HomeMy WebLinkAboutChange Order Acceptance Letter_Change Order No4
Kittitas County Solid Waste
925 Industrial Way
Ellensburg, WA 98926
February 26, 2025
Belsaas and Smith Construction
103 East 4th Avenue, Suite 209
Ellensburg, WA 98926
Project: Lower Valley Transfer, Change Order No. 4
Mr. Nelson,
I am writing to formally acknowledge and award change order number 4 for Change Order Proposal
(COP) #21, to run 12 strand fiber from the demarcation point at the MRW building to the
Administration building, Compost office, Transfer Station, and Scale House.
We propose the following modifications to our contract dated September 3, 2024.
Base Bid and Additive A2 $18,441,939.80
Additive A1 $642,000.00
Change Order No. 2 <$11,754.08>
Change Order No. 3 <$28,041.41>
COP #21 $145,224.93
Subtotal $19,238,943.96
WSST $1,654,549.18
Total $20,893,493.14
Please consider this letter as our formal acceptance of the change order.
We look forward to successfully completing this project together with these agreed-upon
adjustments. Thank you,
_____________________________ ___________________________________
Bryan Nelson Laura Osiadacz
Secretary Chair, Board of County Commissioners
Belsaas and Smith Construction Kittitas County
103 E 4th Ave # 209 205 W 5th Ave #108
Ellensburg, WA 98926 Ellensburg WA 98926