Loading...
HomeMy WebLinkAboutResolution_CRP No.320-24_VantageHighwayPavingKITTITAS COUNTY DEPARTMENT OF PUBLIC WORKS AGENDA STAFF REPORT AGENDA DATE: May 21, 2024 ACTION REQUESTED: Request to Approve a Resolution initiating County Road Project designated as CRP NO: 320-24, 2024 Vantage Highway Paving. BACKGROUND: In April, Kittitas County was informed that there may be a surplus of Surface Transportation Block Grant (STBG) funds available to Local Agencies that have shovel ready projects able to obligate funding by mid -September of this year. Public Works has identified the repaving of Vantage Highway from No. 81 Road (M.P. 6.56) to the Old Sunset Highway (M.P. 11.17) as a project that meets the criteria of this funding. To meet the requirements of the program the project needs to be initiated as a county road project and needs to be added to the Washington State Department of Transportation (WSDOT) Statewide Transportation Improvement Program. Project design will be performed by Kittitas County Public Works. This project will require a 13.5 percent match in local funds for construction. The current estimated total cost of the project is $2,950,000, with $398,250 being the Local match. INTERACTION: Public Works RECOMMENDATION: Approve a Resolution initiating County Road Project designated as CRP NO: 320-24, 2024 Vantage Highway Paving. HANDLING: Return one (1) original to Public Works ATTACHMENTS: Resolution LEAD STAFF: Cameron Curtis, County Engineer RESOLUTION NO. BEFORE THE BOARD OF COUNTY C of initiating a county road project designated as: CRP NO: 320-24 JOB NO: RC 2299 OF KITTITAS COUNTY, STATE OF WASHINGTON, in the matter IT IS HEREBY RESOLVED that the 2024 Vantage Highway Paving be improved as follows: The project will plane the existing asphalt surface on Vantage Highway MP 6.56 - MP 11.17 and replace the asphalt with a new hot mixed asphalt wearing surface and install new roadway striping and markings. The project will also contemplate necessary safety upgrades to existing infrastructure. ARTERIAL x ACCESS This project is hereby declared to be a public necessity and the County Engineer is hereby ordered and authorized to report and proceed thereon as by law provided. (RCW 36.75.050, 36.80.030, 36.80.070). IT IS FURTHER RESOLVED that an appropriation from the officially adopted road fund budget and based on the County Engineers estimate, is hereby made in the amounts and for the purposes shown: EN F-/ F-4 PURPOSE AMOUNT TOTALS PRELIMINARY ENGINEERING $ 200,000 CONSTRUCTION ENGINEERING $ 250,000 RIGHT-OF-WAY ACQUISITION $ SUB -TOTAL $ 450,000 County Forces CONSTRUCTION $ CONTRACT CONSTRUCTION $ 2,500,000 SUB -TOTAL $ 2,500,000 TOTAL PROJECT COST $ 2,950,000 GRANT OR OTHER FUNDS $ 2,551,750 Is Grant Source: STBG A TOTAL COUNTY ROAD FUND ALLOCATION 398,250 Cameron Curtis, P.E. County Engineer THIS PROJECT IS INCLUDED IN THE OFFICIALLY ADOPTED 2023 ANNUAL ROAD PROGRAM AS ITEM NO. THIS PROJECT IS HEREBY MADE A PART OF THE OFFICIALLY ADOPTED ANNUAL ROAD PROGRAM PROJECT 13 IN ACCORDANCE WITH RCW 36.81.130 IT IS FURTHER RESOLVED THAT: THE CONSTRUCTION IS TO BE ACCOMPLISHED BY CONTRACT IN ACCORDANCE WITH RCW 36.77.020 ET.SEQ. THE CONSTRUCTION IS TO BE ACCOMPLISHED BY COUNTY FORCES IN ACCORDANCE WITH RCW 36.77.065 AND WAC 136-1B. ADOPTED this 21 st day of May, 2024. BOARD OF COUNTY COMMISSIONERS KITTITAS COUNTY, WASHINGTON Attest: Clerk of the Board Cory Wright, Commissioner Brett Wachsmith, Chair Laura Osiadacz, Vice -Chair g:\base\forms\eng\crp-frm 5/1512024