HomeMy WebLinkAboutChange order_Kittitas_additional RTUCOP Coversheet
SCOPE OF WORK
Client Name
Project Number
COP Number
Project Title
Date
Construction
Additional 10T RTU, labor, installation 53,667.00$
crane pick, road closure flagging, permits
Commissioing 7,500.00$
TAB 1,100.00$
Site Supervision 4,900.00$
Sub Total 67,167.00$
Design - 14%9,403.00$
Construction Admin - 12%8,060.00$
M&V 4,029.00$
Overhead - 10%6,716.70$
Profit - 8%5,373.36$
Bond - 1.3%873.17$
Subtotal 101,622.23$
Sales Tax 8.40%8,536.27$
Construction Total 110,158.50$
Total Cost of Change 110,158.50$
Contract Time
Acknowledgement of Total Cost of Change Date
Client
McKinstry
Clarifications and Exclusions: Thermostat controls within 100'
Addition of a 4th RTU to replace existing and end of life RTU - Includes new 10T RTU, crane pick,
road closure, mechanical and electrical installation. Commissioning, TAB, site supervision.
Kittitas County
206119-004
3/10/2024
1
Kittitas County Courthouse HVAC
upgrade
Use contingency funds Use additional owner funds Construction Savings
No Change Increase Decrease OF _____ Calendar Days