HomeMy WebLinkAboutResolution_JUB TO_Taxilane Complex Phase IKITTITAS COUNTY DEPARTMENT OF PUBLIC WORKS AGENDA SESSION STAFF REPORT AGENDA SESSION DATE: September 16, 2025 ACTION REQUESTED: Request to Approve a Resolution authorizing the Chair's signature on Task Order 2025-01 with J-U-B Engineering to perform engineering services for the Bowers Field Hangar Taxilane Complex — Phase 1 Design. BACKGROUND: The Board of County Commissioners approved a Resolution to award J-U-B Engineers the contract to be the Bowers Field consultant on January 3, 2023, providing general planning and engineering services. INTERACTION: Task Order No. 2025-01 for the design of the Hangar Taxilane Complex project is being submitted for consideration. J-U-B has submitted a task order in the amount of $184,170.00. Concurrence has been made by the FAA for the task fee for this project. Project funding for Bowers Field design project FAVAIP No. 3-53-0026-024-2025 has been awarded and accepted by Resolution 2025-147. Funding requires a 5% local match. Matching funds are available in the Airport Fund. Public Works RECOMMENDATION: Approve a Resolution authorizing the Chair's signature on Task Order 2025-01 with J-U-B Engineering to perform engineering services for the Bowers Field Hangar Taxilane Complex — Phase 1 Design. HANDLING: Return one (1) original to Public Works ATTACHMENTS: Resolution; Task Order 2025-01 LEAD STAFF: Josh Fredrickson, Public Works Director BOARD OF COUNTY COMMISSIONERS COUNTY OF KITTITAS STATE OF WASHINGTON RESOLUTION NO.2025 - AUTHORIZING THE CHAIR'S SIGNATURE ON J-U-B ENGINEERING TASK ORDER 2025-01 FOR THE BOWERS FIELD HANGAR TAXILANE PROJECT DESIGN WHEREAS: J-U-B Engineers is currently the service provider to Public Works for projects at Bowers Field selected from County procurement process in 2023; and WHEREAS: J-U-B Engineering has submitted Task Order No. 2025-01 for the Hangar Taxilane Project Design in the amount of $184,170.00; and WHEREAS: Funding for Task Order 2025-01 is through Federal Aviation Administration grant with a 5 percent County match. NOW, THEREFORE BE IT RESOLVED that the Board of County Commissioners, in the best interest of the public, does hereby authorize the Chair's signature on J-U-B Engineering Task Order No. 2025-01 for the Hangar Taxilane Project Design. DATED on this 16th day of September 2025, at Ellensburg, Washington. Attest: ❑ Clerk of the Board- Julie Kjorsvik ❑ Deputy Clerk of the Board- Mandy Buchholz BOARD OF COUNTY COMMISSIONERS KITTITAS COUNTY, WASHINGTON Laura Osiadacz, Chairman Cory Wright, Vice -Chairman Brett Wachsmith, Commissioner TASK ORDER 2025-01 HANGAR TAXILANE COMPLEX PHASE 1 DESIGN AI P-3-53-0026-024-2025 A MASTER AGREEMENT for Engineering Services entered into and effective on the 3rd day of January 2023, shall be appended herein as Task Order No. 2025-01, made as of day of September, 2025, by and between Kittitas County, 205 West 5th Avenue, Suite 108, Ellensburg, Washington, hereinafter referred to as the OWNER, and J-U-B ENGINEERS, Inc., 999 W. Riverside Ave. Suite 700, Spokane, Washington, hereinafter referred to as the ENGINEER. PROJECT OBJECTIVE The County's objective in this agreement is to: • Construct approximately 550 linear feet of Taxilane(s) for GA Aircraft and Hangar Development adjacent to the main GA apron. • Grade the Taxilane Safety and Object Free Areas to meet FAA Standards. • Relocate approximately 1,000 linear feet of chain link airport perimeter fencing. • Install utility sleeves as needed to avoid future pavement cuts to the paved Taxilane. • Improve drainage in the vicinity of the Taxilane. Work includes grading and installation of catch basins and/or pipes to collect stormwater. Included below is a depiction of the proposed project from the ELN Airport Layout Plan (ALP). AIRPORT BUILD67GNACIL" KEY is ®^w.rce[wu,. n. ;1f Eeun :n [xx- u[• !M +.- `E. em�meeew..�wue-wsuiwerRaw vs Yi. r.ea+.�rr�uamw�nn EE xw*a«aax-.ra arrs�uEwe s em uau ..R.0 va• ' w+m..++ E...rwn w ffi n, x wrnsrwn.n s; aeurua. Raoexw,aR�emuo-Ew nm 'sr w.*av� uovr.,R.Kw.ws.. � �E�'E sar •wer.n 's �eEoeusaaEnvnns m `b , wox.�...rnrrina mr '. e..e,...-u.re...m..�Ewn m�•w.i yr w.�s.w.eewRn.v, -I' a.xenWAKWi'uuRE�R rnvn DS jd CYNr At: :)Q W1NM��P,s6WYY1RY f11P `M m�uw IdetllMel 9� ewwtwEN uaruai-teYO+N ifY [' NY0..V[ pnwstlM. IEE' fY ANNL�eEbEaw•�n.ei ;u. ,:r.aws : w 1i .. a�E.nnE ,rr :w uw.eMah.MME.i ^..e, ,tea... ,� r •w w.o[..[�awa.w.w�n •b �,., .mP - .0 ;ty r� yr za. , mr ;i Ne xasro�; • . � — [9YtotWr i/isa _ _—_ - jb ) Cwi,llaY. - I ,nL u o. Al �. RillIGfFO �1 ---.—_ _--------- ------- ------- 4itjAso�rrruwxa �. _s oran . I t6 g B. j nrcamEsmirsawnvai. �.. uuurtEeumuc wA— ciT8tAN91. \\ ub.com\Central\Clients\WA\KittitasCounty\Projects\45-25- 022_BowersField_HangarTxln_PhaselDsgn\ProjMgmt\Agreements\Old\TO 2025_01_Rev5ept2025.docx 1 TASK ORDER 2025-01 HANGAR TAXILANE COMPLEX PHASE 1 DESIGN AI P-3-53-0026-024-2025 SCOPE OF SERVICES J-U-B's Services under this agreement are limited to the following tasks: TASKS Task 001: Project Formulation Phase 1. Conduct a Pre -Design meeting with CLIENT and FAA at the Airport. The meeting will be held to determine the planning and study issues that will need to be addressed during the design of the project. The FAA Predesign Conference Checklist will be the guide for project discussions. Minutes of the Predesign meeting will be compiled and forwarded to the FAA and CLIENT. 2. Assist the CLIENT with Project Scope development and formulation. J-U-B will prepare a Scope of Services narrative and detailed description of all work tasks for CLIENT and FAA review and approval. Discuss review comments and revise accordingly. 3. Prepare a listing of work tasks in a spreadsheet with person -hours, hourly rates, expenses, and costs based on the Scope of Services. This spreadsheet will be used for both J-U-B and the Independent Fee estimate. J-U-B shall prepare a detailed cost proposal on the spreadsheet, based on estimates of work to accomplish the Scope of Services. 4. Provide the CLIENT and the Independent Fee Estimator (IFE) with a blank person - hour spreadsheet, Scope of Services, Project Layout Map, and overall project estimate. 5. Prepare an Agreement for Professional Services for submittal and review by the CLIENT and FAA, including the FAA Professional Service Agreement Checklist. The Agreement shall be comprehensive in description of services and responsibilities of all contract parties. 6. Assist CLIENT with preparation and submittal of a FAA Grant Application for Federal Assistance for the project, including estimated project costs, drawings, and a schedule for FAA submittal prior to beginning of the project. 7. Assist CLIENT in the submittal of FAA Sponsor Certifications. These include the "Selection of Consultants", "Project Plans and Specifications", "Drug Free Workplace", "Equipment/Construction Contracts", "Disclosure Regarding Potential Conflicts" and "Construction Project Final Acceptance". 8. Provide the following services related to Federal Disadvantaged Business Enterprise requirements (DBE). a. Redevelop sponsor's DBE Program Plan in accordance with the Disadvantaged Business Enterprise (DBE) Programs Final Rule dated April 9, 2024 and submit to FAA Civil Rights for review and approval. \\jub.com\Central\CI ients\WA\KittitasCou my\Projects\4S-25- 022_BowersField_HangarTxln_PhaselDsgn\ProjMgmt\Agreements\Old\TO 2025_01_RevSept2025.docx 2 TASK ORDER 2025-01 HANGAR TAXILANE COMPLEX PHASE 1 DESIGN AI P-3-53-0026-024-2025 9. Provide the following services related to Federal Title VI of the Civil Rights Act of 1964. a. Develop scope and fee for requesting design amendment to develop documents related to Title VI. b. Develop a Title VI Program Plan for the Airport based on the FAA provided direction and Title VI plan template. This document will be customized for the sole use of the Owner and includes but is not limited to the following: Work with the City and Airport to identify the Civil Rights Coordinator and their responsibilities. ii. Assist with coordinators access to Civil Rights Connect if not already established. iii. Identify and document plans for required posting distribution iv. Analysis of potential or known community impacts V. Analysis of community statistics vi. Limited English Proficiency (LEP) access planning and implementation vii. Identification of minority business viii. Identification of additional training for staff and new employee onboarding ix. Identification of Title VI compliant procedures X. Create draft Title VI Plan document for review by the Owner xi. Revise Title VI Plan based on comments received and submit final draft to FAA Civil Rights. c. Assist Title VI Coordinator with annual data collection and demographic data d. Develop a Community Participation Plan (CPP) for the Owner based on the FAA provided direction and CPP template i. Identify communication efforts ii. Identify key community representatives iii. Create draft CPP document for review by the Owner iv. Revise CPP based on comments received and submit final draft to FAA Civil Rights. e. Create language assistance plan if required by Title VI 10. Prepare and submit four (4) FAA Quarterly Performance Reports and two (2) Fiscal Year End Financial FAA 271 and 425 forms throughout the project. 11. Attend eight (8) meetings with the Airport Advisory Committee and/or County during the project in order to keep Airport personnel and management abreast of \\ ub.com\Central\Clients\WA\KittitasCounty\Projects\4S-25- 022_BowersFie ld_H angarTxln_Phase1Dsgn\ProjMgmt\Agreements\Old\TO 2025_01_RevSept2025.docx 3 TASK ORDER 2025-01 HANGAR TAXILANE COMPLEX PHASE 1 DESIGN AI P-3-53-0026-024-2025 the progress of the projects. Discussions will include project phasing, budget and schedule updates. 12. Assist CLIENT in preparation and processing of monthly Request for Reimbursement (RFR) by submitting data as described. It is anticipated that the CLIENT will prepare and process eight (8) monthly sets of RFR 'packages' for this project. J-U-B will provide documentation of costs for the CLIENT's use in performing the Request for Reimbursements including consultant invoices, reimbursement spreadsheet and Standard Form 271. 13. Project is within the Urban Growth Area (UGA) of the City of Ellensburg. Anticipate to meet once with the City of Ellensburg representatives to verify requirements of the City. The County has an interlocal agreement in place with regard to development within the UGA. Task 002: Preliminary Design Phase 1. Investigate the proposed job site at the Airport. Allow civil design personnel to become familiar with the proposed job site. Take photographs, perform a visual survey of the pavement areas, and otherwise document findings of visit. 2. Provide or obtain field surveys, which include detailed topographic and cross section information of improvement areas for design purposes. Coordinate with surveyors to verify that design survey is performed as required. This will include one (1) on -site meeting with surveyors to review project location and safety. The general scope of the survey work will include the following: The primary area to be surveyed is approximately 650-ft by 250-ft and encompasses the proposed taxilane, associated safety areas, and adjacent structures. The pavement and shoulder surfaces within this area shall be section surveyed on 20-ft stations. The infield and grass surfaces within this area shall be surveyed on a 50-ft by 50-ft grid. All topographical features within all of these areas shall be surveyed including but not limited to: grade breaks, pavement markings, tie -downs, building corners, fence, drainage structures (invert elevations, pipes sizes, & rim elevations), pavement markings, utility markers, edge of pavements, and lighting and electrical components. Existing control monuments shall be used for the survey control and will need to be tied together to check for accuracy. The survey will have to be coordinated with the Airport Manager for airport access and optimum time to minimize disruption to air traffic. The airfield pavements and runway will be open to aircraft, surveyors will have to monitor the local frequency and move out of safety areas for aircraft. The survey shall be conducted in accordance to FAA AC 150/5370-2G safety guidelines. Vertical datum should be in accordance to NAVD 88, and horizontal datum should be in accordance to NAD 83. Vertical tolerances shall be +0.02-feet for paved surfaces and +0.05-feet for unpaved surfaces. Horizontal tolerances shall be +0.03-feet. \\jub.com\Central\Clients\WA\KittitasCou my\Projects\45-25- 022_BowersFie ld_H angarTxln_PhaselDsgn\ProjMgmt\Agreements\Old\TO 2025_01_RevSept2025.docx 4 TASK ORDER 2025-01 HANGAR TAXILANE COMPLEX PHASE 1 DESIGN AI P-3-53-0026-024-2025 The collected data shall be provided on a compact disk to the Engineer with the following information: point number, description, northing, easting, and elevation along with paper copies of any pertinent field notes. No map or drawing will be required. 3. Administer design Geotechnical Subconsultant contract and coordinate delivery of work product. Provide quality control review of work products. This will include one (1) on -site meeting with geotechnical Subconsultant to review project location and safety. The geotechnical laboratory work will be performed utilizing the services of a Subconsultant. The general scope of the geotechnical work will be the following: Administer three (3) cores/bore logs on the proposed taxilane alignment to a depth of 6-feet or refusal. The geotechnical engineer shall immediately patch all pavement core holes with an approved asphalt cold mix or similar product. Data shall be collected on the soil type, existing asphalt condition, and depths and categorized according to the Unified Soil Classification System (USCS) including Moisture Content, Atterberg Limits, Grain Size Distribution. A sieve analysis shall be performed on both the base course and subbase for each core/bore location. The sieve analysis for base course should include the following classifications: percentage by weight passing sieves of 1-inch, 3/4-inch, No. 4, No. 40, No. 200, and 0.02 mm. The sieve analysis for subbase course should include the following classifications: percentage by weight passing sieves of 3-inch, No. 10, No. 40, No. 200, and 0.02 mm. Ground water depth shall be recorded if encountered. Three California Bearing Ratio (CBR) test shall be performed on the bore log samples at a depth of 24-inches which is the anticipated depth of subgrade. The geotechnical engineer shall coordinate with the Engineer to determine exact core/bore log locations. The geotechnical work shall be conducted in accordance to FAA AC 150/5370-2G safety guidelines. The geotechnical engineer shall be responsible for a utility locate prior to work. It should be anticipated that the cores/bore logs shall be taken during nighttime hours. The geotechnical firm will need to coordinate with the Airport Manager and the Engineer personal for closure time and date. The geotechnical firm shall submit 3 copies of the final geotechnical report including all required information as mentioned above to the Engineer within three weeks upon finishing field work. The firm shall submit a draft copy for review prior to finalizing the report and its findings. This line item shall include the coordination and contracting with Subconsultant. The Subconsultant fees shall be addressed in the Expenses-Subconsultant Section. \\jub.com\Central\Clients\WA\KittitasCou my\Projects\45-25- 022_BowersFie ld_H angarTxln_PhaselDsgn\ProjMgmt\Agreements\Old\TO 2025_01_RevSept2025.docx 5 TASK ORDER 2025-01 HANGAR TAXILANE COMPLEX PHASE 1 DESIGN AI P-3-53-0026-024-2025 4. Analyze the geotechnical testing data to determine the most cost-effective form of new construction. Analyze the performance and stability of existing asphalt section. Rehabilitation methods may include full depth reconstruction in designated select locations, pavement removal and replacement, or pavement overlay depending on test results. Hold a meeting with the CLIENT and FAA at the Airport to present findings of the Geotechnical Testing and analysis of existing pavement. Determine rehabilitation/reconstruction method best suited for the pavement surfaces. 5. Define critical aircraft for the pavement design of the project and develop pavement design section. Pavement design criteria shall be in accordance with the FAA Advisory Circular (AC) 150/5320-6G. This will include calculating and reporting the Airport Pavement Strength- PCR. 6. Perform analysis of existing geometric layout of Taxiway/Runway fillets and radii to determine compliance with current FAA AC requirements. Present findings to CLIENT and FAA for review and comments. 7. Review existing storm water drainage within the project boundary. Evaluate existing drainage patterns and systems. J-U-B shall conduct a required analysis for the design of drainage improvements associated with the project in accordance with the FAA AC 150/S320-5D, Surface Drainage Design. Any necessary drainage improvements will be sized to accommodate local drainage standards. This drainage effort is intended to integrate with previously established drainage designs (specifically the Parallel Taxiway). 8. Address subsurface drainage requirements for the runway and determine appropriate methods for compliance with the FAA Northwest Mountain Region policy on subsurface pavement drainage and edge underdrains. Location of underdrain outlets will be a significant portion of this study. 9. Perform analysis of existing Runway and Taxiway Shoulders, Safety Area and Object Free Area grading adjacent to project area to determine proposed taxilane compliance with current FAA AC 1 S0/S300-13B requirements. 10. Determine the operational and phasing effects of closing portions of adjacent apron pavement areas. Closing the runway will impact the airport users, FBO's and transient aircraft during the construction period. Study the effects of the various alternatives including night construction, temporary displaced thresholds, using parallel taxiway as temporary runway, or phased construction. Complete a cost analysis on all alternatives to present to CLIENT. Two meetings at the Airport will be needed to present preliminary alternatives and phasing plan to the CLIENT and stakeholders. 11. Prepare and submit a State Environmental Policy Act (SEPA) Environmental Checklist in accordance with Title 15 of Kittitas County Code. Environmental work \\ ub.com\Central\Clients\WA\KittitasCounty\Projects\45-25- 022_BowersField_HangarTxln_PhaselDsgn\ProjMgmt\Agreements\Old\TO 2025_01_RevSept202S.docx 6 TASK ORDER 2025-01 HANGAR TAXILANE COMPLEX PHASE 1 DESIGN AI P-3-53-0026-024-2025 beyond that described will be considered additional work and may require a contract modification. 12. Assemble base data and base maps for the project work area from the design survey, previous projects undertaken, and available aerial data. 13. Prepare preliminary Design Plans (60% complete) for review and discussion with the CLIENT and FAA. Resubmit to CLIENT and FAA at 90% complete. It is anticipated that the project design will require sixteen (16) plan sheets including: Sheet 1 — Cover Sheet 2 — Construction Layout Plan Sheet 3 — Operation & Safety Plan - Phase 1 Sheet 4 — Operation & Safety Plan - Phase 2 Sheet 5 — Demolition/Modification Plan Sheet 6 — Grading & Drainage Plan - Sheet 1 Sheet 7 — Grading & Drainage Plan — Sheet 2 Sheet 8 — Plan & Profile Taxilane — Sheet 1 Sheet 9 — Plan & Profile Taxilane — Sheet 2 Sheet 10 — Pavement Marking Plan Sheet 11 — Perimeter Fencing Plan Sheet 12 — Pavement Marking Details Sheet 13 — Fencing Details Sheet 14 — Typical Sections Sheet 15 — Civil Details Sheet 16 - Civil Details 14. Prepare preliminary Bidding and Construction Contract Documents and Technical Specifications (60% and 90% complete intervals) based on latest version of FAA AC 150/5370-10 "Standards for Specifying Construction on Airports" including the current Regional Notice published by the FAA Airports Districts Office. 15. Prepare a preliminary Engineer's Opinion of Probable Construction Cost Estimate based on construction cost estimates, phasing into workable portions for constructability, budget, and construction schedule and advise the CLIENT as to budget status. 16. Prepare a preliminary Construction Safety and Phasing Plan according to AC 150/5370-2G for evaluation by the CLIENT, Airport, FBO, airport users and agencies. An electronic copy will be submitted to the FAA Airport District Office for coordination, review, and approval with other FAA lines of business using the airspace process. 17. Prepare the preliminary Engineer's Design Report in conformance with FAA guidelines. The report shall include a Summary of the Project and its specific design issues, Project Schedule, reference to the Construction Safety and Phasing Plan, Modification of Standards, Design Analysis, Pavement Analysis, Geotechnical \\jub.com\Central\CI ients\WA\KittitasCou my\Projects\45-25- 022_BowersFie ld_HangarTxln_PhaselDsgn\ProjMgmt\Agreements\Old\TO 2025_01_RevSept2025.docx 7 TASK ORDER 2025-01 HANGAR TAXILANE COMPLEX PHASE 1 DESIGN AI P-3-53-0026-024-2025 Investigation Report, Concept Taxilane Layout, and Construction Cost Estimate and Schedule. 18. Conduct in-house quality control/quality assurance review of preliminary design documents. 19. Participate in a preliminary design review meeting with the CLIENT. Anticipate one (1) review meeting with the CLIENT at the Airport, attendance by the Project Manager and Airport Engineer. Review design philosophy, preliminary design drawings, design analysis and project schedules with the CLIENT. 20. Prepare and submit one (1) FAA Form 7460 to airspace the project construction equipment and permanent taxiway geometry. 21. Submit preliminary documents to FAA (1 copy) and CLIENT (2 copies) for approval. Task 003: Final Design Phase 1. Finalize Bidding and Construction Contract Documents and Technical Specifications based on Peer, CLIENT, and FAA Reviews. 2. Finalize Design Plans based on Peer, CLIENT, and FAA Reviews. 3. Prepare final Construction Safety and Phasing Plan to accommodate varying work components that need to meet prescribed schedules. 4. Complete final quantity calculations and prepare Final Engineer's Opinion of Probable Construction Cost Estimate. 5. Prepare final Engineer's Design Report based on Peer, CLIENT, and FAA Reviews. 6. Submit final documents to FAA (1 copy) and CLIENT (2 copies) for approval. Task 004: Bidding Phase 1. Administer the public bid advertisement process including bid document reproduction and distribution of documents to plan rooms, contractors and suppliers. Submit advertisements to appropriate newspaper(s) and trade magazines as required for publication. Maintain a "bidders list" and distribute plans as requested. Fees for Plan & Specification Reproduction shall be reflected in the "Printing" line below. 2. Provide Pre -Bid Conference coordination to familiarize bidders and interested parties with the construction project scope and requirements. Prepare a detailed agenda and displays, prepare and issue conference minutes. It is anticipated that J-U-B will conduct this meeting at the Airport. 3. Prepare Bid Addendums. Addenda are normally required in response to Contractor questions and/or design changes initiated by the CLIENT and/or the FAA. Engineering estimate includes costs for the preparation of two Addendums. \\j u b. com\Centra I\C I ie nts\W A\Kittitascou my\P rojects\45-25- 022_BowersFie ld_H angarTxln_PhaselDsgn\ProjMgmt\Agreements\Old\TO 2025_01_RevSept2025.docx 8 TASK ORDER 2025-01 HANGAR TAXILANE COMPLEX PHASE 1 DESIGN AIP-3-53-0026-024-2025 4. Respond to questions that arise during the Contractor's or supplier's bid preparation process. 5. Assist the CLIENT in conducting the project Bid Opening as required, including preparation of a Project Bid Summary. It is anticipated that J-U-B will coordinate and attend this meeting at Kittitas County Public Works Office. 6. Prepare detailed Bid Tabulations documenting bid results and submit to CLIENT and the FAA. 7. Assist the CLIENT with review and analysis of bids received. J-U-B will determine his opinion on "responsiveness" of bid submittal. Provide letter of recommendation of award along with price/cost analysis in accordance with FAA Order 5100.38D-Appendix U to CLIENT. Advise the CLIENT of possible action in cases where bids exceed budget for the work to be performed by the Contractor. Task 005: Project Closeout Phase 1. Prepare the final project report and close-out documents according to FAA requirements and submit to CLIENT and FAA. 2. Prepare an Airport Layout Plan Set (ALP) Revision to document improvements. A draft copy of the revised ALP will be submitted to the FAA and CLIENT for review. Upon review and comment changes, copies with be distributed to the FAA and CLIENT for signatures. 3. Report Disadvantaged Business Enterprise (DBE) project participation to FAA dbE- Connect including all calculations and background information for review and approval. 4. Assist and coordinate with independent auditors in locating appropriate documents for performing A-133 (Single Audit) annual audit. In addition to finding appropriate project files, answer questions as required. 5. Provide assistance to the CLIENT in assessing, costing, and updating the five-year Capital Improvement Plan for submittal to State Division of Aeronautics. ASSUMPTIONS • No SMS plan is required on this project during the design or other portions of the project. No initial AGIS survey is required for this project. • This project has been determined to be environmentally cleared through a previous Environmental Assessment (EA). Further environmental efforts beyond completing a Kittitas County SEPA will be considered additional work and may require a contract modification. \\j u b. co m\Centra I\C I i e nts\W A\KittitasCou my\Prof ects\45-25- 022_BowersFie ld_H angarTxln_PhaseIDsgn\ProjMgmt\Agreements\Old\TO 2025_01_RevSept2025.docx 9 TASK ORDER 2025-01 HANGAR TAXILANE COMPLEX PHASE 1 DESIGN AIP-3-53-0026-024-2025 SCHEDULE OF SERVICES J-U-B will perform all services according to the following schedule: April 1', 2025 to June 30t'', 2026 This Agreement shall be in effect from April 1, 2025 to September 30, 2026. In the event the services described shall not be completed during the term of this Agreement, the Agreement shall be amended. This schedule shall be equitably adjusted as the PROJECT progresses, allowing for changes in scope, character or size of the PROJECT requested by the CLIENT or for delays or other causes beyond J-U-B`s control. COMPENSATION CLIENT shall pay J-U-B for the identified Services in PART 1 as follows: Preliminary and Final Design Phase. The CLIENT shall compensate J-U-B on the basis of a lump sum amount One Hundred Eighty -Four Thousand, One Hundred Seventy Dollars and No Cents ($184,170.00). See Attachment 1 B for a detailed cost breakdown. This Task Order No. 2025-01 will become part of the referenced AGREEMENT when executed by both parties. IN WITNESS WHEREOF, the parties execute below: For the Owner, Kittitas County, Washington Dated this day of 2025, By: Name For the ENGINEER, J-U-B ENGINEERS, Inc. Dated this I- day of - 2025, By: 161-1=1- Title Title \\j u b.com\Central\Clients\WA\KittitasCounty\Projects\45-25- 022_BowersField_HangarTzln_PhaselDsgn\ProjMgmt\Agreements\Old\TO 2025_01_RevSept2025.docx Group Man 10 T ob a C n C" Oz y�' ro roM ro d Nceb a, roCD a:"�- ro d b b b b ro ro nA yo ZCD p C (CD CD CD dO O 'Uro Oax O.3 'roNO 'croN1 'LroNS 'iroN7 'roNO 'Z3 'roN C:d C O .O0 OO. O `'C C p CD C C CD ORID CD S' y CD CD CD CD CD CY CD CD F-ry Rrp ID �. CD 0 i-t 0 CD ID CD CD M ..� n n nCD M a y n ni CD c�`*D a O Cj o o 'AID b ►r1 Ciy7 ►y, F•~• o '�' b' ' N h °�, M M. �• a a N o !'3 (,D" H S Cy" ('D CCD D w° CDCD y b to w CD CD ID Ell w N. o x n b a c CDP CD CD r CD C. CD C� rb p � CD (D .C-. CD n n, C.CD CD Fy N bQ El " W VG :iQ CD d CD CD V] CD ac �% aQ •� aq hj rn ro w; w CDCD 1'r CD au d o w CD a CD CD CD G 41 A N 00 '7• ll A VI e� R N n n 0 o N o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 O O O O N 0 � o a N OQ m to `C ro CD K 0 0 0 Cl 0 0— �-' O o mrD 0 O R N oo O N N? W ON N N l.D N A N N O W 00 O\ 01 •P O A ? A N ON N w 69 .r�,� fD a arc feD a a1 00 O O D1 00 Cl O A N N W w N a\ •P A V, w w w O w O W N N O O O O O O N NeD O CD 65 d o CD d 0 0 0 0 w O Cl O W O A A O A _ 01 0 Cl Cl 0 0 0 0 0 0 0 0 0 0 0 0 Cl Cl 0 O R p CD < r0 0 0 0 0 0 0 Cl 0 0 W 0 0 0 0 0 0 0 0 Cl 0 0 O O ClO O O O O O O O O Cl O R V1 b N R t r" ro W O .Z O O O O O O O O O O O O O O CD O CD O A O 0 0 0 0 0 0 0 0 0 0 0 0 0 N N EA� n a T G CD JO A -1 N A O �!ebp N 0 0 0 0 0 0 0 0 0 0 0 0 Cl 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 O '~' N a fA 00 �. O O O w N 0 0 w 0 0 0 O O O O O O O O O O CDO O O A O O N -P N N O i3. Do N y O 00 In Vt O1 N T 41 W A 00 A Vi c.n 01 C J N O1 O1 O1 A .P 01 A Cl (.A nd�69 69 69 69 69 A b9 N 69 oo N 6) b9 Is69 69 69 w b9 U 69 .- 69 — 69 .� 69 ? N 65 N 69 N 69 A E„ y ff3 oo b9 w f� 69 .- 69 .- 69 69 69 ? b,y O C/j Uj N 00 00 00 vA -j O O O IJ W �O N 41 00 01 i-A 01 ut O Ut O N ? Q\ 00 o0 00 W 00 O\ A 00 w 00 O J O A 00 'A �O �l 00 Vi N v N O �O J> y n Vl y C1 00 .- w 0 00 T O 00 N A p W W W W W UA 00 00 00 O 00 O O O �c 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 O 0 O 0 O 0 O 0 O 0 0 0 O 0 O 0 O 0 O 0 O 0 O 0 O e o e N z y C• 1n.1 t roy yy�Cro�dbro�zbby'�bnb��,�� ay c oID Z tr C° i i 0 i o CD o o 'ZI co co C y y a pID G coo o a g ,p R• ro bID CD CDCD a �• �• y o � C7 w ua• c 00 CA n n ."r.' t�i c e P NeD 0 0 0 0 0 O O O O O O O 69 � O W i N o� O ? 4A N O� A N N 00 N •P 00 41 N — N N N y 69 d A �� y a O W O G N •P ao N O N A W 0� 00 00 C� Cl AC, 41 �n Q y O d CD A Cl O O N O 0 0 0 000 0 0 0 0 0 O� O O O R 5 G A b _N A O O n w 0 0 Cl 0 0 0 O O o 0 0 0 0 Cn ro N c r.w ro O R A 0 0 0 0 0 0 0 0 Cl 0 0 0 0 Cl 0 0 0 0 O p N N NnG "o � O O O O O O O O O O O O O 0 0 0 0 0 0 a 0 o p C 0 0 0 00 N O O41 O A N O O O O O N O � a1 "y� �isti N O1 00 O O N Vi 00 m -P, ? to 00 �o ndy 69 69 Hi N �i bol)N 69 W N N 69 69 69 N O W �7 D1 ? .A 4U O N `0 00 C> O rf 00 o0 N 0o Cl O 00 oo O �1 �' vi oo 00 W w A vi W 00 00 00 DD �> \O N •P 0Cl�0 o0 0o O, �O 00 00 vi a\ ? oo a1 O O O O O O O O O O O O O O O O O O O O O O O O O O 0 O 0 O 0 O 0 O 0 O 0 O O O d Goo bG� r `V w °z 1y=dt�y O O vzi Ei, CC6 P- n t i cn Y UO a N C + CC . z CD C7 r c � O ca � y o y + a C CD y Cn Cn Cn ti 7 A �1 fi C C W b9 69 69 E 01 CryroD (� N �O O O C", U. n C b 7 O N 0 0 0 0 N O O N o �' � a d o a c, u O fD fD W RrD O N fD ro rD a + o D o N W ono x O O d CD k .. 00 A O R r ro A 41 W (D O 6s 6s cNli v, W y ro ; ro ro W _Nft N N � O O O O O O CD O O O O O'O O tA FA pyp 00 C. J O 7 � O y R b xo N J � A O A A v A i w ice+ N (n w N w 41 w w C7 �l Vl w -A 69 69 l!i O 6s Ess 6s 0 0 O, O T 0 0 0 �O O O N O Cl O O O W O O Cloo a)O O ClO O, O O N O O O