. Provided and
installed new temp single mode 6 strand fiber from Teanaway hall to main grandstand network switch. Surface mounted temp
fiber along fence line along grandstands then utilized existing conduit up to 2nd floor storage room with network switch.
Terminated both fiber ends and reset both owner network switches on 11/12. Tested all work completed and confirmed WI-FI
connection with facilities manager. The fiber run coiled by south video board that runs to the splice box by gold buckle will
need to be refed along with the fiber cable that fed the south video board from the Buckaroo network switch.
Itemize all costs on attached COP Cost Breakdown form.
crew (apprentices, journeymen, & laborers)
foreman
superintendent
Direct Labor Costs:
1. CRAFT LABOR COSTS
safety (NTE 2% of lines 1a, b, & c)
direct supervision (NTE 15% of 1a)
ITG -11/5
Supervision:
1. CRAFT LABOR COSTS
3. EQUIPMENT COSTS
NTE 15% portion of 1, 2, 3, & 4 up to $50,000
CCC
Contractor Breakdown Summary
McGann Electric
freight costs (itemize)
2. MATERIAL COSTS
Date:
Contractor Ref. No.
https://mcgannelectric-my.sharepoint.com/personal/jackmcgann_mcgannelectric_com/Documents/McGann Electric/2025 Ellensburg Rodeo 9.30/COPs/COP1 Fiber/Ellensburg Rodeo Arena
Improvements COP-1 Temp Fiber Summary Issued 11/20/2025
Project Name:COP-1
Project No.11/19/2025
Contractor:
Unit Labor Material Equipment Total
Description Quantity Type Unit $Cost Unit $Cost Unit $Cost Cost
-$ -$ -$ -$
-$ -$ -$ -$
Electrician Labor 6 HR $106.95 641.70$ -$ -$ 641.70$
Foreman Labor 7 HR $117.14 819.98$ -$ -$ 819.98$
-$ -$ -$ -$
-$ -$ -$ -$
Plastic Handhole 1 EA -$ $100.02 100.02$ -$ 100.02$
Fiber Optic Cable 1 LT -$ $972.97 972.97$ -$ 972.97$
Supports 1 LT -$ $10.00 10.00$ -$ 10.00$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
Labor Subtotal 1,461.68$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
1,461.68$ 1,082.99$ -$ 2,544.67$ Subtotal Cost of Work
Ellensburg Rodeo Arena Improvments
Cost Breakdown
McGann Electric
2/1/2017
Contractor Ref. No.
Date:
https://mcgannelectric-my.sharepoint.com/personal/jackmcgann_mcgannelectric_com/Documents/McGann Electric/2025 Ellensburg Rodeo 9.30/COPs/COP1 Fiber/Ellensburg Rodeo Arena Improvements COP-1 Temp FiberCost Breakdown Issued 11/20/2025
Project Name:
Project No:
Contractor:
Trade &ELECTRICIAN ELECTRICIAN ELECTRICIAN
Position JOURNEYMAN FOREMAN SUPERINTENDENT
Rate Schedule Date*10/25/25 10/25/25 10/25/25
Prevailing Wage (incl. Benefits)88.34$ 97.17$ 106.00$
1. Hourly Wage Rate 88.34$ 97.17$ 106.00$
SUBTOTAL 88.34$ 97.17$ 106.00$ -$ -$ -$ -$ -$ -$ -$
Rate
3. FUI % of 1 0.80%0.71$ 0.78$ 0.85$ -$ -$ -$ -$ -$ -$ -$
4. FICA % of 1 6.20%5.48$ 6.02$ 6.57$ -$ -$ -$ -$ -$ -$ -$
5. MEDICARE % of 1 1.45%1.28$ 1.41$ 1.54$ -$ -$ -$ -$ -$ -$ -$
6. SUI % of 1 (insert correct % to right)4.80%4.24$ 4.66$ 5.09$ -$ -$ -$ -$ -$ -$ -$
7. WC (insert $ amount per hour)1.95%1.80$ 1.85$ 1.90$
8.IRA retirement 5%4.63$ 4.75$ 5.09$
9. WPFM leave 0.50%0.47$ 0.49$ 0.51$
TOTAL (incl. payroll taxes)106.95$ 117.14$ 127.55$ -$ -$ -$ -$ -$ -$ -$
NOTES: * Rate schedule date is the date of the Dept. of Labor & Industries Prevailing Wage Rate used or the Union Agreement.
a. for items 3 thru 5, the Federal rates do not vary by firm, and the percentages are already locked into this form.
b. for item 6, the actual rate is determined by the State Employment Security Dept. and varies by firm. It shall be verified by the contractor at the start of the project.
c. for item 7, the rate is based on L & I classification. The hourly dollar amount is specific to the firm/trade and shall be verified by the contractor at the start of the project.
d. definitions
1. items 1 & 2 are basic wages and benefits (see general conditions 7.02 B.7.a(1))
2. item 3, FUI is Federal Unemployment Tax Act (see general conditions 7.02 B.7.a(3))
3. item 4, FICA is Federal Insurance Compensation Act/Social Security (see general conditions 7.02B.7(3))
4. item 5, Medicare is FICA medical aid (see general conditions 7.02 B.7.a(3))
5. item 6, SUI is State Unemployment Compensation Act (see general conditions 7.02 B.7.a(3))
6. item 7, WC is industrial insurance/workers' compensation (see general conditions 7.02 B.7.a(2))
7. item 8, AD is additional compensation for education, dental, vision, entertainment, vehicles
McGann Electric
COP Wage Rates
ERAI
Ellensburg Rodeo Arena Improv
https://mcgannelectric-my.sharepoint.com/personal/jackmcgann_mcgannelectric_com/Documents/McGann Electric/2025 Ellensburg Rodeo 9.30/COPs/COP1 Fiber/Ellensburg Rodeo Arena Improvements COP-1 Temp FiberWage Rates Issued 11/20/2025
c?o
o a a
C7
ujLLI
CO) Q F-
fn
H Z
U
s a
0d
2,
O
o
r
W
of
G w
1
W
¢ F
�
r
r
-=4-
-
I
f
I
�
ge
35
•
7
c i
F
►
4
I
Z
i
���
; �
.o��g�oWp����
� a
se$
W x
L► 8
gap
*�
16
�E
HM,
�,
� �i0
i
�-
j
I
--- --
, .
wnnemid �"
k
r
i
:..
�f
y
j
�LL
w
a
PTui
\
-
uj
q"
LP
_
d
o
h
I
I 1 I
�_ camp
pi
Za
W
��Z
fA�
o
s Q
S
z
Q
JQ
O
a
F— _
wU
r o
a:< �
W W�
W°
�,
° P
—J O
° F
O
w w
W
lL�
a aA
U
i
4
1
I
IIII
1�
n
�
�
1
A
"
o I
1 a
rl
�°
pp
i
r
4
= t
w
mtol
�o
sR
BgeSws�
8.R8
�i HIT
1
5$ i-i 1.
�:.• L.:,
�
-
i
IIj
. r
I
3`'
I
Z &
R r
T�
�._.....n...m..
_
to
UA
W
` a
a
Hn
WGo
�
PROPOSAL
P.O. Box 119
Wenatchee, WA. 98807-0119
Phone 509-662-7119
Fax 509-662-6380
To:PROJECT:Ellensburg Rodeo Arena Improvements
Kittitas County Comissioners COP#2
205 West 5th Ave, Suite 108 DATE:November 21, 2025
Ellensburg, WA 98926 TITLE:RFI 002 - Existing RV Outlet Jbox
Date DESCRIPTION QUANITITY UOM UNIT PRICE AMOUNT
11/21/2025
1 LS 1,027.00$ $1,027.00
$0.00
$0.00
$0.00
1,088.62
11/21/2025
0 HR 128.18$ $0.00
0 WD 925.00$ $0.00
0 HR 161.54$ $0.00
0 HR 116.25$ $0.00
0 HR 63.08$ $0.00
0 HR 119.00$ $0.00
0.00
SUBTOTAL 1,088.62
8.60% 93.62
Total $1,182.24
Pay This Amount $1,182.24
MAKE CHECKS PAYABLE TO:
Cascade Central Construction, LLC
P.O Box 119
Wenatchee, WA. 98807-0119
THANK YOU FOR YOUR BUSINESS!
Supervision
General Conditions
Project Engineer
Schedule Impact:
Subcontractor Cost
Electrical Subcontractor - See attached back-up
General Contractor - Sub Total with 15% Mark-up
Subcontractor - Sub Total with 6% Mark-up
Cascade Central Construction Cost
Project Management & Coordination
Laborer
Carpenter
Project Name:COP-2
Project No.11/19/2025
Description:
a.534.75$
b.-$
c.-$
DIRECT LABOR SUBTOTAL 534.75$
d.
e.10.70$
545.00$
a.311.47$
b.
311.00$
a.-$
b.
-$
a.27.25$
27.00$
883.00$
a.141.28$
b.-$
141.00$
a.
b.
c.
d.-$
-$
a.-$
-$
-$
a.0.15 % of 1 0.82$
b.0.25 % of 1-7 2.56$ 3.38$
a.0.03 % of 1-8 -$
1,027.00$
CCC
Contractor Breakdown Summary
McGann Electric
freight costs (itemize)
2. MATERIAL COSTS
Date:
Contractor Ref. No.
safety (NTE 2% of lines 1a, b, & c)
direct supervision (NTE 15% of 1a)
Supervision:
1. CRAFT LABOR COSTS
3. EQUIPMENT COSTS
NTE 15% portion of 1, 2, 3, & 4 up to $50,000
crew (apprentices, journeymen, & laborers)
foreman
superintendent
Direct Labor Costs:
1. CRAFT LABOR COSTS
Jack McGann
Contractor:
Ellensburg Rodeo Arena Improvements RFI 002 Existing RV Outlet Box
McGann Electric
Source Documents:
Remove and dispose damaged Nema 3R Jbox. Provide and install new 12x12x6 Nema 3R Jbox with screw on cover.
Provide and install new bell box covers, pvc fittings, strut, hardware and terminations. Test all work completed. Clean area
of all constrcution debris. Exclusions: cut patch, paint.
Itemize all costs on attached COP Cost Breakdown form.
2. MATERIAL COSTS
3. EQUIPMENT COSTS
4. SMALL TOOLS
material costs
SUBTOTAL 1 thru 4
7. OVERHEAD & PROFIT ON SUB-SUBCONTRACTORS
owned equipment (per spec approved source)
5. OVERHEAD & PROFIT
4. SMALL TOOLS
rental equipment (per invoices attached)
8. INSURANCE
5. OVERHEAD & PROFIT
6. SUB-SUBCONTRACTORS
9. BOND
9. BOND
small tools (NTE 5% of 1a & b)
7. OVERHEAD & PROFIT ON SUB-SUBCONTRACTORS
NTE 15% of Line 6 up to $50,000 for each sub
Form Revised 04/25/15
6. SUB-SUBCONTRACTORS
TOTAL COST
bond
payroll driven liability insurance
volume driven liability insurance 8. INSURANCE
https://mcgannelectric-my.sharepoint.com/personal/jackmcgann_mcgannelectric_com/Documents/McGann Electric/2025 Ellensburg Rodeo 9.30/COPs/RFI 002 RV
Jbox/Ellensburg Rodeo Arena COP-2 Summary Issued 11/20/2025
Project Name:COP-2
Project No.11/19/2025
Contractor:
Unit Labor Material Equipment Total
Description Quantity Type Unit $Cost Unit $Cost Unit $Cost Cost
-$ -$ -$ -$
-$ -$ -$ -$
Electrician Labor 5 HR $106.95 534.75$ -$ -$ 534.75$
Foreman Labor HR $117.14 -$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
12x12x6 Nema3R Jbox 1 EA -$ $144.74 144.74$ -$ 144.74$
Single gang W/P cover 2 EA -$ $17.94 35.88$ -$ 35.88$
Shallow strut 10 FT -$ $2.43 24.30$ -$ 24.30$
2" pvc fttings 1 LT -$ $4.62 4.62$ -$ 4.62$
1.25" pvc fittings 1 LT -$ $2.41 2.41$ -$ 2.41$
1" pvc fittings 1 LT -$ $10.06 10.06$ -$ 10.06$
ground lug 1 EA -$ $3.03 3.03$ -$ 3.03$
hardware 1 LT -$ $15.50 15.50$ -$ 15.50$
terminations - W/P 1 LT -$ $70.93 70.93$ -$ 70.93$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
Labor Subtotal 534.75$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
534.75$ 311.47$ -$ 846.22$ Subtotal Cost of Work
Ellensburg Rodeo Arena Improvments
Cost Breakdown
McGann Electric
2/1/2017
Contractor Ref. No.
Date:
https://mcgannelectric-my.sharepoint.com/personal/jackmcgann_mcgannelectric_com/Documents/McGann Electric/2025 Ellensburg Rodeo 9.30/COPs/RFI 002 RV Jbox/Ellensburg Rodeo Arena COP-2Cost Breakdown Issued 11/20/2025
PROPOSAL
P.O. Box 119
Wenatchee, WA. 98807-0119
Phone 509-662-7119
Fax 509-662-6380
To:PROJECT:Ellensburg Rodeo Arena Improvements
Kittitas County Comissioners COP#3
205 West 5th Ave, Suite 108 DATE:November 21, 2025
Ellensburg, WA 98926 TITLE:RFI 003 – Buckaroo Grandstand Receptacles
Date DESCRIPTION QUANITITY UOM UNIT PRICE AMOUNT
11/21/2025
1 LS 7,708.00$ $7,708.00
$0.00
$0.00
$0.00
8,170.48
11/21/2025
4 HR 128.18$ $512.72
2 WD 925.00$ $1,850.00
2 HR 161.54$ $323.08
2 HR 116.25$ $232.50
0 HR 63.08$ $0.00
0 HR 119.00$ $0.00
3,356.05
SUBTOTAL 11,526.53
8.60% 991.28
Total $12,517.81
Pay This Amount $12,517.81
MAKE CHECKS PAYABLE TO:
Cascade Central Construction, LLC
P.O Box 119
Wenatchee, WA. 98807-0119
THANK YOU FOR YOUR BUSINESS!
Supervision
General Conditions
Project Engineer
Schedule Impact:
Two (2) Working Days - New Substantial Completion: 7/23/26
Subcontractor Cost
Electrical Subcontractor - See attached Back-up
General Contractor - Sub Total with 15% Mark-up
Subcontractor - Sub Total with 6% Mark-up
Cascade Central Construction Cost
Project Management & Coordination
Laborer
Carpenter
Project Name:COP-3
Project No.11/20/2025
Description:
a.4,227.14$
b.-$
c.-$
DIRECT LABOR SUBTOTAL 4,227.14$
d.
e.84.54$
4,312.00$
a.2,094.26$
b.
2,094.00$
a.-$
b.
-$
a.215.60$
216.00$
6,622.00$
a.1,059.52$
b.-$
1,060.00$
a.
b.
c.
d.-$
-$
a.-$
-$
-$
a.0.15 % of 1 6.47$
b.0.25 % of 1-7 19.21$ 25.67$
a.0.03 % of 1-8 -$
7,708.00$
CCC
Contractor Breakdown Summary
McGann Electric
freight costs (itemize)
2. MATERIAL COSTS
Date:
Contractor Ref. No.
safety (NTE 2% of lines 1a, b, & c)
direct supervision (NTE 15% of 1a)
Supervision:
1. CRAFT LABOR COSTS
3. EQUIPMENT COSTS
NTE 15% portion of 1, 2, 3, & 4 up to $50,000
crew (apprentices, journeymen, & laborers)
foreman
superintendent
Direct Labor Costs:
1. CRAFT LABOR COSTS
Jack McGann
Contractor:
Ellensburg Rodeo Arena Improvements RFI 003 Buckaroo Receptacles
McGann Electric
Source Documents:
Provide and install 2 - 1" underground raceways from PNL - L1A to existing buckaroo grandstand receptacles location.
Provide and install 1 - 50A 2 pole circuit breaker in PNL - L1A. Utilize exsiting 2 - 20A 1pole spare breakers in PNL - L1A for
existing receptacle circuits. Provide and install 1 - 50A 2pole 208v circuit for exsitng 50A receptacle from PNL - 1LA. Provide
and install 2 -20A 120v circuits for 2 existing receptacle circuits under grandstands. All conduit, fittings, wire, supports,
breakers, hardware and terminations included. Exclusions: cut patch and paint, trenching and backfill.
Itemize all costs on attached COP Cost Breakdown form.
2. MATERIAL COSTS
3. EQUIPMENT COSTS
4. SMALL TOOLS
material costs
SUBTOTAL 1 thru 4
7. OVERHEAD & PROFIT ON SUB-SUBCONTRACTORS
owned equipment (per spec approved source)
5. OVERHEAD & PROFIT
4. SMALL TOOLS
rental equipment (per invoices attached)
8. INSURANCE
5. OVERHEAD & PROFIT
6. SUB-SUBCONTRACTORS
9. BOND
9. BOND
small tools (NTE 5% of 1a & b)
7. OVERHEAD & PROFIT ON SUB-SUBCONTRACTORS
NTE 15% of Line 6 up to $50,000 for each sub
Form Revised 04/25/15
6. SUB-SUBCONTRACTORS
TOTAL COST
bond
payroll driven liability insurance
volume driven liability insurance 8. INSURANCE
https://mcgannelectric-my.sharepoint.com/personal/jackmcgann_mcgannelectric_com/Documents/McGann Electric/2025 Ellensburg Rodeo 9.30/COPs/RFI 3 Grandstand
Receptacles/Ellensburg Rodeo Arena Improvements COP-3 Summary Issued 11/20/2025
Project Name:COP-3
Project No.11/20/2025
Contractor:
Unit Labor Material Equipment Total
Description Quantity Type Unit $Cost Unit $Cost Unit $Cost Cost
-$ -$ -$ -$
-$ -$ -$ -$
Electrician Labor 22 HR $106.95 2,352.90$ -$ -$ 2,352.90$
Foreman Labor 16 HR $117.14 1,874.24$ -$ -$ 1,874.24$
-$ -$ -$ -$
-$ -$ -$ -$
50A 2pole QBHW breaker 1 EA -$ $166.04 166.04$ -$ 166.04$
1" emt 20 FT -$ $1.94 38.80$ -$ 38.80$
1" emt connectors 4 EA -$ $5.89 23.56$ -$ 23.56$
1" rigid coupling 4 EA -$ $5.76 23.04$ -$ 23.04$
1" rigid 90 8 EA -$ $19.29 154.32$ -$ 154.32$
1" rigid 40 FT -$ $6.15 246.00$ -$ 246.00$
1" rigid threadless connector 2 EA -$ $14.64 29.28$ -$ 29.28$
1" PVC 280 FT -$ $0.62 173.60$ -$ 173.60$
1" PVC couplings 12 EA -$ $0.61 7.32$ -$ 7.32$
1" PVC FA 16 EA -$ $0.91 14.56$ -$ 14.56$
1" LB 2 EA -$ $18.10 36.20$ -$ 36.20$
deep strut 10 FT -$ $3.41 34.10$ -$ 34.10$
1" strut straps 8 EA -$ $1.68 13.44$ -$ 13.44$
#6 thhn 540 FT -$ $1.11 599.40$ -$ 599.40$
#8 thhn 180 FT -$ $0.72 129.60$ -$ 129.60$
#12 thhn 1500 FT -$ $0.25 375.00$ -$ 375.00$
hardware, terminations, glue, tape 1 LT -$ $30.00 30.00$ -$ 30.00$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
Labor Subtotal 4,227.14$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
4,227.14$ 2,094.26$ -$ 6,321.40$ Subtotal Cost of Work
Ellensburg Rodeo Arena Improvments RFI 003
Cost Breakdown
McGann Electric
2/1/2017
Contractor Ref. No.
Date:
https://mcgannelectric-my.sharepoint.com/personal/jackmcgann_mcgannelectric_com/Documents/McGann Electric/2025 Ellensburg Rodeo 9.30/COPs/RFI 3 Grandstand Receptacles/Ellensburg Rodeo Arena Improvements COP-3Cost Breakdown Issued 11/20/2025
PROPOSAL
P.O. Box 119
Wenatchee, WA. 98807-0119
Phone 509-662-7119
Fax 509-662-6380
To:PROJECT:Ellensburg Rodeo Arena Improvements
Kittitas County Comissioners COP#5
205 West 5th Ave, Suite 108 DATE:December 10, 2025
Ellensburg, WA 98926 TITLE:RFI 004 - Buckaroo Press Box Panel
Date DESCRIPTION QUANITITY UOM UNIT PRICE AMOUNT
12/10/2025
1 LS 19,724.00$ $19,724.00
$0.00
$0.00
$0.00
20,907.44
12/10/2025
2 HR 128.18$ $256.36
0 WD 925.00$ $0.00
2 HR 161.54$ $323.08
0 HR 116.25$ $0.00
8 HR 63.08$ $504.64
0 HR 119.00$ $0.00
1,246.69
SUBTOTAL 22,154.13
8.60% 1,905.26
Total $24,059.39
Pay This Amount $24,059.39
MAKE CHECKS PAYABLE TO:
Cascade Central Construction, LLC
P.O Box 119
Wenatchee, WA. 98807-0119
THANK YOU FOR YOUR BUSINESS!
Laborer - Hand Digging and backfill at structure to route conduit
Schedule Impact:
None, work is able to occur in same sequence as contract work.
General Contractor - Sub Total with 15% Mark-up
Carpenter
Subcontractor Cost
Electrical Subcontractor - See attached Back-up
Earthwork - Minimal added work, utilize same trench as other pathway, no
added cost
Supervision
General Conditions
Project Engineer
Subcontractor - Sub Total with 6% Mark-up
Cascade Central Construction Cost
Project Management & Coordination
Project Name:COP-4
Project No.12/5/2025
Description:
a.7,170.88$
b.-$
c.-$
DIRECT LABOR SUBTOTAL 7,170.88$
d.
e.143.42$
7,314.00$
a.9,271.67$
b.
9,272.00$
a.-$
b.
-$
a.365.70$
366.00$
16,952.00$
a.2,712.32$
b.-$
2,712.00$
a.
b.
c.
d.-$
-$
a.-$
-$
-$
a.0.15 % of 1 10.97$
b.0.25 % of 1-7 49.16$ 60.13$
a.0.03 % of 1-8 -$
19,724.00$
CCC
Contractor Breakdown Summary
McGann Electric
freight costs (itemize)
2. MATERIAL COSTS
Date:
Contractor Ref. No.
safety (NTE 2% of lines 1a, b, & c)
direct supervision (NTE 15% of 1a)
Supervision:
1. CRAFT LABOR COSTS
3. EQUIPMENT COSTS
NTE 15% portion of 1, 2, 3, & 4 up to $50,000
crew (apprentices, journeymen, & laborers)
foreman
superintendent
Direct Labor Costs:
1. CRAFT LABOR COSTS
Jack McGann
Contractor:
Ellensburg Rodeo Arena Improvements RFI 004 Buckaroo Panel
McGann Electric
Source Documents:
Demo out existing 200A feeder, 2" raceway and 200A panel in Buckaroo press box. Provide and install new 2.5" underground
conduit from MDPL to Buckaroo press box panel location. Provide and install 4#3/0's and #4 ground. Provide and install new
3PH, 225A rated 208Y/120V 42 circuit recessed bottom fed panel with surge protection. Provide and install new 200A 3pole
breaker in MDPL. Provide and install circuit breakers to match exisitng circuits in press box. Provide new grounding and
bonding at panel location. Reconnect all existing branch conduits and circuits to new panel. Remove drywall above and below
panel to make room for panel and conduit connections. Label all circuits in panelboard. Provide and install phenolic labels on
panel and MDPL. All conduit, fittings, wire, panel, breakers, supports, hardware, grounding and terminations included.
Exclusions: patch and paint
Itemize all costs on attached COP Cost Breakdown form.
2. MATERIAL COSTS
3. EQUIPMENT COSTS
4. SMALL TOOLS
material costs
SUBTOTAL 1 thru 4
7. OVERHEAD & PROFIT ON SUB-SUBCONTRACTORS
owned equipment (per spec approved source)
5. OVERHEAD & PROFIT
4. SMALL TOOLS
rental equipment (per invoices attached)
8. INSURANCE
5. OVERHEAD & PROFIT
6. SUB-SUBCONTRACTORS
9. BOND
9. BOND
small tools (NTE 5% of 1a & b)
7. OVERHEAD & PROFIT ON SUB-SUBCONTRACTORS
NTE 15% of Line 6 up to $50,000 for each sub
Form Revised 04/25/15
6. SUB-SUBCONTRACTORS
TOTAL COST
bond
payroll driven liability insurance
volume driven liability insurance 8. INSURANCE
https://mcgannelectric-my.sharepoint.com/personal/jackmcgann_mcgannelectric_com/Documents/McGann Electric/2025 Ellensburg Rodeo 9.30/COPs/COP4
Pnl/Ellensburg Rodeo Arena Improvements COP-4 Summary Issued 12/8/2025
Project Name:COP-4
Project No.12/5/2025
Contractor:
Unit Labor Material Equipment Total
Description Quantity Type Unit $Cost Unit $Cost Unit $Cost Cost
-$ -$ -$ -$
-$ -$ -$ -$
Electrician Labor 32 HR $106.95 3,422.40$ -$ -$ 3,422.40$
Foreman Labor 32 HR $117.14 3,748.48$ -$ -$ 3,748.48$
-$ -$ -$ -$
Panel, main and branch breakers 1 LT -$ $3,970.00 3,970.00$ -$ 3,970.00$
-$ -$ -$ -$
-$ -$ -$ -$
2.5" pvc bell end 1 EA -$ $11.26 11.26$ -$ 11.26$
2.5" pvc 160 FT -$ $2.03 324.80$ -$ 324.80$
2.5" couplings 10 EA -$ $2.63 26.30$ -$ 26.30$
2.5" rigid 90 4 EA -$ $91.67 366.68$ -$ 366.68$
2.5" pvc FA 8 EA -$ $3.93 31.44$ -$ 31.44$
2.5" rigid 40 FT -$ $22.22 888.80$ -$ 888.80$
2.5" rigid threadless connector 1 EA -$ $175.25 175.25$ -$ 175.25$
deep strut 10 Ft -$ $2.62 26.20$ -$ 26.20$
2.5" rigid strut straps 4 EA -$ $3.21 12.84$ -$ 12.84$
grounding and bonding 1 LT -$ $55.00 55.00$ -$ 55.00$
glue,hardware,tape, phenolics 1 LT -$ $75.00 75.00$ -$ 75.00$
2.5" lock rings and bushings 1 LT -$ $10.00 10.00$ -$ 10.00$
#250AL 920 FT -$ $1.90 1,748.00$ -$ 1,748.00$
#4 thhn 230 FT -$ $1.54 354.20$ -$ 354.20$
-$ -$ -$ -$
Lift fees 4x4 scissor large working 1 LT -$ $1,090.00 1,090.00$ -$ 1,090.00$
Permit fees (added feeder)1 LT -$ $105.90 105.90$ -$ 105.90$
Labor Subtotal 7,170.88$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
7,170.88$ 9,271.67$ -$ 16,442.55$ Subtotal Cost of Work
Ellensburg Rodeo Arena Improvments RFI 004
Cost Breakdown
McGann Electric
2/1/2017
Contractor Ref. No.
Date:
https://mcgannelectric-my.sharepoint.com/personal/jackmcgann_mcgannelectric_com/Documents/McGann Electric/2025 Ellensburg Rodeo 9.30/COPs/COP4 Pnl/Ellensburg Rodeo Arena Improvements COP-4Cost Breakdown Issued 12/8/2025
PROPOSAL
P.O. Box 119
Wenatchee, WA. 98807-0119
Phone 509-662-7119
Fax 509-662-6380
To:PROJECT:Ellensburg Rodeo Arena Improvements
Kittitas County Comissioners COP#4
205 West 5th Ave, Suite 108 DATE:December 10, 2025
Ellensburg, WA 98926 TITLE:Megaphone Removal
Date DESCRIPTION QUANITITY UOM UNIT PRICE AMOUNT
12/10/2025
1 LS 5,911.00$ $5,911.00
1 LS -$ $0.00
$0.00
$0.00
6,265.66
12/10/2025
0 HR 128.18$ $0.00
0 WD 925.00$ $0.00
2 HR 161.54$ $323.08
0 HR 116.25$ $0.00
0 HR 63.08$ $0.00
0 HR 119.00$ $0.00
371.54
SUBTOTAL 6,637.20
8.60% 570.80
Total $7,208.00
Pay This Amount $7,208.00
MAKE CHECKS PAYABLE TO:
Cascade Central Construction, LLC
P.O Box 119
Wenatchee, WA. 98807-0119
THANK YOU FOR YOUR BUSINESS!
Schedule Impact:
None
General Contractor - Sub Total with 15% Mark-up
Carpenter
Subcontractor Cost
Demolition Subcontractor - See attached Back-up
Electrical Subcontractor - No cost, added work was minimal
Supervision
General Conditions
Project Engineer
Subcontractor - Sub Total with 6% Mark-up
Cascade Central Construction Cost
Project Management & Coordination
Laborer
6
CHANGE ORDER
CHANGE ORDER NUMBER:
Customer: Cascade Central (Rusty & KC)
Project: Ellensburg Rodeo
Description of change:
- Remove speakers from center of arena
+ 2 labors 1 day = 20 hrs
- Boom lift “rental” 1 week charge for electrician
- Light pole removal via push over (haul off coordinated by others but can be added)
Payment for this change order is payable as follows (due within 7 days of signing below if left blank):
• The original Contract Price was…………………………………………….… $ 128,750.00
• Net change by previously authorized Change Orders………………………… $0.00
• The Contract Price prior to this Change Order was……………………………$128,750.00
• This Change Order will the Contract Price by ……………..$5,911.00
• The new Contract Price including this Change Order will be ………………...$134,661.00
• This Change Order will the Contract Time by approx. days.
Customer Date
Eric Pfeifer, Estimator Date
Elite Environmental Services, LLC d/b/a Safeguard Abatement
1 SafeGuard Abatement
1702 Englewood Ave
Yakima, WA 98902
(509) 759-7481
www.safeguardabatement.com
◼ increase
decrease
1 ◼increase
decrease