HomeMy WebLinkAbout2025-08-12-minutes-solid-waste-and-maintenanceKITTITAS COUNTY
SOLID WASTE AND MAINTENANCE MINUTES
BOCC CONFERENCE ROOM, 205 WEST 5TH ROOM 108 - ELLENSBURG
Regular Meeting
TUESDAY 2:00 PM Angus 12, 2025
Board members present: Chairman Laura Osiadacz, Vice- Chairman Cory Wright
(Absent), and Commissioner Brett Wachsmith
Others: Patti Stacey, Lisa Lawrence, Cody Cupp and Jeanne Killgore (Out at 2:30 p.m.)
Call to Order at 2:00 p.m.
Citizen Comments (1 min. time limit) None
Solid Waste Updates: Patti informed the Board that she is working on the new Transfer Station
Project with the change orders below. Patti informed the Board that she is rejecting the quality of
314 yards of concrete on the recent pour of a portion of the tip floor. Discussion was held on
ECP and that they have had their engineers on site. Further discussion included ECP's cement
supplier and the assumption that there was too much lime in the mix.
Patti informed the Board that she is still waiting on the money due from Public Works for the
purchase of Water Rights at the new Transfer Station property, letting them know that is why she
hasn't started the new entrance to Cle Elum Transfer Station Project.
Grinder Replacement — Discussion: Patti informed the Board that she has applied for a Federal
EPA Grant for the purchase of a new electric grinder with solar power capabilities. Patti let the
Board know that the application has made it to the final round and that she should hear in
December if it is awarded. Discussion was held on the $600,000.00 purchase cost along with an
approximately $70,000.00 trade in value of the current grinder. Further discussion included
timeframes and the long lead time once the machine is ordered, since it is not an in -stock item
and has to be built. Board approved working with Manufacturer to get machine manufacturing
started.
Request Board Approval of Change Order No. 8 for New Transfer Station: Discussion was
held on Change order No. 8 increase to the contract in the amount of $104,401.24 due to design
issues. Commissioner Wachsmith moved to approve, Commissioner Osiadacz seconded the
motion. Discussion was held on going after the Engineer to re -coup funds. Motion passed 2-0.
Request Board Approval of Change Order No. 9 for New Transfer Station:: Discussion
was held on Change order No. 9. Patti informed the Board the Staff Report was wrong as she
found an error saving some money with an increase to the contract in the amount of $127,737.00
rather than $131,198.00. Commissioner Wachsmith moved to approve, Commissioner Osiadacz
seconded the motion. Motion passed 2-0.
2025-08-12 MINUTES
Facilities Updates: Cody gave the Board an update on the Jail kitchen leak and repairs.
Discussion was held on the Jail siding repair project and the cost of the jail detention hardware.
Further discussion included the original Jail build design issues.
Staffing Discussion/Decision: Patti presented the Board with a Staff Report requesting to hire a
Project Manager for the Maintenance Department. Discussion was held on the projects currently
on the books and the need for additional staff to manage them.
At 2:23 p.m. Chairman Osiadacz announced the Board would recess into executive Session for 5
minutes with no action anticipated. Per RCW 42.30.110 (d) To review negotiations on the
performance of publicly bid contracts when public knowledge regarding such consideration
would cause a likelihood of increased costs. At 2:28 p.m. the Board reconvened from Executive
Session, no action was taken.
Further discussion took place on the need and cost of a project manager position. The Board
supported the position and directed staff to move forward with a Project Manager Position.
Discussion on Moving Probation to Courthouse: Patti informed the Board that she needed to
budget for the remodel. Discussion was held on what the reception area in the hallway would
look like. The Board directed staff to provide costs and move forward with moving Probation to
the Courthouse.
Other Business — No Action to be taken
Patti informed the Board that she would be bringing a call for bid notification to their Voucher
session on Thursday. A brief discussion was held on the upcoming public hearing for a rate
increase to the Solid Waste Fee Schedule. Discussion was held on the new hires in maintenance
and the posting of the Maintenance Tech position.
Concluded at 2:43 p.m.
1
Lisa Lawrence
2025-08-12 MINUTES
KITTITAS COUNTY COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
Laura Osiadacz, Chairman
KITTITAS COUNTY COMMISSIONERS
Solid Waste and Maintenance
Regular Meeting
Tuesday August 12, 2025 - 2:00 PM
BOCC Conference Room
205 West 5th Room 108 - Ellensburg
1. Call to Order
2. Citizen Comments (1 min. time limit)
3. Solid Waste Updates
4. Grinder Replacement - Discussion
5. Request Board Approval on Change Order No. 8 for New Transfer Station
6. Request Board Approval on Change Order No. 9 for New Transfer Station
7. Facilities Updates
8. Staffing Discussion/Decision
9. Discussion on Moving Probation to Courthouse
10.Other Business - No Action to be taken
11. Concluded
Created on 8/11/2025 12:58:17 PM
KITTITAS COUNTY
BOARD OF COUNTY COMMISSIONERS
STAFF REPORT
Solid Waste
SPECIAL MEETING DATE: August 12,2025
TOPIC: Change Order No. 8
ACTION REQUESTED: Board's Signature on Change Order No. 8
LEAD STAFF: Patti Stacey, Director
RECOMMENDATION: Recommend Boards Signature on Change Order Number 8 with
Belsaas and Smith Construction, Inc.
BRIEFING SUMMARY: We have completed the review of Change Order Proposals
(COP) #22, COP #31, COP #33, and COP #35R. These proposals have been
incorporated into Change order No. 8 and are ready for the Board's signature.
BACKGROUND: On September 3, 2024, the Board of County Commissioners approved
a resolution to award the bid for the Lower County Transfer Station to Belsaas and Smith
Construction, Inc.
DISCUSSION: Change Order Number 8 addresses the following issues:
COP #22: Installation of Roof and Wall drains.
COP #3 1: Scalehouse retaining walls. Add 10 calendar days to contract.
COP #33: Delete trench drains and install Catch basins.
COP #35R: South parking lot grade revisions and valley gutter. Add 7 calendar days to
contract.
FISCAL IMPACTS: Increase of $104,401.24 to the contract before Washington State
Sales Tax
ATTACHMENTS: Change Order No. 8, COP #22, COP #3 1, COP #33, and COP #35R.
Legal consultation - No
Finance consulted - No
Page I of 1
Solid Waste "Special Meeting Staff Report", 2/21/2024
Kittitas County Solid Waste
925 Industrial Way
Ellensburg, WA 98926
August 12, 2025
Belsaas and Smith Construction
103 East 4ch Avenue, Suite 209
Ellensburg, WA 98926
Project: Lower Valley Transfer, Change Order No. 8
Mr. Nelson,
I am writing to formally acknowledge and award change order number 8 for the following Change
Order Proposals (COP):
COP #22: Roof and wall drains $17,758.00
COP #31: Scale house retaining walls $15,096.60
10 contract days
COP #33: Delete trench drains install Type 1 catch $-7,120.77
basins.
COP #35R: South parking lot grade revisions and $78,667.41
valley gutter 7 Contract days.
Change Order No. 8 Total $104,401.24
This change adds 15 Calendar days to our contract dated September 3, 2024.
Base Bid and Additive A2
$18,441,939.80
Additive Al
$642,000.00
Change Order No. 2
<$11,754.08>
Change Order No. 3
<$28,041.41 >
Change Order No. 4
$145,224.93
Change Order No. 5
$233,662.44
Change Order No. 6
<$24,051.84>
Change Order No. 7
$96,439.74
Change Order No. 8
$104,401.24
Subtotal
$19,599,820.82
WSST
$1,685,584.59
Total $21,284,405,41
Please consider this letter as our formal acceptance of the change order.
We look forward to successfully completing this project together with these agreed -upon
adjustments. Thank you,
Bryan Nelson
Secretary
Belsaas and Smith Construction
103 E 4th Ave # 209
Ellensburg, WA 98926
Laura Osiadacz.
Chair, Board of County Commissioners
Kittitas County
205 W 5th Ave #108
Ellensburg WA 98926
BELSAAS
8t
,SMITH-,.
Patti Stacey
Kittitas County Solid Waste
1001 Industrial Way
Ellensburg, WA 98926
Project: Lower County Transfer Station Scale Improvements
BELSAAS & SMITH CONSTRUCTION, INC.
P.O. BOX 926 / 103 EAST 4TH AVE, SUITE 209
ELLENSBURG, WA 98926
509-925-9747 FAX: 509-962-3031
February 24111, 2025
RE: Change Order Proposal 22— Retaining Wall Drain and Roof Drains at Transfer Station Building
We are offering the described work and pricing below as a Change Order Proposal to account for additional costs
due to design changes proposed by the Owner.
Plan Sheet C5A was provided with revisions detailing a drainage envelope being installed on the west side of both
retaining walls running north and south beyond the tunnel wall. The drainage envelope is simply a perforated 4"
pipe surrounded in an 18" x 18" square of drain rock and wrapped in fabric. The drain runs the length of the wall
and stair area to the south. The pipes daylight out at the lower end of the walls.
Plan Sheet C6 was provided with revisions detailing a new collector pipe running along the west edge of the
transfer building, stubbing up at each proposed roof drain, and then daylighting to the south at the bottom of the
building mound with a splash pad and swale to drain.
The total cost of the change order is listed below and broken down on the attached spreadsheet.
Change Order Total: $ 17,758.00
No additional contract time will be requested with this proposal.
Feel free to contact me with questions or concerns.
Sincerely,
'6-ya'y Ale'60ir
Bryan Nelson
Belsaas & Smith Construction, Inc.
Page 1 of 1
.I
BELSAAS PO BOX 926
& ELLENSBURG, WA 9B926
SMITH 509-925-9747, FAX509-962-3031
CHANGE ORDER COST BREAKDOWN
OWNER: Kittitas County Solid Waste DATE OF PROPOSAL: 03/04/25
COP #: 22
DATE WORK PERFORMED: TBD
LOCATION: Transfer Station Building
DESCRIPTION: Install drainage improvements for the transfer station building including roof drain connections, transmition
piping, cleanouts, and outlet for the Transfer Station Building - includes 280' of 6" transmission piping, 3 clean -oats and 5
vertical downspout connections. Also, provide wall drain, transmition piping and outlet for retaining walls near the Transfer
Building - includes 153' of drain pipe wrapped in drain rock and fabric.
ITEM
NAME
TRADE
CITY
HRS
RATE
TOTAL
1
Excavator Operator
1
20
$ 99.23
$ 1,984.60
2
Excavator Operator
1
0
$ 99.23
$ -
3
Loader Operator
1
20
$ 99.23
$ 1,984.60
4
Laborer
3
20
$ 62.12
$ 3,727.20
5
Truck Driver
1
0
$ 75.19
$
Sub -Total: S /,696.4U
15% OH & Profit: $ 1,154.46
TOTAL LABOR: $ 8,850.86
ITEM
I DESCRIPTION
YEAR / MODEL / SIZE
HRS
RATE 1
TOTAL
1
Excavator
CAT 312
20
$ 115.07
$ 2,301.40
2
Loader
Cat 938
20
$ 71.31
$ 1,426.20
3
$ -
4
$ -
5
$ -
Sub -Total: S 3,727.60
15% OH & Profit: $ 559.14
TOTAL EQUIPMENT: $ 4,296.74
ITEM
I DESCRIPTION VENDOR
UNIT
I CITY I UNITCOST TOTAL
1
Piping Materials
HD Fowler
LS
1
$ 1,689.00
$ 1,689.00
2
Drain Rock
ECp
TN
28
$ 17.00
$ 476.00
3
Bedding
ECP
TN
68
$ 17.00
$ 1,156.00
4
Fabric
HD Fowler
LS
1
$ 595.00
$ 595.00
Sub -'Dotal: 3,91b.UU
8.3% WSS Tax
18% OH & Profit: $ 704.88
TOTAL MATERIALS: $ 4,620.88
ITEM COMPANY NAME DESCRIPTION OF WORK FA REF SHEET # TOTAL
1
2
$ -
3
$
Sub -Total: 5
8% OH & Profit: $ -
TOTAL SUBCONTRACTORS: $ -
COMBINED TOTAL: $ 17,758.48
BELSAA
SMITH
BELSASC0330H
May 19, 2025
Re: Scale house retaining walls #31
P.O. BOX 926 / 103 EAST 4TH AVE, SUITE 209
ELLENSBURG, WA 98926
509-925-9747 FAX: 509-962-3031
brandon@belsmith.com
Per the description below, we present the following change order proposal #31 (COP#31).
Per RFI 36 it was revealed that we had grade issues between the scale house, the approach
slab, and the handicap parking at the north end of the scale house building. The engineers
responded with drawing sheet C6A which added retaining walls to this area. This COP
encompasses those changes, all other associated cost will be tracked by contract unit prices.
Please see RFI 36 in project site for the more specifics on how this COP progressed if needed.
Total Cost Added for retaining walls: $58,096.60
Deduct for guardrails: ($43,000.00)
Total Cost added to contract: $15,096.60 + WSST
Time extension required: 10 days
Sincerely,
Brandon Drexler,
Belsaas & Smith Construction
•
•
•
•
ui
ui
1:
U)
•
uj
LLJ
z "r
Cl)
U
LLJ
U) w
z co
0 -1
U U)
•
L•
w
co
•
•
LLJ
z
I.J
1111�11111�11�11111
1�11�1111111110CN
111�
LU
uj
LLI
ui
ui
z co
a.
LU
..
0
....................
8
m
W
b 5
0
ui
� W
O O
u O
X W
W U
W
O
�= z
W
z
Q
U
U)
H
,J)�
(1) Z
W
U�
Q <t
00
�- z
E-
UW
HF-
z to
H
oW
W U-
r U-
Q�F-
uj
o�
za
I>
CO J
� W
Ouj
W
U)
W
w
W
"1
3Z636 N0MIVNYM'9i1f195N3��3 s� '•+-"" mo ''"'"
rei AYM �YIikLNn N1 S76 + r -
+r�i � 3LSYh101lOS ALNf10lSY11111l1 eS� •+u.a as �5.•[.in ox.mi _
7 gMa'baq (m) HVi c—, iSLb)
NOIIVIS auas
m(an�s'ary an�anY wobl sobL a U
• slq-Auoo pue &luevsuoo pyuaw-1Z,
o
Iw �� taiYna ulaoleln3aq 'om V31fV H111ON-Mdld 9NlObilO k
W�
I
,III . S �• w � _�,.
9ZER5 AVM
VI ISnON1f195N3113
�S,�t� morrto oiAinaydnanaxsi AtlMOG AINfloo S�5
31SVM III A1FIf10] SV11llIN
amrrou uoieinseeoeanss' NOUV1S N3dSN"IAa7VA N3M0'
a3ltldo rnIOI5IA38 ply BsnOH3lVOS-NVld ONIOVN'Jaa
3
3 1
n 1 � �a
O
z u z LL
u I I
II
3 �O t5
a w
t� 5
—� o J c
ix
z
F " F
I I
I I
I
;ee � m
o V) n 4
S 8
8
o „
m
F o0
w J" w
co
�
N
Q
W
H
(n
¢
r
V)
Q
W
$
Di
O
U
8
Z
w
rl
U
w
m
sn
U
p
3
w
�
�g
C7
U
Z
r
U
Z
m
inZ
w
O
!R
5
bi
w
a
N
O
Oa
�LL
3� LL
:LL
V
�LL
N
ab..' (E05) xb 00 —1 ISLH e
sooeo �mau,ua=M'a�.wu-ae (�
t0l ayry'3N anuanb Y'AbI SnbL �+ R
atgoetluoO pua quepnsuoO (eluowudlnu3
v
BELSpAA
O[
SMITH
BELSASC0330H
June 3, 2025
Re: Catch basin substitution COP #33
P.O. BOX 926 / 103 EAST 4T" AVE, SUITE 209
ELLENSBURG, WA 98926
509-925-9747 FAX: 509-962-3031
brandon@beismith.com
Per the description below, we present the following change order proposal #33 (COP#33).
COP #33 includes all the labor and materials needed to substitute the per plan trench drains
with the proposed type 1 catch basins. The proposed catch basins are a cost effective way of
achieving the same outcome while offering a deduction to the contract.
Total Cost Deduct:
Time extension required: 0 days
Sincerely,
Brandon Drexler,
Belsaas & Smith Construction
$-7,120.77 + WSST
CN
4—
U)
111111111
LIJ
uj
1:
U)
z
LLJ
cr) cl�
Z
0
U)
0
Do-
ry
CL
CO
C�
w
CO
0
w
U)
0
CN
4..
0
N
F-
uj
LLJ
"r
U)
LU
U)
z
0
ui
U)
0
OIL
CL
ucj)
0
LU
(D
z
r....................
w
Q
W
W
0
w w
X w
Z (-) 0 0
z
w 0
F-
w
w C)
w p
0
z
E
BELSAAS
SMITH
BELSASC0330H
August 1, 2025
Re: South Parking Regrading, Valley Gutter, and Culvert
P.O. BOX 926 / 103 EAST 4T" AVE, SUITE 209
ELLENSBURG, WA 98926
509-925-9747 FAX: 509-962-3031
rilev@belsmith.com
Per the description below, we present the following change order proposal #35 (COP#35).
A. Added work to re -grade and add drainage features for the area north of the MRW and
Admin Bldgs. Work done for new plans provided with changes necessary to add
drainage for MRW downspouts, coverage over utility trenches and drainage Swale
changes. Our work includes: 1. Exposing the new sewer main at 2 locations in order to
pour a 10'x2'x2' encasement for protection including backfill and compaction; 2. Cutting
down and regrading subgrade to accommodate for 400 Lf of 4' wide valley gutter. Plus
added work to grade gravel base in this area for the narrow -sloped feature; 3. Install
new 60' ductile iron culvert; 4. 200' of added 'wide ditch' Swale and added work to
modify and move about 600' of swales in other areas; 5. Add 14' of 18" DI culvert to SE
corner, but delete 92' of 18" DI culvert shown on C4; 6. Add quarry spalls over fabric pad
for hydrodynamic separator.
B. Added 375 LF of 4' wide 6" deep valley gutter, 5 truncated domes, increased striping,
and deducted 405 SF of sidewalk.
Total Cost added to contract: $78,667.41+ WSST
Time extension required: 15 days
Sincerely,
Riley Eres,
Belsaas & Smith Construction
I-
Cfl
O
O
T-
C)
O
M
M
C14
O
0
0
N
N
O
O
O
00
O
O
O
000
CA
dT
CA
00
CO
00
I-
00
00
O
"T
d
p
MIT
t�
I-
ti
O
M
M
N
IT
00
m O
c-
V
A
N
N
N
00
QU
Q
LO
Q
O
oo
CD
O
00
0
0
0
0
0
0
0
0
0
0
0
0
0
0
m
CD
o�
(M
O
o
Cfl
T
Wp
N
C70
N
O
QU
U
2
m
o
�j
�p
o
U
U
0
0
0
0
000
O
O
O
LO
LO
0
0
0
�
M
0
0
0
0
O
0
0
N
U)
0
0
0
CO
O
O
Iq
f`
0
0
01-
0
CD
O
M
000Iq
O
CDNr-N
�MOOOM0
00
N
CEO
L1J U
v-
N
N
O
O
N
CD
CO
m
m
O
M
N
0
LLJ
N
N
N
M
M
ti
rn
r~
rn
rn
rn
2
�
a
(n
p
C3J
0
O
=
O
Z
LO
M
N
00
Lo
M
LO
�w
LOCO
�r
N
3
0
O
o0
o
O
N
00
O
N
O
N
L
N
C
N
COO
LU
)
O
M
LLI
Z =
0
O
L
L
/�
U
L
L
L
VJ
J
L
L'
L'
L'
L'
L
�~
L
L
L
L
L'
2
L
2
V/
J
V)
J
Z
2
2
2
2
2
2
2
2
2
2
m
a
2
2
2
2
2
o
>
--co
O
V >
Z
N
Q
?
CO
N
r
N
`-
X
W
00
-T"T
dT
N
CD
dT
IT
N
N
O
�1
O
O
IT
N
IT
N-
Cfl
M
M
O
co
aD
N
-
Q
U
d
w
Cl)
v+ 0�
m
Z m
.0
O
_
D
O J
U U)
°�
m
C
^
'
Cl)^
v+ N
L
��
to
A\
>
0.•
O
Y
>>
o p
0)
�o�
Na
��
o
O-
of
0
�U
-
ao
fn �
Z
m
w
d
d
c
~
'3
ca
cn
m
4 p
V
N
O
N
c"a
U
(�0
U
_N
O
O
LL
Q
LL
j
W
X�
O
C�
>
X
U
3
w
Q
LL,
J
�LU
V
Cl)
v+
W
L
N
L
N
0
L
M
.`
T
�O/
LL
C
L
N
=
L
N
N
//
�/J
J
00
//�
y/
Z
�
L
("06
x
C0
G
0
C]
M�
Q
O
X
O~
J
Q
W Q
3
N
OCL
v
M
N
Q
0
O
U
N
O�
O
0
M
-'
��
m U
Oto0mUU>0-j
-0
0�0�FL-UUYNO
�U
cm)
QO-10000o
O-
*k
LO
CN
ui
in
ui
CL
06 LU
..
....:...............
m
w
iti
ED
LU w
w w
O_ O
{ 1.
w O
X W
LU U
LU
O
z
(w
V
z
Q
U
cn
F
Cl) Z
02
Q <t
O❑
f- z
H Q
Uw
w
z (q
O E-
UV
w w
= LL
F- Q
w F-
z
J
H
w
0
J
O=
wv
/w/
V�
/
w
W
w
B
O
O
O
N
N
O
O
O
O
O
O
LO
O
LO
O
O
000
O
O
000000
O
d
LO
O
I-
O
O
O�
M
O (n
mO
c��
rn
N
ti
Q U
m
LO
Q
O
O
00
0
0
00
00
0
00
M
0
00
0
0
00
0
00
0
0
0
0
CO
fl (U)
0
C)
O
O
CO
C,
N
o0
ti
rn
OLUp
Q
U
0
�
o
0
CD
m
_
L6
U
U
co
�—
o
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
cn
o
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
NUJ
0
0
0
0
0
0
0
0
00
0
0
0
0
0
0
0
0
00
0
0
00
00
0
0
0
0
W
v-
O
O
O
0
N
N
O
O
O
O
O
I-
�O
OIT
OO
�titi
W
U)
m
CO
N
N
N
W
O
J
00O
OO
2
U
d
Z
C1
W
O
o
0
0
O
o
O
N
IT
O
O
B
O
O
�--
N
T-
�
CV
N
W
W_
Z
N
L
U)
J
LL
U)LL
m
0
2
2
U
2=
J
W
J
J
Z
V 0
Z
o
LO
Iq
CO
(.0
ovr-r-�
Y
O
Q
c
o
w
Z m
`r)
0 J
uS
-_
>
V U)
ro
Z
�
_
=
N
2 0-
J
��
L
W
M
LO
ro
�j
I*-
N
U)
�'�
~
U-
J
N
N
W
4
N
Cl)uj
v I
C
LL
N
O
O
U)
O
U)
N
E
L
c6
W
N
�
�
0
E
0
i�
ro�
0
oo
+6
cn
��
+'
�
0
�
0��
�
E�
(/)
z
>.
Q
L�
E
M-0-0U
ro
m
-0
a�
LU
>
E
a
.L
ro
U
U
d)
Cl)V
�
E
N
a)
a)
L
p
+-
x
o�
Y
aL
Q
'L
(iJ
Z
J
U
rn
Vi
U
L
L
�I-
L
LL
L
cn
L
Cl)
u)
L
N
>J
�
�
�-
/V/J�
'+/�
v,
a
W =
c
O
OL
Q.
c
�Q-0"
U-0
O
/
N
O
O.�.�
F-
py�
W
M
Q
O
O
ro
ro
O
O
O
a
Im(nQQdd
a
a
ro
(�
I
I
I
I
I
O
W U
��
a-cn0UJJLL���
I-
111111111111111111�
co
11111�11�11111�1111
CN
uj
IIIIIIIIIIIIIIIIIIII
LU
ui
LU
iz
06
.uj
.
.....:.............:
W
(3
Z
dC
U
U)
F-
U) Z
U�
Q Q
OQ
F- Z
F- `t
H
z cn
O E—
UU
wLL
W
= LL
F- Q
w F-
Z <
J
F-
w
O=
wV
W
U)
W
W
W
3Z686 NOiONIHSVM'Odn8SN31131171
AtlM1VItl15NON1O SV • ago ;�,� ooasmo �.�
31SVM lVlI OS A1NfOSV11llIN R
il ma ua no iaaeoeo�ssi NOI1V1S NaJSNVldlk3llVA H3MOl 9b6 oa9a B6 ul a�aoe /~�
d W ?�L11�3`Oae LOlali'S'3NarivanV4YlblS.lz
-013GAU03 pue WOW-01 ]MU-10llw3
31tla Nolsln3a g g
.a s 13W H1f10S -Nbld'JNIdVN'J � d
�oN
j JI
ut
nw ' 3 +� W
a$
j
wo=
nm mad w a51
W.
I '
I
�.
is
4 I
io na
ffi
GI `/1 � j II� i��I IIII 91�II gP
D1
e w
-
w
y U,
N 6
xx > Q
WN °
W w �
Z o
U
KITTITAS COUNTY
BOARD OF COUNTY COMMISSIONERS
STAFF REPORT
Solid Waste
SPECIAL MEETING DATE: August 12, 2025
TOPIC: Change Order No. 9
ACTION REQUESTED: Board's Signature on Change Order No. 9
LEAD STAFF: Patti Stacey, Director
RECOMMENDATION: Recommend Boards Signature on Change Order Number 9 with
Belsaas and Smith Construction, Inc.
BRIEFING SUMMARY: We have completed the review of Change Order Proposals
COP #37. This proposal would incorporate the tire and refrigerator loading area into the
project. This area was part of the original bid alternate that wasn't accepted at bid time.
The design has been modified to accommodate the requirements for loading out both the
tires and refrigerators.
If approved this change will be incorporated into Change order No. 9 and is ready for the
Board's signature.
BACKGROUND: On September 3, 2024, the Board of County Commissioners approved
a resolution to award the bid for the Lower County Transfer Station to Belsaas and Smith
Construction, Inc.
DISCUSSION: Change Order Number 8 addresses the following issues:
COP #37: Tire Center
FISCAL IMPACTS: Increase of $40-to the contract before Washington State
Sales Tax
ATTACHMENTS: Change Order No. 9, COP #37.
Legal consultation - No
Finance consulted - No
Page 1ofI
Solid Waste "Special Meeting Staff Report", 2/21/2024
Kittitas County Solid Waste
925 Industrial Way
Ellensburg, WA 98926
August12,2025
Belsaas and Smith Construction
103 East 411 Avenue, Suite 209
Ellensburg, WA 98926
Project: Lower Valley Transfer, Change Order No. 9
Mr. Nelson,
I am writing to formally acknowledge and award change order number 9 forthe following Change
Order Proposals (COP):
COP #37R: Tire Center
Change Order No. 9 Total
$127,737.00
$127,737.00
This change adds 15 Calendar days to our contract dated September 3, 2024.
Base Bid and AdditiveA2
$18,441,939.80
Additive Al
$642,000.00
Change Order No. 2
<$11,754.08>
Change Order No. 3
<$28,041.41>
Change Order No. 4
$145,224.93
Change Order No. 5
$233,662.44
Change Order No. 6
<$24,051.84>
Change Order No. 7
$96,439.74
Change Order No. 8
$104,401.24
Change Order No. 9
$127,737.00
Subtotal
$19,727,557.82
WSST
$1,696,569.97
Total $21,424,127.79
Please consider this letter as our formal acceptance of the change order.
We look forward to successfully completingthis project together with these agreed -upon
adjustments. Thank you,
i
Bryan Nelson
Secretary
Belsaas and Smith Construction
103 E 4th Ave # 209
Ellensburg, WA 98926
ra Osiadaci
ir, Board of County Commissioners
Kittitas County
205 W 5th Ave #108
Ellensburg WA 98926
B E LSA AS
t�L
SMITH
BELSASC0330H
July 10, 2025
Re: Tire Center Changes
P.O. BOX 926 / 103 EAST 4T" AVE, SUITE 209
ELLENSBURG, WA 98926
509-925-9747 FAX: 509-952-3031
riley@belsmith.com
Per the description below, we present the following change order proposal #37
(COP#37)Revised.
COP #37 includes the addition of the tire center as shown on the updated sheet C13 received
on 6/16/2025. The scope of work includes all the labor and materials to perform the specified
scope below.
• Excavation & Site Prep: Excavate footing as specified per the drawings and ensure
subgrade compaction.
• Form & Pour: Construct formwork and pour the required footings and retaining walls.
• Rebar: Supply and crew -install rebar per engineered layout; tie per code.
• Ecology Blocks: Delivery and placement of prefab retaining units per drawings.
• Backfill & Fine Grade: Backfill Excavated materials, compact, and fine grade to smooth
profile to achieve ample drainage.
• Chain -Link Fence: Supply materials, install posts and fabric along the specified
alignment.
All work to be constructed as shown on drawing sheet C13 Dated May 7,2025.
Total Cost added to contract: $127,737.00+ WSST
Time extension required: 15 days
Sincerely,
Riley Eres,
Belsaas & Smith Construction
N+
N
co
It
Ln
Cfl
r
m
rrocpco�rv�n
III
O
H
(f1
d3
EA
d}
fA
fA
ER
6Ft
6i4
U
N
M
LO
M
M
�t
r
m
U
M
M
r`
r-
to
M
C0
r-
L
3
C
Ef3
64
64
EFT
bl3
64
ell
EfT
Efl
0 o
0)
00
Lo
't
"tc
O
00
O`
�-
N
't
It
It
M
N
CD
CD
a
M
V
EFT
EA
Cfl
U}
EFT
Efl
EH
69
U3
a
M
r
00
r
00
m
0
0
LO
r
EA
U')
m
N
N
m
co
m
o
m
N
N
M
c0
Q
EFT
EA
G-?
V?
Efi
EFT
EFT
EF3
64
0
C)
C)
0
.-
CO
O
CO
O
O
M
O
O
N
00U')
M
O
O
O
't
00
't
c7
O
m
(0
t`
N
Z
O
N
4
00
O
O
O
d"
m
w
m
m
N
N
co
O
O
M
Co
.-
M
zf
d'
M
N
m
0
M
c1
a
C
�
U3
Ef-?
EA
Eii
Ei}
E13
U3
US
69
C
J
J-i
J
J
J
J
J
J
+T
C
-
O
[0
0
C
u'
m
C
O
(6
d
C
O
c
y
m
N
QT
cu
-
0
C
U
L-
0
CO
LL
O
x
W
M
a
7�
N
N
rT
p
`J
(n
C
U
U
O
C
0
C
C
0
0
'D
N
0
0
0
0
0-0
�UUWLLQLL�U
�$
N
CO
It
cf1
O
ti
o0
64
Mobilization check list
" Workina Days ( months)
Item #1 Description
Unit I Qty
I Qty Rate
I Total
3
Superintendent
HR/DY
10
1
$ 102.47
$ 1,024.70
4
Office
HR/DY
10
1
$ 88.02
$ 880.20
TOTAL MOB: $ 1,904.90
Item # Description Unit Qty Unit Price
1 I Concrete Footing LS 1 $ 31,928.00
*(Note: }
LABOR
Description Rate / Hr I Qty I Hrs
Total
Carpenter Form
$ 102.00
4
24
$ 9,792.00
Carpenter Pour
$ 102,00
6
6
$ 3,672.00
Carpenter Strip
$ 102.00
4
8
$ 3,264.00
Total Labor: $ 16,728.00
EQUIPMENT
Description
Rate / Hr
Qty Hrs Total
1
0
$
1
0
$
Total Equipment: $ -
SUPPLIERS
Description
Unit Price Qty I Unit
Total
Concrete Supply
$ 220.00
45
CY
$ 9,900.00
Forms
$ 1,400.00
1
LS
$ 1,400.00
Misc- ConcSupplies
$ 300.00
1
LS
$ 300.00
Sub -Total: $ 11,600.UU
Sales Tax (8%):
Total Suppliers: $ 11,600.00
SUBCONTRACTORS
Description I Unit Price
I Qty I Unit
I Total
Pump Truck 1 $ 3,600.00
1 1 LS
1 $ 3,600.00
Total Subcontractors: $ 3,600.U0
SUB -TOTAL: $ 31,928.00
Item # Description Unit Qty Unit Price
2 Concrete Retaining Wall LS 1 $ 43,244.00
(Note: )
LABOR
Description
Rate / Hr
I Qty
I Hrs
Total
Carpenter Form
$ 102.00
4
40
$ 16,320,00
Carpenter Pour
$ 102.00
6
6
$ 3,672.00
Carpenter Strip
$ 102.00
4
12
$ 4,896,00
Carpenter Sack
$ 102.00
4
12
$ 4,896.00
Total Labor: $ 29,7ZAM
EQUIPMENT
Description
Rate / Hr Qty Hrs
Total
1
0
$ -
1
0
$
Total Equipment: $ -
SUPPLIERS
Description
Unit Price
I Qty
I Unit
Total
Concrete Supply
$ 220.00
28
CY
$ 6,160.00
Forms
$ 3,100.00
1
LS
$ 3,100.00
Misc- ConcSupplies
$ 1,200.00
1
LS
$ 1,200.00
Sub -Total: otal: $ l 0,460.00
Sales Tax (8%):
Total Suppliers: $ 10,460.00
SUBCONTRACTORS
Description I Unit Price
I Qty
I Unit
I Total
Pump Truck 1 $ 3,000.00
1 1
LS
1 $ 3,000.00
Total Subcontractors: $ 3,uuu.uu
SUB -TOTAL: $ 43,244.00
Item # Description Unit Qty Unit Price
I 3 I — Ecology Blocks LS 1 $ 4,283.21
*(Note: )
LABOR
Description
Rate / Hr
I Qty
I Hrs
Total
Labor
$ 68.61
2
8
$ 1,097,76
Operator
$ 109.93
1
8
$ 879.46
Driver
$ 81.16
1
3
$ 243.49
Total Labor: $ Z,ZZU.79
EQUIPMENT
Description Rate / Hr
Qty
Hrs
I Total
DT w. trailer $ 87.50
1
3
1 $ 262.50
Total Equipment: $ 262.50
SUPPLIERS
Description
Unit Price I Qty
Unit
Total
ECP- Ecology Blocks
$ 100.00
18
Ea
$ 1,800.00
$
$ -
$ -
$
Sub- iotai: s 1,t$UU.UU
Sales Tax (8%):
Total Suppliers: $ 1,800.00
SUBCONTRACTORS
Description Unit Price Qty Unit Total
$
Total Subcontractors: $ -
SUB -TOTAL: $ 4,283.21
Item # Description Unit Qty Unit Price
4 Footing Excavation LS 1 $ 4,300.ss
"(Note: )
LABOR
Description
Rate / Hr
I Qty I Hrs
Total
Labor
$ 68.61
2
6
$ 823.31
Operator
$ 109.93
1
6
$ 659.60
Driver
$ 81.16
1
6
$ 486.97
I Otal Labor: zl� "I,vutp.00
EQUIPMENT
Description
Rate / Hr
Qty
I Hrs
Total
320
$ 94.75
1
6
$ 568.50
Solo DT/WT
$ 76.25
1
6
$ 457.50
Total Equipment: $ 1,uzb.uu
SUPPLIERS
Description
Unit Price I Qty I Unit
Total
Gravel base
$ 14.50
90
Tn
$ 1,305.00
sun- i otar z 1,suo.uu
Sales Tax (8%):
Total Suppliers: $ 1,305.00
SUBCONTRACTORS
Description
Unit Price Qty Unit
I Total
i otai subcontractors: Z -
SUB -TOTAL: $ 4,300.88
Item # Description Unit Qty Unit Price
5 Additional Backfill of Footing. LS 1 1.$ 3,009.50
*(Note: )
LABOR
Description
Rate / Hr
Qty
Hrs
Total
Labor
$ 68.61
2
6
$ 823.31
Operator
$ 109.93
2
6
$ 1,319.19
Total Labor: $ 2,142.bU
EQUIPMENT
Description Rate / Hr Qty Hrs
Total
320
$ 94.75
1
6
$ 568.50
MH/BH
$ 49.75
1
6
$ 298.50
Total Equipment: $ Bti7.UU
SUPPLIERS
Description
Unit Price
I Qty
I Unit
Total
$
$
Sub-] otal: $ -
Sales Tax (8%): $
Total Suppliers: $
SUBCONTRACTORS
Description Unit Price Qty Unit Total
$
Total Subcontractors: $
SUB -TOTAL: $ 3,009.50
Item # Description Unit Qty Unit Price
6 Fine Grading LS 1 $ 2,006.33
*(Note: )
LABOR
Description
Rate / Hr
Qty Hrs
Total
Labor
$ 68.61
2
4
$ 548.87
Operator
$ 109.93
2
4
$ 879A6
I otal Labor: zo 7,4Ltt.53
EQUIPMENT
Description Rate / Hr
Qty
Hrs Total
320
$ 94.75
1
4
$ 379.00
MH/BH
$ 49.75
1
4
$ 199.00
otal equipment: 4) 010.uu
SUPPLIERS
Description
Unit Price
I Qty
I Unit
Total
$ -
$
Sub- I otal: Z
Sales Tax (8%): $
Total Suppliers: $ -
SUBCONTRACTORS
Description Unit Price Qty Unit I Total
$ -
Total Subcontractors: $ -
SUS -TOTAL: $ 2,006.33
Item # Description Unit Qty Unit Price
7 Rebar Supply/Install LS 1 $ 9,847.00
*(Note: )
LABOR
Description
Rate / Hr Qty Hrs
Total
1
0
$
1
0
$
Total Labor: $ -
EQUIPMENT
Description
Rate / Hr
Qty
Hrs
Total
1
0
$
1
0
$ -
Total Equipment: $ -
SUPPLIERS
Description
Unit Price I Qty
Unit Total
$
$
tiun- i otai: Z
Sales Tax (8%): $
Total Suppliers: $ -
SUBCONTRACTORS
Description
Unit Price
I Qty
I Unit
Total
Rebar Subcontractor
9847
11
LS
1 $ 9,847.00
i otat tiugcontractors: 1� y,u41.uu
SUB -TOTAL: $ 9,847.00
Item tc Description Unit Qty Unit Price
8 Chainlink Fencing LS 1 $ 10,552.00
*(Note: )
LABOR
Description Rate / Hr I Qty I Hrs Total
Total Labor: $ -
EQUIPMENT
Description Rate / Hr I Qty I Hrs Total
Total Equipment: $ -
SUPPLIERS
Description Unit Price I Qty I Unit
Total
Sub -Total:
Sales Tax (8%): $
Total Suppliers: $
SUBCONTRACTORS
Description I Unit Price Qty I Unit Total
-ence Subcontractor 1 $ 10,552 11 LS $ 10,552.00
Total Subcontractors: $ 1u,bum
SUB -TOTAL: $ 10,552.00
KITTITAS COUNTY
BOARD OF COUNTY COMMISSIONERS
STAFF REPORT
Maintenance
SPECIAL MEETING DATE: August 12, 2025
TOPIC: Staff
ACTION REQUESTED: Boards direction regarding a hiring a Project Manager for the
Maintenance Department.
LEAD STAFF: Patti Stacey, Director
RECOMMENDATION: Recommend Boards approval to work with the Human
Recourse Department to hire a Project Manager for the Facility/Maintenance Department.
With the increase in workload for projects it is becoming clear that additional staff will
be needed to handle the work.
Event Center Arena: $12,000,000
RV Park Event Center $ 250,000 plus until completed
Search and Rescue: $ 2,700,000
Jail Projects $ 5,500,000
Continues search and courthouse relocation: $ unknown
This list does not include all the small works projects that need to be handled by the
Facilities Maintenance department.
I recommend that we proceed with filling this position before the end of the year so that
the projects going out to bid this fall have continuity of tracking.
BRIEFING SUMMARY: I have talked with the Human Resource Department and
would like to continue to work with them to develop a posting for this position.
BACKGROUND: Previously all of the contract management has been done by the
Facilities and Waste Operation Director, with assistance for the Project Manager in the
Solid Waste Department and assistance from the Assistant Maintenance Director. We no
longer have a Project Manager in the Solid Waste Department that can assist with the
other projects.
DISCUSSION: Recommend Boards approval to continue working with Human
Resources Department for Project Manager Position.
FISCAL IMPACTS: $72,560 — $88,416 plus benefits.