HomeMy WebLinkAboutCITY OF CLE ELUM REC CENTER LARGE CAP APPLICATIONJune 25, 2025
To the Members of the Kittitas County Lodging Tax Advisory Committee:
As representatives of a team that has worked diligently for several years to bring a community
recreation center to upper Kittitas county, we thank you for the opportunity to submit this Application
for the 2025 Lodging Tax Large Capital Project Program. While a community recreation center will be
transformative for residents of all ages in upper county, who have voiced their desires for a
community recreation center for more than twenty years, we believe this project is uniquely deserving
of lodging tax funding because:
•Currently, there are very few indoor recreation options for visitors in upper county. A visitor
occupying one of the many short-term rentals outside Suncadia, has no access to such
facilities. Even visitors to Suncadia are looking for options, as overcrowding of Suncadia’s
facilities continues to increase. While not quantifiable, this facility will undoubtedly attract
visitors.
•The city has approved our application, and construction documents are complete. This
project is shovel-ready, once governance and financing mechanisms are finalized.
•Basketball courts and a competition swimming pool will increase “sports tourism,”
•By providing an indoor recreation alternative for visitors, this project directly supports tourism
mitigation strategies included in the Kittitas County Tourism Plan
•Because the majority of lodging tax funds are generated in upper county, reinvesting in
upper county is equitable and economically sensible.
•A significant grant of lodging tax funds would provide significant fundraising leverage for
additional grant opportunities the team is pursuing.
In this Application, the Lodging Tax Committee will find support for the above (and more) compelling
reasons to award lodging tax funds to this project. If you have any questions or require additional
information, please contact us.
Respectfully submitted,
Claire Nicholls
President, Upper Kittitas County
Community Recreation Center Alliance
Matthew Lundh
Mayor, City of Cle Elum
Project Team Member
509-304-4576 509-260-1241
Kittitas County Lodging Tax Fund Application
for Tourism-Related Infrastructure Projects
Submitted by: The City of Cle Elum
For: Upper Kittitas County
Community Recreation Center
June 2025
Thank you for the opportunity to submit this application.
2
Table of Contents
Page
I.Applicant Information 3
II.Project Overview 4
1.Project Description
2.Tourism Benefit
3.Target Users
III.Budget and Funding 11
1.Project Budget
2.Funding Sources
3.Long-Term Maintenance Plan
IV.Project Timeline 15
V.Feasibility and Risk Management 15
1.Feasibility
2.Risk Management
VI.Tourism Metrics and Success Measurement 16
VII.Applicant Certification 17
Because of the size of these documents, the following supporting documents are
available by links included here (and later in this Application), or upon request. ”Ctrl
Click” to open the links.
Feasibility Study Report
Schematic Design Report
Construction Documents (available upon request)
Target Funding Sources
Detailed Construction Budget
Detailed Operating Budget (spreadsheet with multiple tabs; available upon request)
Overview of Final Design
3
I.Applicant Information
Project Title: Upper Kittitas County Community Recreation Center
Total Request Amount: $4 million
Applicant Name/Organization: City of Cle Elum
Contact Person: Matthew Lundh, Mayor
Phone: 509-304-4576
Email: mlundh@cleelum.gov
Mailing Address: 119 West First Street, Cle Elum, WA 98922
4
II.Project Overview
1.Project Description
Project Purpose
The proposed project is the construction of a community recreation center, thoughtfully designed
with community input, to serve residents and visitors of Upper Kittitas County for the next 50
years and beyond. For over two decades, community members have voiced a strong and
consistent desire for a year-round facility where people of all ages can safely gather, connect, and
participate in healthy, active lifestyles—particularly during the region’s long and often isolating
winters.
In response to this need, the Upper Kittitas County Community Recreation Center Alliance (UKC
CRCA), a 501(c)(3) nonprofit, was established in 2020 to lead the effort to make this long -
standing community vision a reality. Since then, a broad-based Project Committee—comprised
of leaders from the Hein Legacy Foundation, the City of Cle Elum, local school districts, small
businesses, civic groups, nonprofit organizations, and engaged residents—has worked
collaboratively to bring the project to full construction readiness.
Project History
A community recreation facility—particularly one that includes a swimming pool—has been a
long-standing priority for Upper Kittitas County residents. As part of the 2002 Development
5
Agreement between the City of Cle Elum and Suncadia’s predecessor, provisions were included
to support the creation of a community recreation center. Other community groups championed
efforts in 2007 and 2013, but those projects ultimately fell short. Despite those setbacks, the
need for a community recreation center—and strong public interest in it—has remained steady
and compelling.
In 2020, that vision began to take tangible shape when the UKC CRCA was formed. Since then,
with the participation of more than 1,000 residents and visitors, the project has achieved a series
of meaningful milestones:
• 2020 – The Upper Kittitas County Community Recreation Center Alliance (UKC CRCA), a
501(c)(3) nonprofit, was established to lead a renewed effort toward creating a shared
community recreation space.
• 2021 – Suncadia transferred 12.2 acres of land to the City of Cle Elum, along with $2
million in funding and a promissory note for an additional $2 million due in 2028.
• 2022 – A comprehensive Feasibility Study was completed.
• 2023 – The Schematic Design phase was finalized, and a building permit application was
submitted to the City of Cle Elum.
• 2025 – The project received its SEPA determination, and detailed design and construction
documents were completed. They are available upon request.
Throughout the design and planning process, the Project Committee has worked diligently to
identify the most effective governance and financing structures for both construction and long-
term operations. This has involved extensive collaboration with local and regional leaders,
including the Cle Elum mayor, the Kittitas County Board of Commissioners, staff from the City of
Ellensburg, and representatives from Legislative District 13. These efforts—grounded in
community input and inter-agency cooperation—are nearing final resolution and will ensure the
facility is built and operated in a way that reflects and serves the people of Upper Kittitas County.
Project Scope
The size and scope of the proposed facility have been carefully evaluated by the Project
Committee through extensive collaboration with expert consultants and meaningful public input.
The resulting design reflects a thoughtful balance of priorities:
1. addressing the most pressing needs of current residents and visitors,
2. accommodating anticipated population growth, and
3. ensuring financial sustainability for at least the next 30 years.
The planned recreation center will total 64,786 square feet and include the following key features:
6
• A natatorium featuring a six-lane lap and competition pool; a warmer, zero -entry
recreation pool with a small “lazy river” designed for young children and therapeutic use;
and a hot tub.
• Two full-size indoor basketball courts adaptable for pickleball, volleyball, and other
hardwood sports.
• An elevated indoor running track offering views of the pool, courts, and surrounding
natural landscape.
• A fitness area equipped with weights, cardio machines, and training space.
• Two multipurpose community rooms for meetings, gatherings, and events.
• Two flexible-use rooms intended for fitness classes and other programming.
• A welcoming central “living room” space at the main entrance, designed to
encourage community connection and social interaction.
• A child watch area where small children can be supervised while the parent or
guardian uses the facility
• An outdoor splash pad, currently not included in the construction cost estimate, may
be added as an alternate in the bidding process.
Floor plans are shown below. A comprehensive facility overview with numerous images can be
found here.
7
8
While additional outdoor amenities may be developed in future phases, all Lodging Tax funds
requested through this application will be used exclusively to support construction of the
indoor facility. Construction documents, prepared by ALSC Architects, are complete and
available for review upon request. The project is ready for bid as soon as construction financing is
secured.
Project Location
The facility will be built on 12.2 acres of land owned by the City of Cle Elum, specifically
dedicated for this project. The site is ideally located—adjacent to the Cle Elum-Roslyn School
District and directly across Bullfrog Road from Suncadia—making it easily accessible to residents
and visitors from all Upper Kittitas County communities.
Set within a beautifully forested area, the design thoughtfully preserves the site’s natural
character. The facility will be accessible by vehicle via Bullfrog Road and by foot or bicycle
through a network of existing and planned trails. These connections will enhance access for
students and residents, while also supporting the growing mountain biking community, which
increasingly views Upper Kittitas County as a premier destination. To accommodate and
encourage active transportation, bike barns are included in the project design.
Overview of Impact on Tourism
While the project is designed for the benefit of Kittitas County residents, the impact on tourism is
expected to be substantial. See next sections for rationale.
2. Tourism Benefit
Access to recreational amenities varies significantly among visitors, particularly those staying in
short-term rentals (STRs) located outside private developments like Suncadia. Many of these
STRs lack fitness or pool facilities, creating a clear demand fo r a public recreation center that is
accessible for a fee. Even guests within Suncadia often do not have access to private
amenities—or may seek alternatives due to capacity constraints and overcrowding. A centrally
located public facility would capture unmet demand and generate new revenue streams from
both use fees and facility rentals. Notably, Suncadia’s management supports the development of
this community resource, recognizing its value as a complementary offering to the area’s tourism
infrastructure.
Additional user groups—including campers, outdoor recreationists, and accompanying family
members—represent further market segments with limited access to indoor facilities. These
visitors often contribute to the local economy and would likely increase per-visitor spending
through paid facility access and participation in programs or events.
While the precise number of incremental visitors is difficult to project, the presence of an indoor
recreation facility would enhance the region’s competitive positioning as a year-round
9
destination. It could influence travel decisions, extend the average length of stay, and increase
off-season visitation—all of which contribute to broader tourism-driven economic growth.
The projected operating budget (Section III.3) includes non -resident revenue projections,
reflecting the expected contribution of visitor use to the facility’s financial sustainability and the
local economy.
3. Target Users
The Kittitas County Tourism Strategic Plan identifies several key visitor segments: (1) leisure
travelers, (2) event and festival attendees, (3) cultural and heritage tourists, (4) business and
university-related visitors, and (5) day-use visitors. Each of these segments represents a
distinct opportunity for engagement through a publicly accessible, year-round recreation
facility.
This project is particularly well-positioned to serve two high-impact segments:
1. Event-based tourism, especially sports tourism—including basketball tournaments,
swim meets, and other competitive athletic events that bring participants and their
families from across the region.
2. Leisure and business travelers, including STR guests, conference attendees, and
families visiting the area who seek recreational options during their stay.
Currently, Upper Kittitas County lacks sufficient indoor venues to host regional athletic events
at scale. For example, local basketball programs have noted that tournament capacity is
constrained by the limited availability of gymnasium space—restricting opportunities to host
events that attract weekend and holiday visitors from across the Pacific North. With the
addition of a modern recreation facility, the region could significantly expand both the size and
number of such events. Likewise, nearby school districts have expressed interest in offering
expanded aquatic programming, such as swimming lessons and the potential formation of a
swim team. These types of activities would not only serve local youth but also create
opportunities to host swim meets and related events, drawing visiting teams and families
from across the region.
Beyond sports, the recreation center will also accommodate a range of non-athletic event
uses, including private parties, weddings, and community functions. Its flexible
indoor/outdoor space creates the foundation for multi-purpose use that evolves over time. In
future phases, based on public input, enhancements such as a small outdoor amphitheater
may be added, further expanding the facility’s capacity to serve cultural and community
events.
10
This broad spectrum of target users ensures that the recreation center will be a year-round
asset—not only for residents, but for the full range of visitor types outlined in the county’s
tourism plan—supporting both economic growth and quality of life in Upper Kittitas County.
11
III. Budget and Funding
1. Project Budget Breakdown - The construction cost budget below was prepared by MACC
Estimating Group for our architects (ALSC Architects) in February 2024 and is adjusted to
reflect Q1 2025 costs. The details behind this summary are available here.
Foundations $ 549,607
Superstructure 5,634,759
Exterior Enclosure 3,569,910
Roofing 2,045,863
Interior Construction 1,134,503
Stairs 223,053
Interior Finishes 1,750,665
Conveying Systems 93,000
Plumbing 2,064,000
HVAC 3,580,068
Fire Protection 299,192
Electrical 3,285,000
Equipment 293,250
Furnishings 446,411
Special Construction 2,843,525
Building Construction Cost 27,812,806
Site Preparation 637,774
Site Improvements 2,856,892
Site Mechanical Utilities 637,797
Site Electrical Utilities 200,000
Sitework Cost 4,332,463
General Requirements (2.75%) 883,995
Subtotal of Estimated Construction Cost $33,029,264
Bonds and Insurance (1.25%) 412,866
WA B&O Tax (0.5%) 165,146
Overhead and Profit (2.75%) 908,305
Contractor Fees 1,486,317
Contingency (5%) 1,725,779
Cost index to Q1 2025 (3.91%) 1,349,559
Total Estimated Bid Amount $37,590,919
Soft Costs (30% of Construction Costs) 11,277,276
Total Cost $52,168,195
12
2. Funding Sources
Construction funding:
Upper Kittitas County voters will be asked to fund approximately 75–80% of the project’s
construction cost through bonds secured by property tax revenues. Based on an assessed
valuation of $7 billion across the upper county, the estimated impact is $0.39 per $1,000 of
assessed value. As the region continues to grow, this cost per thousand is expected to
decline with increasing total assessed value.
To complement the bond funding, the Project Committee is committed to raising at least
$10 million in non-bond funds through a combination of targeted public and private
sources. A $4 million grant from the Kittitas County Lodging Tax Fund would significantly
strengthen the project’s fundraising position—enhancing the likelihood of meeting or
exceeding the $10 million goal and demonstrating broad public support for the facility.
Recognizing that major donors will require clarity regarding ownership and long-term
governance, the Project Committee has prudently delayed launching a formal capital
campaign until those structures are finalized. The Upper Kittitas County Community
Recreation Center Alliance (UKC CRCA) will not be the facility’s owner or operator, but it
will continue to lead fundraising efforts once the governing entities responsible for
construction, operations, and public funding are in place.
Since 2021, the following funds have been raised:
Source Amount Purpose / Notes
Suncadia (2021) $2,000,000 Funded feasibility study, schematic and
detailed design
Suncadia/Bullfrog Flats
(Promissory Note) $2,000,000 (due 2028) Legally obligated contribution to City of
Cle Elum for the project
Hein Legacy Foundation $20,000 secured
+ $1–2M committed
Additional $1–2M contingent on bond +
sales tax approval
Kittitas County (2023) $133,000 Used to complete construction
documents
Suncadia Fund for Community
Enhancement (2023) $10,000 Applied to construction document
completion
City of Cle Elum (2022–2025) $168,000 Includes project management fees and
lodging tax funds
WA State Capital Budget (2025) $155,000 For signage and site work
Individual Donor $100,000 Held and used for reimbursable pre-
development activities
UKC CRCA has a comprehensive list of targeted public and private funding sources. The
group is confident in its ability to secure the targeted construction funding over time.
13
Operations funding:
As outlined in Section III.1, the facility’s operating expenses are projected to exceed
revenues by approximately $1 million during its first year. This level of subsidy is typical for
public recreation centers—particularly those that include aquatics—and is consistent with
facilities serving rural and suburban populations.
The primary strategy for closing this operational gap is the formation of a Public Facilities
District (PFD), which would collect a dedicated 0.2% sales tax to support ongoing
operations. The PFD model offers a scalable solution that aligns with projected regional
growth. It also has broad support among local and county government leaders, who
recognize its long-term potential to sustainably fund public facilities.
As Upper Kittitas County’s population and sales activity increase, the operating shortfall is
expected to diminish, with surplus revenue potentially used to accelerate bond repayment.
While the PFD is the preferred approach, the Project Committee remains open to
alternative solutions to ensure long-term operational sustainability.
14
3. Long-term Maintenance Plan
A comprehensive operating budget was developed in 2022 by Ballard-King & Associates, a
nationally recognized firm specializing in the planning and operations of aquatic and recreation
centers. The budget was created in collaboration with the Project Committee and reflects
conservative, experience-based assumptions. The summarized operating budget is below, and a
multi-tab spreadsheet with details and assumptions is available upon request.
Because it is common for public recreation facilities—particularly those with aquatics
components—to operate at a deficit, the summary begins with projected expenses. The ratio of
projected revenues to expenses is expressed as the recovery percentage, representing the share
of operating costs expected to be offset by user-generated revenue. The projected recovery rate
aligns with similar rural facilities and is expected to improve over time as population and usage
increase.
Annual Operating Expenses:
Salaries and Wages $1,526,319
Utilities 193,600
Capital replacement fund 55,000
Contract services 47,000
Insurance 37,000
Chemicals 35,000
Maintenance and repair materials 20,000
Janitorial, recreation, and office supplies 48,000
Advertising 20,000
Credit card fees (75% of fees x 3.5%) 26,536
Other 54,749
Total Annual Operating Expenses,
Including Capital Replacement Fund
$2,063,204
Annual Revenues:
Membership and admission fees 615,054
Aquatic rentals and facility rentals 77,000
Aquatic programs (e.g., swim lessons) 56,706
General fitness programs (e.g., exercise classes) 218,619
Other 43,500
Total Annual Revenues $1,010,879
Difference ($1,052,325)
Recovery 49%
15
IV. Project Timeline
Because of dependencies on many factors outside the project team’s unilateral control, the timeline
below is ambitious but achievable.
Milestone Start End
Finalize governance strategy In process July 2025
Form Public Facilities District (in coordination with County
Commissioners and city officials in Cle Elum, Roslyn, and Ellensburg) July 2025 October
2025
Conduct campaign to form a Metropolitan Parks District (MPD) in Upper
County (targeting November 2025 ballot) July 2025 November
2025
Launch fundraising campaign to secure approximately $10 million from
public and private sources July 2025 December
2025
Conduct campaign to pass:
– 0.2% county-wide sales tax to fund operations
– MPD bond measure to fund a portion of construction
October
2025
February
2026
Solicit construction bids and select contractor February
2026 April 2026
Construct the facility April 2026 March 2028
V. Feasibility and Risk Management
1. Feasibility
The project is highly economically feasible. The land has already been secured, and complete
construction documents are in hand, making the project truly "shovel-ready." Upper Kittitas
County’s substantial assessed property value provides a strong foundation for issuing bonds
backed by property tax revenues. In addition, a modest 0.2% sales tax increase, equitably
allocated between the upper and lower county, would be sufficient to support the operational
funding needs of this and other regional projects—ensuring long-term financial sustainability.
2. Risk Management
The most significant challenge facing the project is securing voter approval for the bond and levy
measures required to fund construction and ongoing operations. While similar efforts in 2007
and 2013 were unsuccessful, both failed by narrow margins. Since then, the demographics of
Upper Kittitas County have evolved, and public support for a community recreation facility has
grown markedly.
The Project Committee is composed of experienced, committed stakeholders who have worked
for over four years to move this project forward in close collaboration with community members,
local and state officials, and subject matter experts. That same level of diligence, transparency,
16
and outreach will be applied to ensure a successful public campaign and to bring this long-
awaited facility to life.
VI. Tourism Metrics and Success Measurement
1. Addressing the Kittitas County Tourism Strategic Plan
This project directly supports the goals outlined in the Kittitas County Tourism Strategic Plan,
particularly the first objective: “Managing Visitor Impact and Strengthening Infrastructure.” While
an indoor recreation facility is a long-standing priority for residents, it also offers an important
benefit to the tourism ecosystem by relieving pressure on popular outdoor assets—such as trails
and parks—through the creation of alternative, year-round recreational opportunities for visitors.
The project also supports the plan’s second strategic goal: “Enhancing Trail Connectivity.” Current
facility designs include connections to nearby trails, particularly those located north of the site.
Nicky Pasi, of Mountains to Sound Greenway and a member of the Project Committee, has played
a key role in identifying and shaping these planned connections. Looking ahead, the future
development of Bullfrog Flats offers a strong opportunity to collaborate with the developer on
expanding regional trail access. This improved connectivity would enhance visitor mobility,
promote sustainable recreation patterns, and strengthen the relationship between indoor and
outdoor experiences—helping to further distribute visitor activity across the Upper Kittitas County
area.
2. Metrics
Assuming continued emphasis on tourism-driven economic growth in Upper Kittitas County,
an indoor recreation facility is expected to be a strong attractor for visitors. The operating
model includes differentiated pricing, with higher user fees for non-residents, making it
straightforward to identify and track visitor usage through point-of-sale systems. These
systems will capture data on day-use admissions, memberships, and program participation,
offering reliable, real-time metrics on non-resident facility use.
Additional insights may be gathered through a voluntary guest registry, allowing visitors to
indicate their home city or ZIP code. This low-cost tool can provide supplemental data on
geographic reach, particularly in the early years of operation.
Facility rentals—such as those for tournaments, swim meets, and other events—will also be
tracked through booking systems, and event organizers (e.g., athletic clubs or school
districts) can be asked to report estimates on attendance and visitor origin. These events are
likely to contribute meaningfully to overnight stays and tourism revenue.
Importantly, many residents involved in the design process expressed concerns about
overuse by visitors. To ensure a balance between tourism promotion and resident
17
satisfaction , the facility will implement periodic surveys of both local users and visitors.
These surveys will gather both quantitative feedback and anecdotal insights, helping inform
operational decisions and marketing strategies.
Collected metrics will be summarized and reported on a regular basis to facility
management, local lodging tax committees, and other key stakeholders to evaluate the
facility’s tourism impact and guide future planning.
3. Promotion
During the construction phase, the Project Committee will collaborate with the Kittitas County
Chamber of Commerce, short-term rental owners, and other local partners to develop strategies
for integrating the facility into regional tourism and promotional materials. This early coordination
will help ensure the center is positioned as a key amenity for visitors upon opening.
In addition, the facility will maintain a dedicated website to provide residents and visitors with up -
to -date information on recreational offerings, hours of operation, pricing, and event schedules.
4. Reporting
Upper Kittitas County Community Recreation Center Alliance (UKC CRCA) will provide
administrative and financial support to the project through the construction phase and continue
its support indefinitely through the operations/maintenance phase. Fundraising efforts will be
ongoing. Grants typically come with reporting requirements, and we expect that a variety of
metrics and anecdotal outcomes in addition to those listed above will be tracked and reported to
various funders, including the Kittitas County Lodging Tax Committee.
VII. Applicant Certification
I certify that the information provided in this application is true and complete to the best of my
knowledge. I further certify that I understand the eligibility requirements and that this project
complies with the requirements of RCW 67.28.1816.
Signature: ___________________________
Name: Matthew Lundh
Title: Mayor, City of Cle Elum
Date: ___________________________