HomeMy WebLinkAboutChange Order Acceptance Letter_Change Order No3
Kittitas County Solid Waste
925 Industrial Way
Ellensburg, WA 98926
February 25, 2025
Belsaas and Smith Construction
103 East 4th Avenue, Suite 209
Ellensburg, WA 98926
Project: Lower Valley Transfer, Change Order No. 3
Mr. Nelson,
I am writing to formally acknowledge and award change order number 3 for the following Change
Order Proposals (COP):
COP #05: Electrical vault downsizing.
COP #06: Blink charger upgrade.
COP #07: Feeder conduit size reduction.
COP #08: Credit for redundant switch gear.
COP #11: Additional siding and insulation at the transfer station tunnel and push wall.
COP #14: Upsizing the compost service hydrants and irrigation lines
COP #18: Scale model change.
COP #19: Mixer pump deletion.
We propose the following modifications to our contract dated September 3, 2024.
Base Bid and Additive A2 $18,441,939.80
Additive A1 $642,000.00
Change Order No. 2 <$11,754.08>
COP #05 <$50,066.00
COP #06 $35,400.42
COP #07 <$25,000.00>
COP #08 <$10,000.00>
COP #11 $21,172.26
COP #14 $3,249.13
COP #18 $4,517.78
COP #19 <$7,315.00>
Subtotal $19,044,144.31
WSST $1,637,796.41
Total $20,681,940.72
Please consider this letter as our formal acceptance of the change order.
We look forward to successfully completing this project together with these agreed-upon
adjustments. Thank you,
_______________________ ______________________________
Bryan Nelson Laura Osiadacz
Secretary Chair, Board of County Commissioners
Belsaas and Smith Construction Kittitas County
103 E 4th Ave # 209 205 W 5th Ave #108
Ellensburg, WA 98926 Ellensburg WA 98926