HomeMy WebLinkAboutStaff Report (6)K
KITTITAS COLINTY
DEPARTMENT OF PUBLIC WORKS
AGENDA STAFF REPORT
AGENDA DATE May 21,2024
ACTION REQUESTED: Request to Approve a Resolution initiating County Road
Project designated as CRP NO: 320-24, 2024 Vantage
Highway Paving.
BACKGROUND:In April, Kittitas County was informed that there may be a
surplus of Surface Transportation Block Grant (STBG)
funds available to Local Agencies that have shovel ready
projects able to obligate funding by mid-September of this
yeaL
Public Works has identified the repaving of Vantage
Highway from No. 81 Road (M.P. 6.56) to the Old Sunset
Highway (M.P. 11.17) as a project that meets the criteria of
this tunding.
To meet the requirements of the program the project needs
to be initiated as a county road project and needs to be added
tslthe Washington State Department of Transportation
(WSD OT) Statewide Transportation Improvement Pro gram.
Project design will be performed by Kittitas County Public
Works. This project will require a 13.5 percent match in local
funds for construction. The current estimated total cost ofthe
project is $2,950,000, with $398,250 being the Local match.
INTERACTION:Public Works
RECOMMENDATION:Approve a Resolution initiating County Road Project
designated as CRP NO: 320-24, 2024 Vantage Highway
Paving.
HANDLING:
ATTACHMENTS
Return one (1) original to Public Works
Resolution
Cameron Curtis, County EngineerLEAD STAFF':