HomeMy WebLinkAboutKittitas County CEMP_Completed_Review_Letter (Final)April 10, 2025
Sheriff Clay Myers
Kittitas County Sheriff’s Office
307 W. Umptanum Road
Ellensburg, WA 98926
Re: Kittitas County Comprehensive Emergency Management Plan
Dear Sheriff Myers:
Thank you for submitting the Kittitas County Comprehensive Emergency Management Plan (CEMP)
for our review, as required under RCW 38.52.070. Congratulations on completing this significant
accomplishment.
The enclosed documents provide a compilation of recommendations for your next planning and
review cycle to meet the requirements of chapter 38.52 RCW and chapter 118-30 WAC. Addressing
the lawful requirements category will ensure your CEMP’s continued consistency with the State
CEMP and the incorporation of industry best practices. The Washington Emergency Management
Division (EMD) looks forward to receiving the next iteration of Kittitas County’s CEMP in five
years.
To better incorporate the use of core capabilities and make the CEMP a more operational document,
CEMP development in Washington has undergone significant changes. If you would like additional
information or assistance, please contact EMD’s Planning Section at emdcempreview@mil.wa.gov.
Sincerely,
Director
Enclosures (2)
EMD CEMP Evaluated Checklist – Kittitas County 2025
CEMP Review and Recommendations – Kittitas County 2025
EMD CEMP Evaluated Checklist - Kittitas County 2024.xlsx
Section Title Tier III - Required Tier II - Suggestions Tier I - Optional
Introductory Documentation 88%91%0%
Purpose, Situation, & Assumptions 100%100%100%
Concept of Operations 100%76%59%
Direction, Control, & Coordination 100%65%72%
Organization 100%100%100%
Responsibilities 100%72%75%
Communications 100%67%
Administration 100%100%
Finance 100%100%100%
Logistics 100%100%100%
Development & Maintenance 100%100%24%
Population Protection 100%75%
ESF 4 100%100%
ESF 5 65%79%
ESF 6 73%86%
ESF 8 82%92%
ESF 9 75%89%
ESF 10 83%90%
ESF 13 60%87%
ESF 15 67%90%
Resource Management 72%88%
ESF 7 78%85%
ESF 11 100%100%
Critical Infrastructure 100%79%
ESF 1 60%79%
ESF 2 100%96%
ESF 3 75%84%
ESF 12 71%93%
TIER TOTALS*96%73%77%
Rating:
4
4
4
4
4
4
5
5
4
4
3
4
4
4
5
5
3
4
4
4
4
4
5
4
5
5
Basic Plan
Annexes
COMPREHENSIVE EMERGENCY MANAGEMENT PLAN (CEMP)
Five Fundamental Plan Review Criteria:
Rating System:
1 = Missing All of the specified characteristics
2 = Minimally addresses the specified characteristics
3 = Addresses Some of the specified characteristics
4 = Addresses Most of the specified characteristics
5 = Addresses All of the specified characteristics
*Each Tier Total is the sum of all elements that have been addressed across all sections in the column and displayed in a percentage
Cells that are grayed out do not contain elements that are reviewed for that tier.
ADEQUACY
A plan is adequate if:
The scope and concept of planned operations identify and address critical tasks effectively;
The plan can accomplish the assigned mission while complying with guidance;
The plan's assumptions are valid, reasonable, and comply with guidance.
FEASIBILITY
A plan is feasible if:
The organization can accomplish the assigned mission and critical tasks by using available resources whithin the time contemplated by the plan;
The organization allocates available resources to tasks and tracks the resources by status;
Available resources include internal assets and those available through mutual aid or through existing state, regional, or Federal assistance agreements.
Specifically, the jurisdiction should complete a capability estimate that:
Identifies the current status of resources arrayed to support the plan;
Analyzes the required resources based on the courses of action in the plan;
Identifies the most supportable courses of action and ways to reduce the impact of resource deficiencies.
ACCEPTABILITY
A plan is acceptable if:
It meets the requirements driven by a threat or incident;
It meets decision maker and public cost and time limitations;
It is consistent with the law;
It can be justified in terms of the cost of resources;
Its scale is proportional to mission requirements.
COMPLIANCE The Plan should align with guidance and doctrine to the maximum extent possible because these provide a baseline that facilitates both planning and execution.
COMPLETENESS
A plan is complete if it:
Incorporates all tasks to be accomplished;
Includes all required capabilities;
Integrates the needs of the general population, children of all ages, individuals with disabilities and others with access and functional needs, immigrants,
individuals with limited English proficiency, and diverse racial and ethnic populations;
Provides a complete picture of the sequence and scope of the planned response operation;
Makes time estimates for achieving objectives;
Identifies success criteria and a desired end-state.
COMPLETE OVERVIEW
Washington Emergency 3/19/2025
Management Division Page 1
Comprehensive Emergency Management Plan (CEMP) Review &
Recommendations
Jurisdiction: Kittitas County (2024)
The plan provides well written, easy to understand and necessary information for the
administration of an emergency management program. The recommendations provided below
are separated into three tiers:
Tier III – Lawful Requirements; Tier II – State Suggestions; and Tier I – Optional
State consistency reviews will follow the recommendations identified in Tier III. Tier II
identifies the next logical step in the planning process and should be considered guidance to
assist with state-wide planning coordination; Tier II does not include any legal requirements,
but highly suggested recommendations to better prepare your jurisdiction. Tier I identifies
entirely optional, accreditation-related elements and remains dependent on individual
jurisdictions’ preparedness goals, capabilities and resources.
TIER III – Lawful Requirements
CEMP Location Recommendation to Meet Legal Obligations Reference
Basic Plan – Approval
Document
Ensure the approval document is signed by
either the Emergency Management Director
or the senior elected official. This is expected
and is a reminder to sign the official
document when it is ready to be
promulgated/approved.
Chapter 118-30, WA
CEMP, CPG 101
ESF 7 – Mutual Aid
Discuss the procedures to provide projected
or anticipated costs, as well as the
reimbursement process when mutual aid
agreements are activated. Also, consider
including as attachments any checklists and
forms for requesting and providing
assistance.
Title 38.56 RCW, WA
CEMP, CPG 101
ESF 7 – Mutual Aid
Discuss the procedures to provide projected
or anticipated costs, as well as the
reimbursement process when mutual aid
agreements are activated. Describe or briefly
highlight the process and procedures that are
followed to reimburse incident related
expenses.
The next step is to describe how those
expenses are paid for. Do departments pay
Title 38.56 RCW, WA
CEMP, CPG 101
Washington State Emergency 3/19/2025
Management Division Page 2
TIER III – Lawful Requirements
CEMP Location Recommendation to Meet Legal Obligations Reference
out of their own budgets? Who might pay for
a contractor who covers work done by
multiple departments? What if a department
does not have the money to pay for the
resources they need?
ESF 7 – Unsolicited
Donations
Consider addressing or developing a plan
which covers the management of unsolicited
donations and spontaneous volunteers.
Chapter 118-30
WAC, WA CEMP,
CPG 101
TIER II – State Suggestions
CEMP Location Recommendation to Meet Legal Obligations Reference
CEMP
Word Choice – The use of the term “special
populations” or “vulnerable populations” is
not advised. A more appropriate term that
fits your needs is Access and Functional
Needs, which includes the populations you
are intending to address. Consult the
National Preparedness Goal 3nd Edition,
Appendix A: Terms and Definition, Access and
Functional Needs. Consider reviewing
documents to update this word choice.
NIMS 2017
Basic Plan – Approval
Document
Consider discussing authorities and decision-
making policies in either your approval
document or the delegation of authority if
the senior or appointed officials were absent.
WA CEMP, CPG 101
Basic Plan – Concept
of Operations
There are many elements that can be
addressed in the Concept of Operations
section of the Basic Plan relating to three
elements, or Core Capabilities, which impact
all Mission Areas. The first is Planning, the
second is Public Information & Warning, and
the third is Operation Coordination. Your
plan did a good job of addressing these, there
were just a few missing.
The National
Planning
Frameworks, WA
CEMP
Basic Plan – Direction,
Control, &
Coordination
Part of the Comprehensive Emergency
Management Plan should include a
description of the activities taking place in
the other mission areas (i.e. Prevention,
Protection, Mitigation, Recovery). While
your Annexes show some of this planning
consideration, the Basic Plan is meant to
The National
Planning
Frameworks, WA
CEMP
Washington State Emergency 3/19/2025
Management Division Page 3
TIER II – State Suggestions
CEMP Location Recommendation to Meet Legal Obligations Reference
describe the relationships between these
mission areas/planning efforts/etc. The State
CEMP is currently moving in this direction
with its own Plan which is the reasoning
behind offering this recommendation and the
previous one as a suggestion for future
updates to your CEMP.
Basic Plan – Direction
Control &
Coordination –
Staging Areas
When discussing multi-jurisdictional
coordination, there is an opportunity to
discuss how your jurisdiction would
coordinate to establish logistical staging
areas and community points of Distribution
(CPODs).
National Response
Framework,
National Disaster
Recovery
Framework, WA
CEMP, CPG 101
Basic Plan –
COOP/COG
Consider adding a section to the Basic Pian to
address Continuity of Operations and
Continuity of Government (COG). There are
multiple elements within the Tiered Checklist
to guide you on the information that is
recommended to add to the Basic Plan. Also,
consider reaching out to the Continuity
Planner at WA EMD for more information.
National Planning
Frameworks,
Continuity Guidance
Circular, CPG 101
Basic Plan –
Responsibilities
There are many tasks and abilities that
Departments/Agencies (at all levels of
government), the private sector, community
organizations, and individuals should be
participating in and accomplishing based on
the guidance offered by the National
Planning Frameworks. The Responsibilities
section is an opportunity to not only address
what capabilities are, but what they should
be. This section should also be considered a
place to set expectations. For more
information on stakeholder responsibilities,
consult the CEMP Evaluation Checklist – Tier
II Suggestions tab.
Overall, this section was well-written, there
were just a few missing.
The National
Planning
Frameworks, WA
CEMP, CPG 101
Basic Plan – Terms
and Definitions /
Abbreviations
Consider moving those terms and definitions
which only apply to a specific function to a
Support Annex. The definitions section within
WA CEMP, CPG 101
Washington State Emergency 3/19/2025
Management Division Page 4
TIER II – State Suggestions
CEMP Location Recommendation to Meet Legal Obligations Reference
a support annex serves to house unique
terms or jargon. This will leave the Basic
Plan’s terms and definitions section free to
discuss more general concepts that are
appropriate to its intended audience. Also,
consider removing any terms, definitions, or
anacronyms that is not used in the Plan to
help reduce its length and sharpen its focus.
ALL ESFs –
Responsibilities
Support Agencies that do not fall within the
jurisdiction of the county should not be given
responsibilities. Rather, you should list how
you coordinate with them when they are
executing their responsibilities that are
detailed in their own plans. For example,
State Patrol should not have responsibilities
listed, rather what should be listed is how
you coordinate together to help accomplish
the mission.
WA CEMP, CPG 101
ESF 1 – Alternative
Transportation
Describe the alternative methods of
transportation that can be used during an
incident (e.g. using ferries, local school buses,
city/county buses, etc.).
The National
Planning
Frameworks, WA
CEMP, CPG 101
ESF 1 – Coordination
with ESF 11
Consider describing how ESF 11 may work
with ESF 1 to manage the transportation of
food supplies, livestock, or emergency
resources to affected areas. This
collaboration ensures that critical resources
reach their destinations efficiently and safely
during a disaster or emergency
The National
Planning
Frameworks, WA
CEMP, CPG 101
ESF 1 – Incident
Management
Building off the incident management
measures described for Roadways, Pipeline,
and Rail; consider describing what incident
management practices will be implemented
for those involving Aviation and Maritime.
Even if your jurisdiction has no capabilities to
perform either of these a discussion should
still occur concerning who manages those
specific incident types and how your
jurisdiction assists or coordinates (e.g.
provides traffic control in affected areas,
WA CEMP
Washington State Emergency 3/19/2025
Management Division Page 5
TIER II – State Suggestions
CEMP Location Recommendation to Meet Legal Obligations Reference
provides specific transportation resources,
etc.).
ESF 3 – Utility
Coordination
Discuss the coordination involved with ESF 12
in the identification, prioritization, and repair
work for utilities.
The National
Planning
Frameworks, WA
CEMP, CPG 101
ESF 5 – Senior Officials
Describe the process involved in providing
routine briefings to Senior Officials during an
incident.
WA CEMP, CPG 101
ESF 5 – Public
Information
Management
(Unplanned
Assistance)
Consider discussing the consideration for the
unplanned arrival of individuals and
volunteer groups as well as integration of
unplanned assistance from community
members or neighboring jurisdictions.
WA CEMP, CPG 101
ESF 5 –
Staff/Equipment
Requirement and EOC
Layout
Consider identifying the staff and equipment
requirements necessary for the EOC. This can
include training requirements for staff and
equipment (laptops, monitors,
communication devices, whiteboard, etc.)
that would be needed.
Provide a diagram of the primary and
alternate EOCs (e.g., locations, floor plans,
displays) and identify and describe the critical
communications equipment
available/needed (e.g., phone numbers, radio
frequencies, faxes).
WA CEMP, CPG 101
ESF 6 – Shelters
There were a few additional elements that
should be addressed when describing this
ESF. The first is the establishment of
reception centers at shelter locations (not to
be confused with disaster recovery centers)
and alternative accommodation for those
who are unable to attend congregate shelters
(ex. Pet friendly or Domestic Violence
victims.)
Also, consider discussing the process for
family reunification, registered offenders
with lawful restrictions, and other hazards
that may be posed by the incident.
National Response
Framework,
National Disaster
Recovery
Framework, WA
CEMP, CPG 101
Washington State Emergency 3/19/2025
Management Division Page 6
TIER II – State Suggestions
CEMP Location Recommendation to Meet Legal Obligations Reference
ESF 7 - Credentialing
Consider discussing how personnel who fulfill
an ICS position are credentialed to be
considered capable or qualified to meet the
roles and responsibilities.
Prevention
Framework,
Protection
Framework, WA
CEMP, CPG 101
ESF 8 – Managing
Disaster-related
Conditions
Discuss how ESF 8 provides distribution
systems for their services (i.e. Point of
Dispensing (POD)). Also discuss how human
waste disposal services are provided.
National Disaster
Recovery
Framework, WA
CEMP, CPG 101
ESF 9 – Concept of
Operations
Excellent work creating a concise and well
thought out SAR ESF. Consider discussing the
following topics to completely round it out:
• Methods for monitoring distress levels;
• Tracking locations of distressed
individuals.
WA CEMP, CPG 101
ESF 10 – Concept of
Operations
While a separate review is conducted for ESF
10/LEPC Plans by EMD’s LEPC Planning Team,
there are a few elements that are addressed
in FEMA guidance. Consider discussing the
implementation of treatment options.
Even if your jurisdiction does not participate
in the process (i.e. the Department of
Ecology takes care of the waste), ESF 10
should briefly describe/highlight who is
participating in these activities and if any
coordination is involved.
National Mitigation
Framework,
National Response
Framework,
National Disaster
Recovery
Framework, WA
CEMP, CPG 101
ESF 12 -Disruption,
Extended Outage,
Neighbors
Consider discussing what impacts a
significant disruption in energy supplies (gas,
electricity, natural gas, etc.) would cause. A
secondary consideration would then be to
discuss a plan to manage and endure those
extended energy outages. Lastly, consider
discussing how disruptions to energy supplies
or suppliers in neighboring geographical
areas affect your jurisdiction and others.
The National
Planning
Framework, WA
CEMP, CPG 101
ESF 13 – Public Safety
and Security
Discuss the process for determining public
safety and security resource support. Also,
discuss how a common operating picture will
be developed.
National Response
Framework,
National Disaster
Recovery
Washington State Emergency 3/19/2025
Management Division Page 7
TIER II – State Suggestions
CEMP Location Recommendation to Meet Legal Obligations Reference
Framework, WA
CEMP, CPG 101
ESF 14
ESF 14 has been superseded by the
development of the National Disaster
Recovery Framework and is being replaced in
the National Response Framework to
coordinate lifelines. While a Long-Term
Recovery annex is no longer necessary, you
may opt to keep it (consider renaming to ESF
21, or 22, etc. to maintain consistency with
guidance) or use it to begin building a
Recovery Plan to compliment your response
efforts (for more information talk to the EMD
Recovery Coordinator about the
implementation of the Washington
Restoration Framework).
NRF, NDRF, WA
CEMP
ESF 15 – Notices
The topics covered within ESF 15 encompass
aspects of nearly all of the activities of other
ESFs and is a difficult Support Annex to
develop. Considering this, your ESF 15 Annex
demonstrates a high-level of development
and forward thinking. There are only a few
considerations which can be addressed.
Discuss how information pertaining to the
potential impacts of secondary hazards is
relayed to the public. Discuss mechanisms
which will be in place for the family
reunification process. Discuss the
notifications provided for emergency
transportation information. Lastly, discuss
the possibility of providing announcements
for upcoming community meetings (i.e.
involving state officials, local authorities,
damage assessments, etc.).
National Response
Framework,
National Disaster
Recovery
Framework, WA
CEMP
TIER I – Optional
CEMP Location Recommendation to Meet Legal Obligations Reference
General
The biggest concern with accreditation
entities and requirements is detailed
explanations of process and procedures. It is
often not enough to simply address that you
EMAP
Washington State Emergency 3/19/2025
Management Division Page 8
TIER I – Optional
CEMP Location Recommendation to Meet Legal Obligations Reference
perform an activity, but rather explain each
step of the process involved to accomplish
such activities.
Basic Plan
Develop and/or reference a multi-year
strategic plan complete with goals,
objectives, milestones, and implementation
methods.
EMAP 3.1.1
Basic Plan – Concept
of Operations
Discuss some basic NIMS concepts (i.e.
modular, unified command process, span of
control, etc.)
EMAP 4.5.1
Basic Plan -
Communications
There are a lot of elements to try and provide
methods and processes regarding crisis
communication, public information, and
education.
EMAP 4.11.1 -
4.11.4
Basic Plan -
Development and
Maintenance
A training and exercise program contains
numerous components. Accreditation is
primarily concerned with the methods used
to train, exercise, and track all this data.
EMAP 4.9 - 4.10
Additional Considerations
CEMP Location Recommendation
ESF 6: Mass Care - ARC
While it is fairly common to rely on the support and
capabilities of the American Red Cross, your own capabilities
should not be discounted. Consider investing in planning
efforts focused on what the capabilities of the County and its
Cities are capable of in comparison of those of the ARC. If a
significant or widespread disaster were to occur, then the
capabilities and resources of the ARC would be severely
diminished and prove to be insufficient. Therefore, it is
advised that you work closely with them to develop your own
plans based on your capabilities which can be instituted in a
worst-case scenario. At the very least (as the former is no
small task), consider reviewing the ARC’s procedural manuals
so that you can describe how the ARC accomplishes certain
capabilities. For example, examine what methodology the
ARC uses in shelter site selection, qualification, and
operations. This can be incorporated into your ESF 6 annex in
the case that the ARC is not able to assist you immediately
following a disaster or emergency.