HomeMy WebLinkAboutlowervalleyTS_request for CA No. 3 _final
2405 140th Ave. NE, Suite 107, Bellevue, WA 98005 | 425-746-4600 | eFax 503-684-6948
Environmental Consultants & Contractors
September 30, 2024
Project No. 01222292.00
Patti Stacey, Director
Kittitas County Solid Waste/Facility Maintenance Director
925 Industrial Way
Ellensburg, WA 98926
Subject: Project - Kittitas County Lower Valley Transfer Station
Request for a Contract Amendment No. 3
Dear Patti:
SCS Engineers (SCS) is requesting a contract amendment to provide engineering services during
construction for the Lower Valley Transfer Station project in Ellensburg, WA. This amendment
request also includes additional design work, project management, and additional services during
the bidding phase as noted below.
1.0 CONSTRUCTION PHASE ENGINEERING SUPPORT SERVICES
SCS will provide Kittitas County (County) construction phase support services including reviewing
shop drawings, responding to Request For Information (RFI’s), preparing design changes, providing
geotechnical engineering support, participation during project meetings, specialty inspection
services, geotechnical engineering, asbuilts, and participation in a final project walkthrough.
1.1 Project Management
SCS will provide project management services including subconsultant coordination, preparation of
monthly invoices, and participation in monthly check-in calls with the County.
Assumptions
Project Management Services for a 15-month period.
2 hours per month for SCS PM and 2 hours per month for Lead Engineer
Fifteen monthly invoices and check-in calls (30 mins each).
1.2 Submittal Review/RFI Responses/Design Change Notices
SCS will perform review of contractor submittals. SCS will prepare responses utilizing Owner
provided software (Trimble Project Sight). The estimated number of submittals by discipline is shown
below:
Civil 56
Structural 10
Architectural 57
MEP 24
Total 147 Submittals
Kittitas County Lower Valley Transfer Station
September 30, 2024
Page 2
SCS will review and provide responses to an estimated 130 Request For Information (RFI) and
prepare an estimated 30 Design Change Notices.
Assumptions
147 Submittal Reviews (Estimated 2.5 hours per submittal)
Respond to 130 RFIs (Estimated 4 hours per RFI)
Develop 30 Design Change Notices (Estimated 14 hours per DCN)
1.3 Project Meetings and Specialty Inspections
One SCS staff will participate in 30 – 1-hour progress meetings remotely throughout the 15- month
project duration.
The SCS team will provide approximately 20 specialty inspections of project components throughout
the project duration. Each inspection will include 4–hours of onsite time and travel time from either
Seattle of Spokane.
Assumptions
Attendance of one SCS staff at 30 – 1-hour project meetings (remotely)
20 Specialty Inspections- 4-hours onsite
1.4 Geotechnical Engineering Support
SCS’s subconsultant will provide approximately 60 hours of engineering services providing the Owner
with support during construction on an as needed basis.
Assumptions
60 Hours of Geotechnical Engineering Support
1.5 As-Builts and Project Closeout
SCS will prepare as-built drawings utilizing contractor provided markups. Four (4) SCS team staff will
participate in a substantial completion walkthrough and will provide the Owner with a final punch list
of items to be corrected by the contractor.
The number of asbuilt drawings to be prepared by discipline:
Civil 34
Architectural 59
Structural 27
MEP 46
Total 166 Asbuilt Drawings
Assumptions
Preparation of 166 As-Built Drawings
Kittitas County Lower Valley Transfer Station
September 30, 2024
Page 3
Attendance of 4 SCS Team Staff on Final Substantial Completion Inspection
Each SCS staff (4 total) to be onsite for 12 hours for the final inspection
2.0 ADDITIONAL ENGINEERING SERVICES
2.1 Compost Pond Re-Design
SCS will redesign the compost area contact water ponds to account for high groundwater elevations.
The design will be based on the highest groundwater encountered during the recent irrigation
season. The Owner will provide recent groundwater depths. The design will be submitted to
Department of Ecology for review and approval and SCS will submit the revised drawings to the
contractor. Drawings C-5B, C-6, C-17, and C-29 will be revised and re-submitted.
Assumptions
Revise Drawings C-5B, C-6, C-17, and C-29.
One Submittal to Department of Ecology
One Submittal to Contractor
2.2 Additional Support During Bidding Phase
SCS will provide additional engineering support during the bidding phase including utilizing and
revising Owner requested AIA upfront documents, preparation of final contract documents, and
development of conformed set of contract documents and drawings. Documents revised include:
Standard Form of Agreement (AIA 101-2017) – 6 pages
General Conditions of the Contract (AIA 201-2017)- 38 pages
Instruction to Bidders (AIA 701 – 2017) – 8 pages
Supplementary Instruction to Bidders - 1 Page
Supplementary General Conditions of the Contract – 24 pages
Conformed Set of Upfront Documents – 200 pages
Conformed Set of Technical Specifications – 858 Pages
Conformed Set of Drawings – 168 Drawings
2.3 Owner Requested Services
SCS will provide additional engineering services as requested by the OWNER during the 15-month
project duration. Services may include responding to regulatory agency questions/comments,
additional construction administration support, and other requests by the Owner. The Owner will
provide written authorization to SCS for work performed under this task. Work will be invoiced on a
Time and Material basis in accordance with the standard unit rate sheet.
ADDITIONAL BUDGET
The estimated cost for the additional work described in this Amendment 3 is $438,470. The terms
and conditions for this added scope of work will remain the same as those listed in the executed
contract.
Kittitas County Lower Valley Transfer Station
September 30, 2024
Page 4
Table 1. Proposed Fees for Amendment 3
CLOSING
SCS appreciates the opportunity to assist you on this important project. We will continue to work
closely with you and your staff to ensure that responsive and efficient services are provided. We look
forward to working with you further on this project. Please do not hesitate to contact us if you have
any questions or comments.
Sincerely,
Thomas D. Parker, P.E., BCEE Michelle P. Leonard
Project Director Senior Vice President
SCS Engineers SCS Engineers
Task Task Description Estimated Cost Billing Type
1.1 Project Management $24,164 Time and Materials
1.2 Submittal Review/RFI Response/
Design Changes Notices $211,896
Time and Materials
1.3 Project Meetings and Specialty
Inspections $43,955
Time and Materials
1.4 Geotechnical Engineering Support $12,800 Time and Materials
1.5 Project Closeout and As-Builts $69,045 Time and Materials
2.1 Compost Pond Re-Design $18,200 Lump Sum
2.2 Additional Support During the
Bidding Phase $39,910 Lump Sum
2.3 Owner Requested Services $18,500 Time and Materials
Total $438,470