KITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
AGENDA STAF'F'REPORT
May 7,2024
Request to Approve a Resolution to Award the Contract for the
Bowers Field East Taxilane Pavement Rehabilitation and Apron
Reconfiguration and Authorize the Public Works Director to
execute the same.
BACKGROUIID:
INTERACTION
RECOMMENDATION
HANDLING:
ATTACHMENTS:
On March 5,2024, the BOCC approved a Notice of Call for
Sealed Bids for the construction of the Bowers Field East
Taxilane Pavement Rehabilitation Project. Sealed bids were
opened publicly on March 28,2024, at Kittitas County Public
Works. There were three (3) responsive bids received. The
lowest responsive bid was from Central Paving, LLC in the
amount of $351,414.94.
The Federal Aviation Administration (FAA) reviewed bid
documents and responded on April 19,2024, with concurrence
to award.
Pavement rehabilitation of the east taxilane and apron area are
identified as a priority need in the Bowers Field Capital
Improvement Plan (CIP). The Bipartisan Infrastructure Law as
enacted in the Infrastructure Investment and Jobs Act authorized
additional allocation for airport projects. Funding for pavement
rehabilitation work for Bowers Field project FAA/AIP No. 3-53-
0026-022-2023 was awarded for 90 percent of construction with
a l0 percent local match. A grant application has been submitted
to the Washington State Department of Transportation Aviation
Division for funding to cover 5 percent of the required match.
The FAA has not yet released funds for the grant. This is
anticipated. The anticipated start of construction is June 2024.
Public Works.
Approve the Resolution to Award the Contract for the Bowers
Field Taxilane Pavement Rehabilitation and Apron
Reconfiguration Project and Authorizethe Public Works
Director to execute the same.
Return one (1) copy to Public Works.
Resolution with Bid Tab
Joshua Fredrickson
Public Works Director
LEAD STAFF: