HomeMy WebLinkAboutResolution_CRP No.320-24_VantageHighwayPavingKITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
AGENDA STAFF REPORT
AGENDA DATE: May 21, 2024
ACTION REQUESTED: Request to Approve a Resolution initiating County Road
Project designated as CRP NO: 320-24, 2024 Vantage
Highway Paving.
BACKGROUND: In April, Kittitas County was informed that there may be a
surplus of Surface Transportation Block Grant (STBG)
funds available to Local Agencies that have shovel ready
projects able to obligate funding by mid -September of this
year.
Public Works has identified the repaving of Vantage
Highway from No. 81 Road (M.P. 6.56) to the Old Sunset
Highway (M.P. 11.17) as a project that meets the criteria of
this funding.
To meet the requirements of the program the project needs
to be initiated as a county road project and needs to be added
to the Washington State Department of Transportation
(WSDOT) Statewide Transportation Improvement Program.
Project design will be performed by Kittitas County Public
Works. This project will require a 13.5 percent match in local
funds for construction. The current estimated total cost of the
project is $2,950,000, with $398,250 being the Local match.
INTERACTION: Public Works
RECOMMENDATION: Approve a Resolution initiating County Road Project
designated as CRP NO: 320-24, 2024 Vantage Highway
Paving.
HANDLING: Return one (1) original to Public Works
ATTACHMENTS: Resolution
LEAD STAFF: Cameron Curtis, County Engineer
RESOLUTION NO.
BEFORE THE BOARD OF COUNTY C
of initiating a county road project designated as:
CRP NO: 320-24 JOB NO: RC 2299
OF KITTITAS COUNTY, STATE OF WASHINGTON, in the matter
IT IS HEREBY RESOLVED that the 2024 Vantage Highway Paving be improved as follows:
The project will plane the existing asphalt surface on Vantage Highway MP 6.56 - MP 11.17 and replace the asphalt with
a new hot mixed asphalt wearing surface and install new roadway striping and markings. The project will also contemplate
necessary safety upgrades to existing infrastructure.
ARTERIAL x
ACCESS
This project is hereby declared to be a public necessity and the County Engineer is hereby ordered and authorized to report and
proceed thereon as by law provided. (RCW 36.75.050, 36.80.030, 36.80.070).
IT IS FURTHER RESOLVED that an appropriation from the officially adopted road fund budget and based on the County
Engineers estimate, is hereby made in the amounts and for the purposes shown:
EN
F-/
F-4
PURPOSE
AMOUNT
TOTALS
PRELIMINARY ENGINEERING
$ 200,000
CONSTRUCTION ENGINEERING
$ 250,000
RIGHT-OF-WAY ACQUISITION
$
SUB -TOTAL
$ 450,000
County Forces CONSTRUCTION
$
CONTRACT CONSTRUCTION
$ 2,500,000
SUB -TOTAL
$ 2,500,000
TOTAL PROJECT COST
$ 2,950,000
GRANT OR OTHER FUNDS
$ 2,551,750
Is
Grant Source: STBG A
TOTAL COUNTY ROAD FUND ALLOCATION
398,250
Cameron Curtis, P.E.
County Engineer
THIS PROJECT IS INCLUDED IN THE OFFICIALLY ADOPTED 2023 ANNUAL ROAD PROGRAM AS
ITEM NO.
THIS PROJECT IS HEREBY MADE A PART OF THE OFFICIALLY ADOPTED ANNUAL ROAD PROGRAM PROJECT 13
IN ACCORDANCE WITH RCW 36.81.130
IT IS FURTHER RESOLVED THAT:
THE CONSTRUCTION IS TO BE ACCOMPLISHED BY CONTRACT IN ACCORDANCE WITH RCW 36.77.020 ET.SEQ.
THE CONSTRUCTION IS TO BE ACCOMPLISHED BY COUNTY FORCES IN ACCORDANCE WITH RCW 36.77.065 AND
WAC 136-1B.
ADOPTED this 21 st day of May, 2024.
BOARD OF COUNTY COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
Attest:
Clerk of the Board
Cory Wright, Commissioner
Brett Wachsmith, Chair
Laura Osiadacz, Vice -Chair
g:\base\forms\eng\crp-frm 5/1512024