HomeMy WebLinkAboutResolution_TO5_WSEKITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
AGENDA STAFF REPORT
AGENDA DATE: May 7, 2024
ACTION REQUESTED: Request to Approve a Resolution to Authorize the Chair's
Signature on Watershed Science and Engineering, Inc.
Task Order No. 5 - Ellensburg Urban Flooding Hydraulic
Analysis.
BACKGROUND: The City of Ellensburg was awarded Flood Control
Account Assistance Program (FCAAP) funding by the
Department of Ecology. This grant will fund a city -led
effort to improve flood risk information associated with
Whiskey and Mercer Creeks in the city and identify flood
mitigation actions. The City has asked the Flood Control
Zone District to provide matching contributions valued at
$100,000 in the form of District staff time and tasking our
on -call consultant with integration of the City's work with
County -led flood risk assessment. Task Order No. 5 -
Ellensburg Urban Flooding Hydraulic Analysis tasks our
on -call consultant with this work. The value of Task Order
No. 5 exceeds the contract authorization amount currently
provided to the Public Works Director.
At the April 8, 2024 Study Session, the Board of County
Commissioners provided staff with direction to proceed to
support the City's FCAAP project.
INTERACTION: Public Works
RECOMMENDATION: Approve a Resolution to Authorize the Chair's Signature
on Watershed Science and Engineering, Inc. Task Order
No. 5 - Ellensburg Urban Flooding Hydraulic Analysis.
HANDLING: Return one original to Public Works
ATTACHMENTS: Resolution; Task Order No. 5
LEAD STAFF: Arden Thomas
Public Works Water Resource Manager
BOARD OF COUNTY COMMISSI4
COUNTY OF KITTITAS
STATE OF WASHINGTON
RESOLUTION NO.2024-
AUTHORIZING CHAIR SIGNATURE ON WATERSHED SCIENCE AND ENGINEERING,
INC. TASK ORDER NO.5 — ELLENSBURG URBAN FLOODING HYDRAULIC ANALYSIS
WHEREAS: Kittitas County desires to participate in a City of Ellensburg project that will improve
information available about flood risk from Whiskey and Mercer Creeks in the city and
identify effective mitigation actions; and
WHEREAS: The Kittitas County Flood Control Zone District will participate in the City's project for
the purposes of coordinating this effort with District -led floodplain mapping and flood -
risk reduction projects; and
WHEREAS: The Department of Public Works procured on -call professional hydraulic and hydrologic
engineering services from Watershed Science and Engineering, Inc. consistent with state
law and county code in December 2022; and
WHEREAS: Watershed Science and Engineering, Inc. prepared a scope of work and fee proposal to
provide technical floodplain hydraulic analysis and to of coordinate this effort with
District -led floodplain mapping and flood -risk reduction projects; and
WHEREAS: The value of Task Order No. 5 exceeds the contract authorization amount currently
provided to the Public Works Director;
NOW THEREFORE, BE IT RESOLVED The Board of County Commissioners of Kittitas County,
Washington, in the best interest of the public, does hereby authorize Chair signature on
Watershed Science and Engineering, Inc. Task Order No. 5 - Ellensburg Urban Flooding
Hydraulic Analysis.
DATED this 7' day of May 2024, at Ellensburg, Washington.
Attest:
❑ Clerk of the Board- Julie Kjorsvik
❑ Deputy Clerk of the Board- Mandy Buchholz
BOARD OF COUNTY COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
Brett Wachsmith, Chairman
Laura Osiadacz, Vice -Chairman
Cory Wright, Commissioner
ova_ ro
�p
"�� n6' KITTZTAS COUNTY
DEPARTMENT OF PUBLIC WORKS
KITnITAS COIN V
Formal Task (
hr Document
Watershed Science and Engineering, Inc.
Task Order Number 5
Maximum Amount Payable $104,999 Completion Date 06/30/2025
The general provisions and clauses of the 2023 - 2025 Task Order Master Contract for
Hydraulic and Hydrology Professional Consulting Services shall be in full force and effect
for this Task Order.
Location of Project: Whiskey and Mercer Creeks
Project Title: Ellensburg Urban Flooding Hydraulic Analysis
Description of Work: See the attached Scope of Work.
Cost Breakdown: See the budget included in the attached Scope of Work.
Project Schedule: The project is scheduled to be completed by 06/30/2025.
Agency Signature:
Date:
Consultant Signature: Livl+il' l �^ Date: 5/01/2024
le-WWATERSHED
SCIENCE & ENGINEERING April 30, 2024
Scope of Work
Ellensburg Urban Flooding Hydraulic Analysis
Kittitas County, WA
Background
The City of Ellensburg (City) is conducting an in-depth analysis within the Ellensburg Urban Growth Area
(UGA) and city limits to support an updated stormwater model for the current floodplain map update
process led by Kittitas County, focused on urban flooding caused by Whiskey and Mercer Creeks. The
modeling will also support future flood map updates proposed for Wilson Creek, increase understanding
of flooding in the city, and identify mitigation actions. With this knowledge, the City will be more
prepared for flood events, and residents within the City and its UGA--especially those in areas with a
high probability of flooding during a 1%annual chance flood --will be better equipped to take additional
precautions or mitigate against the risk of flooding. The consultant team is led by Perteet with support
from Evergreen H2O and Watershed Science & Engineering (WSE). The following tasks will be completed
by WSE under a contract with Kittitas County Public Works (County) and are structured to be consistent
with tasks contracted between the City and Perteet.
Task 2. Data Collection and Modeling
The goal of Task 2 is to gather all information required to increase the City's and County's understanding
of flooding within the UGA, prepare the stormwater model, and increase the accuracy of the hydraulic
model and/or increase the City's level of certainty in the hydraulic model, which can be used to support
a Letter of Map Revision (LOMR).
Task 2.1. Core Planning Team and Project Management
This task is dedicated to the overall management of the project. WSE's work elements include:
• Attending up to 20 Core Planning Team (CPT) meetings
• Preparing monthly progress reports for the County
Assumptions:
• CPT meetings with be virtual
• WSE's staff engineer will attend all 20 meetings. WSE's senior engineer will attend up to 10 of
the meetings as needed.
• The project duration will be 14 months
Deliverables:
• Monthly progress reports
Task 2.2. Data Collection
This task will provide the data necessary to evaluate the stormwater system and flooding in the
Ellensburg UGA to support the development of current baseline conditions updates to the flood model,
development of the stormwater model, and define the projected climate change scenario for
precipitation and flooding that will be used in this project.
The consultant team will review existing data and determine what additional data must be collected to
inform the project and document current baseline conditions. Data to be collected may include
ie a► WATERSHED
SCIENCE 6 ENGINEERING
April 30, 2024
information about the City's stormwater system, roads, bridges, culverts, watercourse data, ground
elevations, changes in the terrain, records of flooding, and climate change predictions.
Perteet will prepare a City Conditions Memo that describes the current conditions in the City and the
data collection process, provides an inventory of data collected and its quality, and identifies the system
or capacity needs within Ellensburg to support future mitigation strategy development. The memo will
also identify recommendations for additional data collection and discuss any assumptions that were
made about the collected data or its use.
The following tasks will be completed by WSE:
• Review the collected data that pertains to surface water flooding.
• Participate in a one -day field investigation to support data collection.
• Provide input on surface water flooding issues for the City Conditions Memo.
Assumptions:
Two WSE staff will participate in a one -day field investigation to verify existing data and/or
collect additional data.
Deliverables:
• WSE contributions to the draft and final City Conditions Memo
Task 2.3. Floodplain Analysis
The consultant team and Tech Team will review the current draft flood maps and compare extents to
photos or accounts of past flooding events. Perteet will gather information about past flooding events to
develop a greater understanding of flood dynamics and what influences flow paths through the City.
Depending on the availability, completeness, and level of confidence of the flow paths and past flooding
data, Perteet may map past event flood extents in ISIS and prepare a flood history map. The consultant
team will identify where there have been changes to the built environment that may affect flood flows
since the most recent UDAR was collected in 2019 (e.g. new road cuts through the Cascades to Palouse
trail embankment, new curbs, or other changes the terrain). This may include meetings with City
maintenance staff to better understand the performance of the existing stormwater system or past
flooding. The results of the data collection, summary of flood dynamics, and effects of climate change
will be included in the Task 2.2 City Conditions Memo.
The following tasks will be completed by WSE:
Review background data and mapping and contribute to the review and comparison of past
flooding to the current flood model results.
Coordinate with FEMA to discuss methods of identifying flow paths in urban alluvial fans (e.g.
method used to map Wenatchee Number 2 Canyon) and when Zone X should be used for areas
with very shallow flooding. The consultant team will analyze how the selected climate change
scenario will affect the City.
Provide input on past flooding comparison to existing hydraulic model results for Task 2.2 City
Conditions Memo
Q 0, WATERSHED
SCIENCE & ENGINEERING
April 30, 2024
Assumptions:
• City and County staff and the CPT will support the collection of data, photos, and accounts of
flooding.
• Except for GIS flood history data, no new data will be created in this task.
• The climate change evaluation will be qualitative and descriptive and will not be modeled unless
it is determined necessary and sufficient budget remains, as directed by the City's and County's
project manager.
Deliverables:
• WSE contributions to the draft and final City Conditions Memo.
Task 2.4. Stormwater Model
WSE will not have any specific tasks related to the stormwater model
Task 2.5. Update Hydraulic Model
WSE will update and refine the existing HEC-RAS 2D hydraulic model of Whiskey and Mercer Creek
within the City of Ellensburg using data gathered in Tasks 2.2 and 2.3. The model will comply with the
FEMA guidelines and standards for flood risk analysis and mapping.
WSE will update the model to:
• Incorporate new topographic data and survey identified or collected In Task 2.2
• Refine model mesh to improve model resolution based on flood mapping analysis completed in
Task 2.3
• Incorporate significant stormwater inflow and/or outflow locations modeled in Task 2.4
WSE will then run the model for the 100-year flood event and one other flood event determined
through coordination with the Tech Team. Model results will be presented to the Tech Team in Task 2.1
to assess the level of accuracy, identify primary flow paths, and compare to the results of stormwater
modeling completed in Task 2.4. WSE will complete additional model refinements, if necessary, based
on stakeholder input.
WSE will create a topographic workmap of the resulting 100-year inundation mapping and develop a
brief technical memo to document the model updates.
Assumptions:
• Modeling will be completed by updating Whiskey -Mercer HEC-RAS 21) model that was most
recently updated in 2023.
Deliverables:
• Updated HEC-RAS model that complies with FEMA guidelines and specifications for flood risk
assessment and mapping.
• A topographic workmap showing draft 100-year inundation extents based on most current
FEMA methods as determined in Task 2.3.
0 Brief technical memo documenting model updates
o� WATERSHED
SCIENCE & ENGINEERING April 30, 2024
Task 3. Identify Mitigation Actions and Public Outreach
The goal of Task 3 is to identify priority mitigation actions that will provide the greatest reduction in
flood risk in the studied areas within the UGA and City while being feasible, resilient to changing
conditions, equitable, and cost-effective. The actions will be identified using the most current and
accurate information, in a collaborative environment with shared goals. Action development and
alternatives analysis will be consistent with CFHMP guidance.
Task 3 will result in a list of prioritized mitigation actions that will be added to the County's and/or City's
CFHMP or HMP. After the mitigation actions are identified, the City and County will have a unified
mitigation strategy and can work towards implementation of the actions for reduced flood risk
associated with Whiskey Creek, Mercer Creek, and Wilson Creek.
Task 3 also includes a robust public outreach process to involve the public in the project and create
awareness of potential flooding scenarios, highest risk areas, and notify affected property owners of
proposed updates to the Flood Insurance Rate Maps.
Task 3.1. Technical Stakeholder Team
Perteet will support the City's formation of a Technical Stakeholder Team (Tech Team) that will be active
throughout the project to help guide the City in decision -making processes, floodplain analysis,
identification of potential mitigation actions, public outreach efforts, and data collection efforts. The
Tech Team will include, but not be limited to, staff from the City, County, and County Flood Control Zone
District, consultant team members, and other agencies or entities that have an interest in flood
reduction (e.g. CWU, WDFW, Kittitas Conservation District, Ecology, etc.), or provide support to
vulnerable populations within the City. At the onset of the Tech Team meetings, the Tech Team will
identify goals which can be used to measure success of this project and the identification of mitigation
actions.
The following tasks will be completed by WSE:
• WSE's senior and staff engineer will participate in Tech Team meetings.
Assumptions:
• The Tech Team will meet as needed and no more than monthly throughout the duration of the
project (14 months).
• WSE staff will attend Tech Team meetings virtually.
Task 3.2. Public Outreach
Perteet will lead the development of accessible, engaging, and educational outreach events using
various methods, including websites, story map, and in -person events. Public outreach will include the
whole community, but some outreach will be targeted towards residents of properties that are
identified as being in the high -risk flood zone and are affected by the proposed map change in the City
and UGA. The outreach will focus on flood education and notification of potential future map changes
and will meet the Federal Emergency Management Agency (FEMA) requirements for LOMR outreach.
Perteet will support the City in developing materials for and hosting joint open house events in which
the public can learn more about the project and discuss their specific concerns.
o� WATERSHED
SCIENCE & ENGINEERING April 30, 2024
After the flood model is refined (Task 2.5), the City will host an outreach event for the whole community
and targeted towards properties that are identified as being in the high -risk flood zone. The outreach
will focus on flood education and notification of potential future map changes and will meet the FEMA
requirements for LOMR outreach. During the analysis of mitigation alternatives (Task 3.4), the City will
host public outreach to present the results of the alternatives analysis and solicit the public's opinion on
their preferred alternatives.
The following tasks will be completed by WSE:
• Attend and/or provide information to support meeting material preparation for the open house
meetings and the public outreach meeting.
Assumptions:
• Two WSE staff will participate in up to three in -person meetings to support public outreach.
Deliverables:
• Information to support public outreach materials.
Task 3.3. Floodplain-Stormwater Model Results Analysis
After tasks 2.4 and 2.5 are completed, the consultant team, with support from the CPT and Tech Team,
will evaluate the model results to support the development of mitigation actions. The evaluation will
include comparing the effective floodplain, previous flood model results, and updated flood model
results; identifying areas where the stormwater system helps reduce flooding or adds to the flooding,
such as moving stormwater from one area of the City to another; and to discuss where potential
interactions occur between the flood waters and the stormwater system. The results of the evaluation
will support the determination of mitigation measures in Task 3.4 and will be summarized in a
floodplain-stormwater analysis technical memo. This task also provides an opportunity for the City to
more thoroughly review the floodplain model to increase the City's level of certainty in the model
results and the identified floodplain boundaries.
WSE will:
• Provide floodplain information and input to support an evaluation comparing the existing flood
model results to potential updates incorporating the stormwater model and
stormwater/floodway interactions.
• Provide floodplain information for the technical memo.
Assumptions:
• Any identified interactions, effects, or other results of the analysis will be assessed further in
Task 3.4.
Deliverables:
• WSE contributions to draft and final floodplain-stormwater analysis technical memo
Task 3.4. Mitigation Actions
The consultant team and Tech Team will evaluate the results of the updated hydraulic model, the new
stormwater model, and the technical memo prepared in Task 3.3 to identify potential mitigation
�e_WWATERSHED
SCIENCE & ENGINEERING April 30, 2024
measures. The evaluation will focus on identifying actions that will provide the greatest benefit to the
public and are feasible, cost-effective, resilient, and equitable, and meet the goals of this project.
Certain actions that modify flooding and/or stormwater will be modeled to determine the effectiveness.
Actions that also benefit the habitat within the City and UGA will be identified as multiple benefit
actions. Actions may include, but not be limited to: acquisitions; identifying and protecting primary flow
paths or flood storage areas; improvements to the stormwater system, such as regional stormwater
facilities; outreach and education; regulation updates; staff training; conservation/flood easements;
emergency response measures; and/or home elevations or property acquisitions. Some actions may also
identify future planning needs, such as additional alternatives analyses or feasibility studies.
After the action alternatives are identified, the actions will undergo an alternatives analysis pursuant to
Comprehensive Flood Hazard Management Plan (CFHMP) guidance. The actions will be prioritized,
grouped into strategies, and a funding and partnership strategy will be developed. The actions and
strategies will be added to the Kittitas County Hazard Mitigation Plan (HMP) which also serves at the
County's CFHMP. All in -water actions will undergo an alternatives analysis and evaluation of effects in
compliance with WAC 173-145-040. The actions and strategies will also include all information necessary
to meet FEMA HMP requirements, per the Local Mitigation Planning Policy Guide, effective April 19,
2023 (FP 206-21-0002).
All mitigation actions considered will be described in a memo. The Mitigation Actions Memo will address
all actions and describe the alternatives analysis process and why certain actions were or were not
prioritized. A list of prioritized mitigation actions will be prepared in a format that facilitates adding the
actions into the HMP.
The following tasks will be completed by WSE:
• Update the hydraulic model to reflect up to 4 separate mitigation action scenarios, and run each
scenario model to simulate the 100-year flood.
• Produce figures comparing 100-year water surface extents and elevations for mitigated
conditions to existing conditions flooding.
• Provide text and figures to describe modeling updates and results for the Mitigation Actions
Memo.
Assumptions:
• The Tech Team will identify which actions should be modeled to determine effectiveness.
• Each alternative actions will represent single project or combinations of minor project that can
reasonably be easily incorporated into the hydraulic model in 4 hours of staff engineer time.
• Information necessary to update the model, such as grading surfaces or adjusted flow inputs
due to stormwater changes, will be provided to WSE by the Tech Team for incorporation into
the model.
• If budget remains after simulating 4 mitigation alternatives, the City and/or County may request
more modeling.
Deliverables:
0 WSE contributions to the Mitigation Actions Memo.
t-WWATERSHED
SCIENCE & ENGINEERING
Task 4. Administrative Reserve
April 30, 2024
An administrative reserve is included to allow WSE to address additional questions or issues that may
arise during project review or coordination with the County, City, CPT, and/or Tech Team. This may
include additional analysis, modeling, meetings, presentations, documentation, and/or discussion.
Administrative reserve funds will only be used if authorized by the County.
Cost
See attached spreadsheet.
40AL WATERSHED
_. SCIENCE & ENGINEERING
506 2nd Ave, Suite 2700
Seattle, WA 98104
Tel. (206)521-3000
Estimate of Professional Services
Prepared for:
Kittitas County Public Works
Project:
Ellensburg Urban Flooding Hydraulic Analysis
Date:
April 30, 2024
Prepared By:
Chris Frei
TASK DESCRIPTION
Hours
Totals
Principal
Sr. Eng.1
Sr. Geom.
Eng.
Jr. Eng
Atlmin
.e.
2 loans Collection and Modeling
2.1 Core Planning Team and Prow Management
1
20
16
8
$ 7998
2.2 Data Collection
8
40
16
$ 9.766
2.3 Floodiplain Analysis
8
40
$ 7,954
2.4 Stormwatsr Model
IS
2.5 Update Hraulic Model
24
160
24
IS 32,710
Subtotal
1
60
0
256
40
8
$ 58,429
3 Identify Mitigation Actions and Public Outreach
3.1 Technical Stakeholder Team
16
16
$ 6'�
3.2 Public Outreach
24
40
$ 11,599
3.3 Floodplain-Stormwater Model Results Analysis
16
24
S 7,324
3.4 Mitigation Actions
16
80
IS15908
Subtotal
0
72
0
160
0
0
S 40,929
4 lAdininistratfive Reserve
5000
.... ..®..............,......e..............o...............L....................................
Total Hours and Direct Labor Cost(DL) 1.0 132.0 0.0 416.0 40.0 8.0
Labor Rate($/hr, July 2023 WSDOT OH 157.22%,30%profit on DL) 1 $241.65 1 $227.84 $185.04 $163.28 $113.23 $93.35
TOTAL LABOR COST $242 $30,075 $0 $63,764 54,529 $747 $ 104,357
Direct Expense Detail
Units Rate Cost
Mileage 980 $0.655 $ 642
Total $ 642
Cost Summary
Total Labor
Total Dire
Direct Expenses
$
$
Total $
D4,357
642
642
104,999