STATEMENT OF WORK
Between
Kittitas County
205 W 5th Avenue, Suite 105
Ellensburg, WA
98926
USA
And Cayenta, A Division of
N. Harris Computer Corporation
8333 Eastlake Drive, Suite 101
Burnaby, British Columbia
V5A 4W2
Canada
For
Cayenta V9.2 Upgrade
+
Oracle to SQL Server Conversion
+
HCM & Connect Implementation
+
Analytics & Operational Models
Contents
Executive Summary & Overview ................................................................................................................... 1
Customer Profile ........................................................................................................................................... 2
Project Start Pre-Requisites .......................................................................................................................... 4
Project Scope – Products & Services ............................................................................................................. 5
General ...................................................................................................................................................... 5
Version 9.2 Upgrade ................................................................................................................................. 6
Oracle to SQL Server Conversion .............................................................................................................. 6
Connect Web Products Implementation .................................................................................................. 6
New Product Implementation .................................................................................................................. 7
Health Check (FMS & HCM) ...................................................................................................................... 8
Deliverables Summary .................................................................................................................................. 9
Deliverables Detail ...................................................................................................................................... 11
Methodology & Schedule ........................................................................................................................... 28
Methodology ........................................................................................................................................... 28
Project Management .......................................................................................................................... 28
Environment Setup ............................................................................................................................. 29
Configuration ...................................................................................................................................... 29
New Feature Overview & Train-the-Tester Training........................................................................... 29
Testing ................................................................................................................................................. 29
Training ............................................................................................................................................... 29
Go Live ................................................................................................................................................. 30
Post Go-Live and Transition Support .................................................................................................. 30
Schedule .................................................................................................................................................. 30
Project Environments.................................................................................................................................. 30
Payment Milestones ................................................................................................................................... 31
Overall Terms & Termination...................................................................................................................... 34
Terms and Conditions ......................................................................................................................... 34
Termination ......................................................................................................................................... 35
Appendix A: Incident Priority Definitions ................................................................................................... 36
Appendix B: Change Control Process .......................................................................................................... 37
The purpose of this Statement of Work is to set forth in detail the Software and Services deliverables to
be provided by HARRIS, the milestones, schedule and acceptance criteria for such deliverables, the
process for changes in scope and the respective responsibilities of HARRIS and CLIENT in connection
with this Statement of Work. HARRIS will be the Prime Contractor for all application software and
Services being provided under the Contract with CLIENT.
This Statement of Work shall be governed by the terms and conditions of the Software License,
Implementation and Support Agreement, dated _______________ between N. Harris Computer
Corporation and Kittitas County.
IN WITNESS WHEREOF, a duly authorized representative of each party has executed this Statement of
Work on the Effective Date:
Kittitas County
CAYENTA, a division of N. Harris
Computer Corporation
Name:
Name:
(Signature) (Signature)
Name:
Name:
(Print) (Print)
Title: Title:
Date:
Date:
1
Cayenta V9 Statement of Work
Executive Summary & Overview
Kittitas County (CLIENT) is embarking on an upgrade of Cayenta software to version 9.2 (the
latest release available) as well as implementing a number of new products including several
web-based Connect products, Operational Models and Analytics Frameworks. Under the
direction of the CLIENT Project Owner, the CLIENT Project Manager will drive and oversee the
project in coordination with the HARRIS Project Manager.
CLIENT has requested to engage Cayenta (HARRIS) for value-added services related to the upgrade
outlined in Deliverables. These services are not included in the Software and Maintenance Fees.
During the project, if CLIENT needs to make any changes to the Upgrade Environment, the changes need
to be approved by the HARRIS project team. Changes to the configuration or interfaces that are not
advised by the HARRIS project team also need to be fully documented in CayStone.
The ongoing operation for the Solution will be the responsibility of the CLIENT following the project
Go-live date with the support of HARRIS. The CLIENT will transition to HARRIS Support after
completion of the Transition period as outlined in the Deliverables below.
HARRIS and CLIENT agree to schedule and begin the project within 90 days of signature.
2
Cayenta V9 Statement of Work
Customer Profile
3
Cayenta V9 Statement of Work
4
Cayenta V9 Statement of Work
Project Start Pre-Requisites
HARRIS and CLIENT agree that the following pre-requisites are satisfied in order to begin work on this
project. Any pre-requisites that are the responsibility of CLIENT will be considered out of scope of this
project and any services required of HARRIS for CLIENT-owned pre-requisites will be addressed through
the Change Control process outlined in this document.
Pre-Requisite Responsible Party
Cayenta software is at a minimum version of V7.9 CLIENT
Hardware infrastructure required for the software environments
specified in this document are ready for HARRIS to perform
installation prior to the start date of this project.
CLIENT
Provide monitors with full HD (1920x1080) for CLIENT users of
the Cayenta Software.
CLIENT
CLIENT will have resources assigned to work on the project as
per the schedule defined in this document. This is inclusive of all
project work including test execution, workshop & meeting
participation as well as any other activities prescribed
CLIENT
5
Cayenta V9 Statement of Work
Project Scope – Products & Services
This project will include the following components
General
This is a project involving multiple threads of work. However, there are tasks and activities that will be
performed by both HARRIS and CLIENT that are applicable to many if not all threads of work. Those key
activities are outlined below. Key responsibilities are also outlined on a deliverable-by-deliverable basis
in the Deliverables section of this document.
Key HARRIS Activities:
• Prepare a project schedule that outlines all project activities for both HARRIS and CLIENT
• Conduct a project kickoff meeting (remote) to provide a project overview to all stakeholders
• Provision a CayStone project complete with core V9.2 test cases
• Deliver train-the-tester training on new V9.2 features and modules in scope of this project
• Provide testing support and incident remediation services as described in the Deliverables
section of this document
• Conduct weekly incident review meetings (during testing)
• Conduct weekly project management meetings to review progress, risks, and issues
• Conduct monthly Executive Steering Committee (ESC) meetings (shared responsibility with
CLIENT project manager)
• Prepare a go-live cutover checklist that details all the tasks needed to successfully complete a
go-live cutover
• Rehearse the go-live by conducting a mock go-live cutover, using the go-live cutover checklist
• Schedule and execute the go-live cutover (outside of business hours)
• Provide post go-live support to CLIENT as noted in the Deliverables section of this document
Key CLIENT Activities:
• Provision required hardware & infrastructure for HARRIS to install and configure all products in
scope of this project
• Participate in the development of the project schedule, identifying any key dates that need to
be considered (ex. Regulatory deadline, vacation/blackout periods, year-end, etc.)
• Participate in HARRIS-led overview & training sessions
• Provide input and clarifications as required to support the configuration of the solution
• Participate in weekly incident review meetings & project management meetings
• Contribute to Executive Steering Committee presentations
• Lead, manage and monitor all testing activities, ensuring that testing is successfully completed
per the dates in the project schedule
• Ensure that all logged incidents have sufficient detail for HARRIS to properly triage and
remediate the incidents
• Re-test corrected incidents in a timely manner
• Develop custom test cases that are not included in the V9.2 core test cases provided by HARRIS
• Contribute to the go-live cutover checklist and identifying CLIENT-specific tasks that may not be
in the standard HARRIS cutover checklist
6
Cayenta V9 Statement of Work
• Own and execute all go-live cutover checklist tasks (both for mock go-live and actual go-live)
• Prepare for and deliver all end user training
Version 9.2 Upgrade
HARRIS will work with CLIENT to set up the new V9.2 solution. V9.2 offers a variety of new features and
functionality.
Key HARRIS Activities:
• Install the V9.2 solution
o New environment will utilize SQL Server as part of the Oracle to SQL Server migration
• Configure the V9.2 solution for CLIENT testing
• Provide overview training on new features of the V9.2 solution
• Upgrade CLIENT Cognos installation (will be done as part of Cognos for SQL installation)
• Provide three data refreshes (which also include Oracle to SQL conversions on each refresh)
including one for testing, one for mock go live and one for go live
Oracle to SQL Server Conversion
HARRIS will migrate the solution from the current Oracle database platform to SQL Server as part of this
project.
Key HARRIS Activities:
• Install the two staging environments (one for Oracle and one for SQL Server) in addition to the
V92 PROD and V92 TEST environments (as outlined in the Environments section of this
document)
• Develop conversion scripts to migrate from Oracle to SQL Server
• Execute three (3) conversions (to double as data refreshes for V9.2)
1. Testing conversion
2. Mock Go Live conversion
3. Go Live conversion
• Provide testing support and incident remediation services as described in the Deliverables
• HARRIS support for custom database objects (views, tables, stored procedures, functions, etc.) is
not included in the scope of this project
• HARRIS support for custom-developed (i.e. non-core) Cayenta objects such as reports, interfaces
or portal stats is not included in the scope of this project
Connect Web Products Implementation
HARRIS will deliver the following web-based Connect products:
• Connect Finance
• Connect Employee
• Connect Manager
• Connect Time Entry
7
Cayenta V9 Statement of Work
Key HARRIS Activities:
• Install and configure each Connect web product
• Provide a solution overview to CLIENT testers
• Deliver training for CLIENT testers
• Provide testing support and incident remediation services as described in the Deliverables
New Product Implementation
HARRIS will deploy several new products in the scope of this project. HARRIS will take a similar approach
for each product to ensure a successful delivery. New modules to be rolled out as part of this project will
include:
• Human Capital Management (HCM)
• Connect Suite
o Connect Finance
o Connect Employee
o Connect Manager
o Connect Time Entry
• Grants Management
• Miscellaneous AR & Payments Processing (for FMS)
• Cayenta Analytics for FMS
• Cayenta Analytics for HCM
• Operational Models for FMS
• Operational Models for HCM
Key HARRIS Activities:
• Overview session(s) to confirm configuration requirements
• Install the modules
• Configure the solution
• Provide a solution overview
• Deliver training for CLIENT testers
• Provide testing support and incident remediation services as described in the Deliverables
8
Cayenta V9 Statement of Work
Health Check (FMS & HCM)
After the go-live, HARRIS and CLIENT will schedule a series of workshops with CLIENT core team
members and subject matter experts to examine core business processes with the intention of
identifying opportunities for improvement and how the Cayenta solution can contribute to these areas
of improvement.
Key HARRIS Activities:
• Lead the Health Check workshops (onsite)
• Document findings from the workshops
• Prepare a document outlining targeted improvements that can be made via process and/or
configuration changes
Key CLIENT Activities
• Ensure all required stakeholders attend the onsite sessions
• Manage the logistics of the onsite meetings
• Contribute to discussions during the Health Check workshops
9
Cayenta V9 Statement of Work
Deliverables Summary
Below is a summary list of the Services deliverables for the project. The Deliverables section itemizes
each deliverable in detail regarding specific scope, responsibilities for HARRIS and CLIENT as well as
acceptance criteria.
Component
Group
Deliverable
#
Deliverable Name Cost
Consulting
Services
1.01 Project Management Services - Month 1 $17,600.00
1.02 Project Management Services - Month 2 $17,600.00
1.03 Project Management Services - Month 3 $17,600.00
1.04 Project Management Services - Month 4 $17,600.00
1.05 Project Management Services - Month 5 $17,600.00
1.06 Project Management Services - Month 6 $17,600.00
1.07 Project Management Services - Month 7 $17,600.00
1.08 Project Management Services - Month 8 $17,600.00
1.09 Testing Support - Month 1 $31,900.00
1.10 Testing Support - Month 2 $31,900.00
1.11 Testing Support - Month 3 $31,900.00
1.12 Testing Support - Month 4 $31,900.00
1.13 Testing Support - Month 5 $31,900.00
1.14 Testing Support - Month 6 $31,900.00
1.15 Mock Go Live $8,800.00
1.16 Go Live Services $8,800.00
1.17 Support Transition & Project Close $27,720.00
Consulting Services Total $377,520.00
Technical
Services
2.01 CAYPROD92 Environment Build $8,800.00
2.02 CAYTEST92 Environment Build $8,800.00
2.03 Install Cognos for MS SQL $3,300.00
2.04 Connect Web Products Installation $6,600.00
2.05 New Test and Production Cayenta Software
Manager installation
$4,400.00
2.06 Data Conversion 1 $33,000.00
2.07 Data Conversion 2 (Mock Go Live) $33,000.00
2.08 Data Conversion 3 (Go Live) $33,000.00
Technical Services Total $130,900.00
Product
Services
3.01 V9.2 Overview Training & Core Portals/Stats
Training
$1,760.00
3.02 CayStone Test Cases Setup $1,760.00
10
Cayenta V9 Statement of Work
3.03 FMS Scripting Assistance $1,760.00
3.04 HCM Module Delivered for Testing $35,200.00
3.05 Time-Based Employee Master Delivery for
Testing
$26,400.00
3.06 CONNECT Finance Delivery for Testing $22,000.00
3.07 CONNECT Time Entry Delivery for Testing $22,000.00
3.08 CONNECT Employee Delivery for Testing $22,000.00
3.09 CONNECT Manager Delivery for Testing $22,000.00
3.10 Implement New Equipment Module $5,280.00
3.11 Grants Module Delivered for Testing $33,000.00
3.12 Misc. AR Module Delivered for Testing $33,000.00
3.13 FMS Health Check $13,200.00
3.14 WMS Health Check $13,200.00
Product Services Total $252,560.00
BI Services 4.01 Custom portal stats and interfaces testing
support (T&M)
$2,640.00
4.02 FMS Operational Model Delivered for Testing $17,600.00
4.03 HCM Operational Model Delivered for
Testing
$17,600.00
4.04 FMS Analytics Module Delivered for Testing $17,600.00
4.05 HCM Analytics Module Delivered for Testing $17,600.00
BI Services Total $73,040.00
Project Total $834,020.00
11
Cayenta V9 Statement of Work
Deliverables Detail
Below is a detailed listing of all deliverables in scope of this project. With each deliverable are specific
responsibilities to be performed by HARRIS and CLIENT respectively as part of completion of this
deliverable. Acceptance criteria for each deliverable specifies the criteria by which CLIENT will accept
the deliverable upon completion by HARRIS. Upon satisfying the acceptance criteria for the deliverable
will make the deliverable eligible to be billed as defined in the Payment Milestones section of this
document.
Deliverable ID 1.01
Deliverable
Type
Fixed Price
Deliverable
Name
Project Management Services - Month 1
Deliverable
Description
HARRIS will provide a Project Manager to manage the planned activities for the project in order to
deliver the scope as defined in this document. Working with the CLIENT Project Manager, the HARRIS
Project Manager will provide project management services as outlined in the Harris Responsibilities
section of this deliverable.
HARRIS
Responsibilities
• Develop the project schedule
• Co-facilitate the project kickoff meeting with CLIENT Project Manager
• Prepare weekly status reports
• Facilitate weekly status meetings
• Co-facilitate monthly Executive Steering Committee meetings with CLIENT Project Manager
• Provide management and direction to HARRIS project team members
CLIENT
Responsibilities
• Provide input & feedback as required to weekly status reports
• Provide input & feedback as required to Executive Steering Committee presentation
• Co-facilitate monthly Executive Steering Committee meeting
• Co-facilitate project kickoff meeting
• Provide management and direction to CLIENT team members
• Attend weekly status meetings
Deliverable
Acceptance
Criteria
End of Month 1 of the project
Deliverable ID 1.02
Deliverable
Type
Fixed Price
Deliverable
Name
Project Management Services - Month 2
Deliverable
Description
HARRIS will provide a Project Manager to manage the planned activities for the project in order to
deliver the scope as defined in this document. Working with the CLIENT Project Manager, the HARRIS
Project Manager will provide project management services as outlined in the Harris Responsibilities
section of this deliverable.
HARRIS
Responsibilities
• Prepare weekly status reports
• Facilitate weekly status meetings
• Co-facilitate monthly Executive Steering Committee meetings with CLIENT Project Manager
• Provide management and direction to HARRIS project team members
12
Cayenta V9 Statement of Work
CLIENT
Responsibilities
• Provide input & feedback as required to weekly status reports
• Provide input & feedback as required to Executive Steering Committee presentation
• Co-facilitate monthly Executive Steering Committee meeting
• Provide management and direction to CLIENT team members
• Attend weekly status meetings
Deliverable
Acceptance
Criteria
End of Month 2 of the project
Deliverable ID 1.03
Deliverable
Type
Fixed Price
Deliverable
Name
Project Management Services - Month 3
Deliverable
Description
HARRIS will provide a Project Manager to manage the planned activities for the project in order to
deliver the scope as defined in this document. Working with the CLIENT Project Manager, the HARRIS
Project Manager will provide project management services as outlined in the Harris Responsibilities
section of this deliverable.
HARRIS
Responsibilities
• Prepare weekly status reports
• Facilitate weekly status meetings
• Co-facilitate monthly Executive Steering Committee meetings with CLIENT Project Manager
• Provide management and direction to HARRIS project team members
CLIENT
Responsibilities
• Provide input & feedback as required to weekly status reports
• Provide input & feedback as required to Executive Steering Committee presentation
• Co-facilitate monthly Executive Steering Committee meeting
• Provide management and direction to CLIENT team members
• Attend weekly status meetings
Deliverable
Acceptance
Criteria
End of Month 3 of the project
Deliverable ID 1.04
Deliverable
Type
Fixed Price
Deliverable
Name
Project Management Services - Month 4
Deliverable
Description
HARRIS will provide a Project Manager to manage the planned activities for the project in order to
deliver the scope as defined in this document. Working with the CLIENT Project Manager, the HARRIS
Project Manager will provide project management services as outlined in the Harris Responsibilities
section of this deliverable.
HARRIS
Responsibilities
• Prepare weekly status reports
• Facilitate weekly status meetings
• Co-facilitate monthly Executive Steering Committee meetings with CLIENT Project Manager
• Provide management and direction to HARRIS project team members
CLIENT
Responsibilities
• Provide input & feedback as required to weekly status reports
• Provide input & feedback as required to Executive Steering Committee presentation
• Co-facilitate monthly Executive Steering Committee meeting
• Provide management and direction to CLIENT team members
• Attend weekly status meetings
13
Cayenta V9 Statement of Work
Deliverable
Acceptance
Criteria
End of Month 4 of the project
Deliverable ID 1.05
Deliverable
Type
Fixed Price
Deliverable
Name
Project Management Services - Month 5
Deliverable
Description
HARRIS will provide a Project Manager to manage the planned activities for the project in order to
deliver the scope as defined in this document. Working with the CLIENT Project Manager, the HARRIS
Project Manager will provide project management services as outlined in the Harris Responsibilities
section of this deliverable.
HARRIS
Responsibilities
• Prepare weekly status reports
• Facilitate weekly status meetings
• Co-facilitate monthly Executive Steering Committee meetings with CLIENT Project Manager
• Provide management and direction to HARRIS project team members
CLIENT
Responsibilities
• Provide input & feedback as required to weekly status reports
• Provide input & feedback as required to Executive Steering Committee presentation
• Co-facilitate monthly Executive Steering Committee meeting
• Provide management and direction to CLIENT team members
• Attend weekly status meetings
Deliverable
Acceptance
Criteria
End of Month 5 of the project
Deliverable ID 1.06
Deliverable
Type
Fixed Price
Deliverable
Name
Project Management Services - Month 6
Deliverable
Description
HARRIS will provide a Project Manager to manage the planned activities for the project in order to
deliver the scope as defined in this document. Working with the CLIENT Project Manager, the HARRIS
Project Manager will provide project management services as outlined in the Harris Responsibilities
section of this deliverable.
HARRIS
Responsibilities
• Prepare weekly status reports
• Facilitate weekly status meetings
• Co-facilitate monthly Executive Steering Committee meetings with CLIENT Project Manager
• Provide management and direction to HARRIS project team members
CLIENT
Responsibilities
• Provide input & feedback as required to weekly status reports
• Provide input & feedback as required to Executive Steering Committee presentation
• Co-facilitate monthly Executive Steering Committee meeting
• Provide management and direction to CLIENT team members
• Attend weekly status meetings
Deliverable
Acceptance
Criteria
End of Month 6 of the project
Deliverable ID 1.07
Deliverable
Type
Fixed Price
14
Cayenta V9 Statement of Work
Deliverable
Name
Project Management Services - Month 7
Deliverable
Description
HARRIS will provide a Project Manager to manage the planned activities for the project in order to
deliver the scope as defined in this document. Working with the CLIENT Project Manager, the HARRIS
Project Manager will provide project management services as outlined in the Harris Responsibilities
section of this deliverable.
HARRIS
Responsibilities
• Prepare weekly status reports
• Facilitate weekly status meetings
• Co-facilitate monthly Executive Steering Committee meetings with CLIENT Project Manager
• Provide management and direction to HARRIS project team members
CLIENT
Responsibilities
• Provide input & feedback as required to weekly status reports
• Provide input & feedback as required to Executive Steering Committee presentation
• Co-facilitate monthly Executive Steering Committee meeting
• Provide management and direction to CLIENT team members
• Attend weekly status meetings
Deliverable
Acceptance
Criteria
End of Month 7 of the project
Deliverable ID 1.08
Deliverable
Type
Fixed Price
Deliverable
Name
Project Management Services - Month 8
Deliverable
Description
HARRIS will provide a Project Manager to manage the planned activities for the project in order to
deliver the scope as defined in this document. Working with the CLIENT Project Manager, the HARRIS
Project Manager will provide project management services as outlined in the Harris Responsibilities
section of this deliverable.
HARRIS
Responsibilities
• Prepare weekly status reports
• Facilitate weekly status meetings
• Co-facilitate monthly Executive Steering Committee meetings with CLIENT Project Manager
• Provide management and direction to HARRIS project team members
CLIENT
Responsibilities
• Provide input & feedback as required to weekly status reports
• Provide input & feedback as required to Executive Steering Committee presentation
• Co-facilitate monthly Executive Steering Committee meeting
• Provide management and direction to CLIENT team members
• Attend weekly status meetings
Deliverable
Acceptance
Criteria
End of Month 8 of the project
Deliverable ID 1.09
Deliverable
Type
Fixed Price
Deliverable
Name
Testing Support - Month 1
Deliverable
Description
HARRIS will provide testing support services to CLIENT during test execution by CLIENT
HARRIS
Responsibilities
• Incident remediation, prioritizing work based on marked priority in the incident according to criteria
defined in this document
• Providing clarifications and guidance on new feature testing
15
Cayenta V9 Statement of Work
CLIENT
Responsibilities
• Execute testing per test sets as defined in CayStone
• Log incidents as issues arise with testing, ensuring that appropriate screenshots, verbiage and
reproduction steps are documented in the CayStone incidents
• Conduct validation testing on remediated incidents in a timely manner
Deliverable
Acceptance
Criteria
First month of CLIENT testing is complete
Deliverable ID 1.10
Deliverable
Type
Fixed Price
Deliverable
Name
Testing Support - Month 2
Deliverable
Description
HARRIS will provide testing support services to CLIENT during test execution by CLIENT
HARRIS
Responsibilities
• Incident remediation, prioritizing work based on marked priority in the incident according to criteria
defined in this document
• Providing clarifications and guidance on new feature testing
CLIENT
Responsibilities
• Execute testing per test sets as defined in CayStone
• Log incidents as issues arise with testing, ensuring that appropriate screenshots, verbiage and
reproduction steps are documented in the CayStone incidents
• Conduct validation testing on remediated incidents in a timely manner
Deliverable
Acceptance
Criteria
Second month of CLIENT testing is complete
Deliverable ID 1.11
Deliverable
Type
Fixed Price
Deliverable
Name
Testing Support - Month 3
Deliverable
Description
HARRIS will provide testing support services to CLIENT during test execution by CLIENT
HARRIS
Responsibilities
• Incident remediation, prioritizing work based on marked priority in the incident according to criteria
defined in this document
• Providing clarifications and guidance on new feature testing
CLIENT
Responsibilities
• Execute testing per test sets as defined in CayStone
• Log incidents as issues arise with testing, ensuring that appropriate screenshots, verbiage and
reproduction steps are documented in the CayStone incidents
• Conduct validation testing on remediated incidents in a timely manner
Deliverable
Acceptance
Criteria
Third month of CLIENT testing is complete
Deliverable ID 1.12
Deliverable
Type
Fixed Price
Deliverable
Name
Testing Support - Month 4
Deliverable
Description
HARRIS will provide testing support services to CLIENT during test execution by CLIENT
16
Cayenta V9 Statement of Work
HARRIS
Responsibilities
• Incident remediation, prioritizing work based on marked priority in the incident according to criteria
defined in this document
• Providing clarifications and guidance on new feature testing
CLIENT
Responsibilities
• Execute testing per test sets as defined in CayStone
• Log incidents as issues arise with testing, ensuring that appropriate screenshots, verbiage and
reproduction steps are documented in the CayStone incidents
• Conduct validation testing on remediated incidents in a timely manner
Deliverable
Acceptance
Criteria
Fourth month of CLIENT testing is complete
Deliverable ID 1.13
Deliverable
Type
Fixed Price
Deliverable
Name
Testing Support - Month 5
Deliverable
Description
HARRIS will provide testing support services to CLIENT during test execution by CLIENT
HARRIS
Responsibilities
• Incident remediation, prioritizing work based on marked priority in the incident according to criteria
defined in this document
• Providing clarifications and guidance on new feature testing
CLIENT
Responsibilities
• Execute testing per test sets as defined in CayStone
• Log incidents as issues arise with testing, ensuring that appropriate screenshots, verbiage and
reproduction steps are documented in the CayStone incidents
• Conduct validation testing on remediated incidents in a timely manner
Deliverable
Acceptance
Criteria
Fifth month of CLIENT testing is complete
Deliverable ID 1.14
Deliverable
Type
Fixed Price
Deliverable
Name
Testing Support - Month 6
Deliverable
Description
HARRIS will provide testing support services to CLIENT during test execution by CLIENT
HARRIS
Responsibilities
• Incident remediation, prioritizing work based on marked priority in the incident according to criteria
defined in this document
• Providing clarifications and guidance on new feature testing
CLIENT
Responsibilities
• Execute testing per test sets as defined in CayStone
• Log incidents as issues arise with testing, ensuring that appropriate screenshots, verbiage and
reproduction steps are documented in the CayStone incidents
• Conduct validation testing on remediated incidents in a timely manner
Deliverable
Acceptance
Criteria
Sixth month of CLIENT testing is complete
Deliverable ID 1.15
Deliverable
Type
Fixed Price
17
Cayenta V9 Statement of Work
Deliverable
Name
Mock Go Live
Deliverable
Description
HARRIS will conduct a mock-go live prior to the go-live, ensuring the cutover checklist is sufficient to
ensure a successful cutover at go-live.
HARRIS
Responsibilities
• Prepare mock go-live checklist
• Review mock go-live checklist with CLIENT
• Execute HARRIS-assigned tasks per the checklist
• Make any necessary changes to checklist based on mock go-live execution
CLIENT
Responsibilities
• Review mock go-live checklist and add any additional tasks for CLIENT
• Execute CLIENT-assigned tasks per the checklist
• Provide feedback on mock go-live execution for the purpose of checklist revision
Deliverable
Acceptance
Criteria
Completion of mock go-live activities per the mock go-live checklist
Deliverable ID 1.16
Deliverable
Type
Fixed Price
Deliverable
Name
Go Live Services
Deliverable
Description
HARRIS and CLIENT will execute the assigned tasks, per the go-live cutover checklist, over the planned
one (1) day go-live time frame.
HARRIS
Responsibilities
• Execute HARRIS-assigned tasks per the go-live cutover checklist
• HARRIS will be available on go-live weekend to perform HARRIS-assigned tasks per the go-live cutover
checklist.
CLIENT
Responsibilities
• Execute CLIENT-assigned tasks per the go-live cutover checklist
• CLIENT will be available on go-live weekend to perform CLIENT-assigned tasks per the go-live cutover
checklist.
Deliverable
Acceptance
Criteria
Completion of go-live activities per the go-live checklist and CLIENT can access and use the CAYPROD90
environment for production purposes
Deliverable ID 1.17
Deliverable
Type
Fixed Price
Deliverable
Name
Support Transition & Project Close
Deliverable
Description
HARRIS transitions CLIENT from assigned Project Team back to Cayenta Support and formally closes the
project. The period of post go-live support provided by the Project Team will be four (4) weeks from the
date of go-live.
Acceptance of this deliverable signifies the acceptance of the project and official project close.
HARRIS
Responsibilities
• Facilitate handover meeting from Project Team to Cayenta Support
• Deliver Support Transition document to CLIENT and Cayenta Support
• Remediate P1 & P2 priority incidents
CLIENT
Responsibilities
• Attend handover meeting
• Validate & close P1 & P2 priority incidents
Deliverable
Acceptance
Criteria
HARRIS provides Support Transition document
All P1 & P2 incidents logged for the project have been remediated
Deliverable ID 2.01
18
Cayenta V9 Statement of Work
Deliverable
Type
Fixed Price
Deliverable
Name
CAYPROD92 Environment Build
Deliverable
Description
HARRIS will set up the new CAYPROD90 environment which will be the primary environment used for
testing during the project as well as the new production system after go-live.
HARRIS
Responsibilities
• Install the Cayenta software
• Conduct an environment audit, including technical and functional validation of the environment
CLIENT
Responsibilities
• Provide required hardware & infrastructure necessary to host the CAYPROD90 environment as well as
any other required infrastructure items
• Provide access to the infrastructure to HARRIS Technical Resources
Deliverable
Acceptance
Criteria
CLIENT project team is granted access to and can log into the CAYPROD90 environment.
Deliverable ID 2.02
Deliverable
Type
Fixed Price
Deliverable
Name
CAYTEST92 Environment Build
Deliverable
Description
HARRIS will set up the new CAYTEST90 environment which will be the new test system after go-live.
HARRIS
Responsibilities
• Install the Cayenta software
• Conduct an environment audit, including technical and functional validation of the environment
CLIENT
Responsibilities
• Provide required hardware & infrastructure necessary to host the CAYTEST90 environment as well as
any other required infrastructure items
• Provide access to the infrastructure to HARRIS Technical Resources
Deliverable
Acceptance
Criteria
CLIENT project team is granted access to and can log into the CAYTEST90 environment.
Deliverable ID 2.03
Deliverable
Type
Fixed Price
Deliverable
Name
Install Cognos for MS SQL
Deliverable
Description
HARRIS will install one Cognos 11 environment
HARRIS
Responsibilities
• Perform a new installation of the Cognos 11 environment
• Configure Test and Production Cayenta application to use the new Cognos 11 environment
CLIENT
Responsibilities
• Provide the required server infrastructure for HARRIS to perform the install
• Ensure HARRIS technical personnel have proper access to server infrastructure to perform the
installation
Deliverable
Acceptance
Criteria
CLIENT project team are provided access to the Cognos 11 environment
Deliverable ID 2.04
Deliverable
Type
Fixed Price
19
Cayenta V9 Statement of Work
Deliverable
Name
Connect Web Products Installation
Deliverable
Description
HARRIs will install the included Connect products
HARRIS
Responsibilities
• Install Connect Finance
• Install Connect Employee
• Install Connect Time Entry
• Install Connect Manager
CLIENT
Responsibilities
• Provide the required server infrastructure for HARRIS to perform the install
• Ensure HARRIS technical personnel have proper access to server infrastructure to perform the
installation
Deliverable
Acceptance
Criteria
Connect Finance is installed
Connect Employee is installed
Connect Time Entry is installed
Connect Manager is installed
Deliverable ID 2.05
Deliverable
Type
Fixed Price
Deliverable
Name
New Test and Production Cayenta Software Manager installation
Deliverable
Description
HARRIS will deploy two new instances of the Cayenta Software Manager tool (PROD and TEST) to
support the project
HARRIS
Responsibilities
• Install the Cayenta Software Manager tool
CLIENT
Responsibilities
• Provide required hardware & infrastructure necessary for the installation
• Provide access to the infrastructure to HARRIS Technical Resources
Deliverable
Acceptance
Criteria
HARRIS installs the Cayenta Software Manager tool
Deliverable ID 2.06
Deliverable
Type
Fixed Price
Deliverable
Name
Data Conversion 1
Deliverable
Description
HARRIS will develop the conversion scripts required to migrate the CLIENT data from Oracle to the new
SQL Server environment. This will include the removal of data related to the electrical services
contained in the Oracle environment as well as converting data required for the HCM application as
defined in this document. HARRIS will also migrate the custom database objects (views, functions,
stored procedures) as indicated in this document. HARRIS will deliver the first completed conversion to
set the stage for the testing phase of the project.
HARRIS
Responsibilities
• Develop & test conversion scripts
• Migrate custom objects (views, functions, stored procedures)
• Convert required HCM data
• Execute and deliver Conversion 1 for CLIENT testing
• Produce audit reports & record counts
• Remediate conversion issues as required
20
Cayenta V9 Statement of Work
CLIENT
Responsibilities
• Provide input & clarification as required related to conversion & data mapping
• Participate in workshops/meetings as required
• Test & confirm data has been converted successfully/log detailed incidents for any issues
• Provide a copy of the production Oracle database to be used for the conversion
• Ensure critical processes are done before copy of Oracle (ex. Month end)
• Remediate source data issues
Deliverable
Acceptance
Criteria
Conversion 1 is delivered with balanced audit reports and CLIENT signs off on submitted audit reports.
Deliverable ID 2.07
Deliverable
Type
Fixed Price
Deliverable
Name
Data Conversion 2 (Mock Go Live)
Deliverable
Description
HARRIS to perform the second data conversion from Oracle to SQL Server.
HARRIS
Responsibilities
• Develop & test conversion scripts
• Migrate custom objects (views, functions, stored procedures)
• Convert required HCM data
• Execute and deliver Conversion 1 for CLIENT testing
• Produce audit reports & record counts
• Remediate conversion issues as required
CLIENT
Responsibilities
• Test & confirm data has been converted successfully/log detailed incidents for any issues
• Provide a copy of the production Oracle database to be used for the conversion
• Ensure critical processes are done before copy of Oracle (ex. Month end)
• Remediate source data issues
Deliverable
Acceptance
Criteria
Conversion 2 is delivered with balanced audit reports and CLIENT signs off on submitted audit reports.
Deliverable ID 2.08
Deliverable
Type
Fixed Price
Deliverable
Name
Data Conversion 3 (Go Live)
Deliverable
Description
HARRIS to perform the third data conversion from Oracle to SQL Server.
HARRIS
Responsibilities
• Develop ETL tool and scripts used for the conversion
• Examining source database, identifying custom objects
• Restore a copy of production Oracle to Oracle staging environment
• Execute conversion
• Copy converted database to SQL Production environment
• Produce audit reports & record counts
• Remediate conversion issues as required
CLIENT
Responsibilities
• Test & confirm data has been converted successfully/log detailed incidents for any issues
• Provide a copy of the production Oracle database to be used for the conversion
• Ensure critical processes are done before copy of Oracle (ex. Month end)
• Remediate source data issues
21
Cayenta V9 Statement of Work
Deliverable
Acceptance
Criteria
Conversion 3 is delivered with balanced audit reports and CLIENT signs off on submitted audit reports.
Deliverable ID 3.01
Deliverable
Type
Fixed Price
Deliverable
Name
V9.2 Overview Training & Core Portals/Stats Training
Deliverable
Description
HARRIS will provide two overview sessions on the new V9.2 features
HARRIS will provide an overview training session on how to use portals including core portals, online vs.
batch processing, column modifications and export capabilities.
HARRIS
Responsibilities
• Facilitate overview training sessions
CLIENT
Responsibilities
• Attend overview training sessions
Deliverable
Acceptance
Criteria
HARRIS delivers the overview training sessions
Deliverable ID 3.02
Deliverable
Type
Fixed Price
Deliverable
Name
CayStone Test Cases Setup
Deliverable
Description
HARRIS will set up the CayStone testing environment, granting access to all CLIENT testers and
stakeholders required. HARRIS will provide the core V9.2 test cases. Any custom test cases will be the
responsibility of CLIENT to develop.
HARRIS
Responsibilities
• Create the new CayStone project with V9.2 core test cases
• Provision access for all CLIENT testers
CLIENT
Responsibilities
• Provide list of testers to HARRIS
• Develop any required custom test cases
Deliverable
Acceptance
Criteria
CayStone project has been created and access provided to all testers listed by CLIENT
Deliverable ID 3.03
Deliverable
Type
T&M
Deliverable
Name
FMS Scripting Assistance
Deliverable
Description
HARRIS to provide CLIENT with assistance in updating existing FMS scripts to ensure compatibility with
V9 platform
HARRIS
Responsibilities
• Perform services as requested
CLIENT
Responsibilities
• Provide written approval to proceed with requested work
Deliverable
Acceptance
Criteria
CLIENT will be invoiced monthly for hours expended. Hours invoiced will not exceed allocated hours
without written approval from CLIENT
22
Cayenta V9 Statement of Work
Deliverable ID 3.04
Deliverable
Type
Fixed Price
Deliverable
Name
HCM Module Delivered for Testing
Deliverable
Description
HARRIS will conduct an overview session of the HCM module to show CLIENT how the module is used as
well as elicit any additional configuration requirements. HARRIS will deliver a configured solution to
CLIENT for testing of the HCM module and conduct a training/handover session for CLIENT testers.
HARRIS
Responsibilities
• Facilitate the overview session
• Configure HCM module
• Facilitate the training session
CLIENT
Responsibilities
• Attend overview session
• Attend training session
• Provide input/clarifications as required
Deliverable
Acceptance
Criteria
HARRIS delivers configured HCM module for testing
Deliverable ID 3.05
Deliverable
Type
Fixed Price
Deliverable
Name
Time-Based Employee Master Delivery for Testing
Deliverable
Description
HARRIS will configure the Time-Based Employee Master and deliver an overview session to CLIENT
HARRIS
Responsibilities
• Configure Time-Based Employee Master
• Provide overview session
CLIENT
Responsibilities
• Attend overview session
• Provide input/clarifications as required
Deliverable
Acceptance
Criteria
HARRIS delivers configured Time-Based Employee Master module for testing
Deliverable ID 3.06
Deliverable
Type
Fixed Price
Deliverable
Name
CONNECT Finance Delivery for Testing
Deliverable
Description
HARRIS will configure the Connect Finance application for CLIENT testing.
HARRIS
Responsibilities
• Configure the Connect Finance application
• Conduct unit testing
• Facilitate a handover training session in preparation for CLIENT testing
CLIENT
Responsibilities
• Provide input/clarifications as required
• Attend handover/training session
Deliverable
Acceptance
Criteria
HARRIS delivers the configured Connect Finance application for CLIENT testing
23
Cayenta V9 Statement of Work
Deliverable ID 3.07
Deliverable
Type
Fixed Price
Deliverable
Name
CONNECT Time Entry Delivery for Testing
Deliverable
Description
HARRIS will configure the Connect Time Entry application for CLIENT testing.
HARRIS
Responsibilities
• Configure the Connect Time Entry application
• Conduct unit testing
• Facilitate a handover training session in preparation for CLIENT testing
CLIENT
Responsibilities
• Provide input/clarifications as required
• Attend handover/training session
Deliverable
Acceptance
Criteria
HARRIS delivers the configured Connect Time Entry application for CLIENT testing
Deliverable ID 3.08
Deliverable
Type
Fixed Price
Deliverable
Name
CONNECT Employee Delivery for Testing
Deliverable
Description
HARRIS will configure the Connect Employee application for CLIENT testing.
HARRIS
Responsibilities
• Configure the Connect Employee application
• Conduct unit testing
• Facilitate a handover training session in preparation for CLIENT testing
CLIENT
Responsibilities
• Provide input/clarifications as required
• Attend handover/training session
Deliverable
Acceptance
Criteria
HARRIS delivers the configured Connect Employee application for CLIENT testing
Deliverable ID 3.09
Deliverable
Type
Fixed Price
Deliverable
Name
CONNECT Manager Delivery for Testing
Deliverable
Description
HARRIS will configure the Connect Manager application for CLIENT testing.
HARRIS
Responsibilities
• Configure the Connect Manager application
• Conduct unit testing
• Facilitate a handover training session in preparation for CLIENT testing
CLIENT
Responsibilities
• Provide input/clarifications as required
• Attend handover/training session
Deliverable
Acceptance
Criteria
HARRIS delivers the configured Connect Manager application for CLIENT testing
24
Cayenta V9 Statement of Work
Deliverable ID 3.10
Deliverable
Type
T&M
Deliverable
Name
Implement New Equipment Module
Deliverable
Description
HARRIS will conduct an overview session and configure/implement New Equipment Module
functionality, based on the outcome of discovery.
HARRIS
Responsibilities
• Facilitate the discovery session
• Document requirements pertaining to New Equipment Module functionality.
• Perform related configuration and conversion
based on the discovery.
• Assist with testing the newly implemented module.
CLIENT
Responsibilities
• Attend discovery session
• Provide decisions needed to confirm requirements and sign-off on the requirements
• Functional and integrated testing on the new module
Deliverable
Acceptance
Criteria
CLIENT confirms the delivered requirements document covers all requirements needed to implement
New Equipment Module functionality.
CLIENT will be invoiced monthly for hours expended. Hours invoiced will not exceed allocated hours
without written approval from CLIENT
Deliverable ID 3.11
Deliverable
Type
Fixed Price
Deliverable
Name
Grants Module Delivered for Testing
Deliverable
Description
HARRIS will conduct an overview session of the Grants module to show CLIENT how the module is used
as well as elicit any additional configuration requirements. HARRIS will deliver a configured solution to
CLIENT for testing of the Grants module and conduct a training/handover session for CLIENT testers.
HARRIS
Responsibilities
• Facilitate the overview session
• Configure Grants module
• Facilitate the training session
CLIENT
Responsibilities
• Attend overview session
• Attend training session
• Provide input/clarifications as required
Deliverable
Acceptance
Criteria
HARRIS delivers configured Grants module for testing
Deliverable ID 3.12
Deliverable
Type
Fixed Price
Deliverable
Name
Misc. AR Module Delivered for Testing
Deliverable
Description
HARRIS will conduct an overview session of the Miscellaneous AR module to show CLIENT how the
module is used as well as elicit any additional configuration requirements. HARRIS will deliver a
configured solution to CLIENT for testing of the Miscellaneous AR module and conduct a
training/handover session for CLIENT testers.
25
Cayenta V9 Statement of Work
HARRIS
Responsibilities
• Facilitate the overview session
• Configure Miscellaneous AR module
• Facilitate the training session
CLIENT
Responsibilities
• Attend overview session
• Attend training session
• Provide input/clarifications as required
Deliverable
Acceptance
Criteria
HARRIS delivers configured Miscellaneous AR module for testing
Deliverable ID 3.13
Deliverable
Type
Fixed Price
Deliverable
Name
FMS Health Check
Deliverable
Description
After the project has gone live at a time determined collaboratively between HARRIS and CLIENT,
HARRIS will conduct a Health Check on CLIENT usage of the FMS solution. Sessions allocated for health
check review will focus on improving the processes so as the result the customer can be more efficient
in their day to day activities. The result of these sessions is a detailed report with summary of findings
and the next steps and recommendations. Any resulting configuration or system changes requiring
Cayenta involvement will be managed through the Change Control process.
HARRIS
Responsibilities
• Facilitate the Health Check Sessions
• Prepare & Present Health Check Report
CLIENT
Responsibilities
• Participate in Health Check Sessions
Deliverable
Acceptance
Criteria
FMS Health Check report delivered and presented
Deliverable ID 3.14
Deliverable
Type
Fixed Price
Deliverable
Name
WMS Health Check
Deliverable
Description
After the project has gone live at a time determined collaboratively between HARRIS and CLIENT,
HARRIS will conduct a Health Check on CLIENT usage of the FMS solution. Sessions allocated for health
check review will focus on improving the processes so as the result the customer can be more efficient
in their day to day activities. The result of these sessions is a detailed report with summary of findings
and the next steps and recommendations. Any resulting configuration or system changes requiring
Cayenta involvement will be managed through the Change Control process.
HARRIS
Responsibilities
• Facilitate the Health Check Sessions
• Prepare & Present Health Check Report
CLIENT
Responsibilities
• Participate in Health Check Sessions
Deliverable
Acceptance
Criteria
WMS Health Check report delivered and presented
Deliverable ID 4.01
Deliverable
Type
T&M
26
Cayenta V9 Statement of Work
Deliverable
Name
Custom portal stats and interfaces testing support (T&M)
Deliverable
Description
T&M hours to be used for updating of custom portal stats and interfaces, as needed for the upgrade.
HARRIS
Responsibilities
• Perform services as requested
CLIENT
Responsibilities
• Provide written approval to proceed with requested work
Deliverable
Acceptance
Criteria
CLIENT will be invoiced monthly for hours expended. Hours invoiced will not exceed allocated hours
without written approval from CLIENT
Deliverable ID 4.02
Deliverable
Type
Fixed Price
Deliverable
Name
FMS Operational Model Delivered for Testing
Deliverable
Description
HARRIS will configure the FMS Operational Model for CLIENT testing and provide a training session to
set up CLIENT for testing.
HARRIS
Responsibilities
• Configure FMS Operational Model
• Deliver overview session
CLIENT
Responsibilities
• Attend overview session
Deliverable
Acceptance
Criteria
HARRIS delivers FMS Operational Model for testing
Deliverable ID 4.03
Deliverable
Type
Fixed Price
Deliverable
Name
HCM Operational Model Delivered for Testing
Deliverable
Description
HARRIS will configure the HCM Operational Model for CLIENT testing and provide a training session to
set up CLIENT for testing.
HARRIS
Responsibilities
• Configure HCM Operational Model
• Deliver overview session
CLIENT
Responsibilities
• Attend overview session
Deliverable
Acceptance
Criteria
HARRIS delivers HCM Operational Model for testing
Deliverable ID 4.04
Deliverable
Type
Fixed Price
Deliverable
Name
FMS Analytics Module Delivered for Testing
Deliverable
Description
HARRIS will configure the FMS Analytics Module for CLIENT testing and provide a training session to set
up CLIENT for testing.
HARRIS
Responsibilities
• Configure FMS Analytics Module
• Deliver overview session
27
Cayenta V9 Statement of Work
CLIENT
Responsibilities
• Attend overview session
Deliverable
Acceptance
Criteria
HARRIS delivers FMS Analytics Module for testing
Deliverable ID 4.05
Deliverable
Type
Fixed Price
Deliverable
Name
HCM Analytics Module Delivered for Testing
Deliverable
Description
HARRIS will configure the HCM Analytics Module for CLIENT testing and provide a training session to set
up CLIENT for testing.
HARRIS
Responsibilities
• Configure HCM Analytics Module
• Deliver overview session
CLIENT
Responsibilities
• Attend overview session
Deliverable
Acceptance
Criteria
HARRIS delivers HCM Analytics Module for testing
28
Cayenta V9 Statement of Work
Methodology & Schedule
Methodology
Cayenta follows a practiced and proven methodology for delivering projects to our customers. Below is
an overview of our project phases.
Project Management
HARRIS will provide a project manager to the project to oversee the HARRIS team and to work with the
CLIENT project manager. The HARRIS project manager will be responsible for the following items:
• Develop and maintain the project schedule, collaborating with CLIENT project manager.
• Schedule and facilitate weekly PM meetings.
• Schedule and facilitate weekly team meetings.
• Develop go-live cutover checklist, collaborating with HARRIS and CLIENT project teams
• Ownership of the Change Control process as outlined in the Change Control section of this
document
Schedule development is a collaborative task – the initial timeframe reflects the pricing provided, and a
final schedule is dependent on the completion of project planning, where tasks and dependencies are
finalized, resource allocation is confirmed and all non-working days are identified. A finalized project
schedule must be delivered and baselined before the environment setup begins, and material changes
to the initial schedule may require a change order. Any deviation from this process must be agreed to by
the project teams.
HARRIS agrees to provide project management services on a monthly basis as outlined in the
deliverables of this document. Should there be a need to extend project management services from
Environment
Setup
PGL Support
Go Live
Tes ng
End ser
Training
Train the Tester
Training
Project Management
Mock
1 2Conversion
Development
Product
Con gura on Tes ng Support
29
Cayenta V9 Statement of Work
HARRIS beyond what is currently scoped in this document, additional months of testing support may be
added to the project at a cost determined through the Change Control process.
Environment Setup
HARRIS will create the environments required for the project, as defined in this document in the Project
Environments section. This requires CLIENT to ensure that any server infrastructure required by HARRIS
is provisioned and accessible by the HARRIS team.
Configuration
HARRIS will perform required configuration services to deliver the products to CLIENT in a test-ready
fashion. Both HARRIS and CLIENT recognize that there may be configuration rework required as testing
progresses however any significant configuration rework that is not the direct result of incorrect
configuration by HARRIS may require a monetary change order
New Feature Overview & Train-the-Tester Training
HARRIS will provide solution overview with a focus on new features offered in the new version of the
software. HARRIS consultants will work with CLIENT testers to deliver the training required for CLIENT
testers to execute test cases for the project. HARRIS will also ensure that CLIENT testers have access to
the CayStone environment and that all core test cases are available for CLIENT testers to execute testing
against.
Testing
Application testing will be the most critical phase of this project and allows CLIENT to ensure a level of
comfort with the delivered solution prior to going live. HARRIS will provide testing support
commensurate with the services outlined in the Deliverables section of this document.
CLIENT will test the application and configured solution delivered by HARRIS. CLIENT agrees to use the
CayStone testing platform, provided by HARRIS to plan test cases/test sets, track all testing progress via
updating of executed test cases/test sets and log incidents for all defects found. Should CLIENT decide
to forego the use of CayStone for these purposes (i.e., using alternate means to plan and track testing
and incidents), HARRIS may initiate the change control process (per the Change Control section of this
document) to determine impacts to the project, monetary and otherwise.
HARRIS agrees to provide testing support services on a monthly basis as outlined in the deliverables of
this document. Should there be a need to extend testing support services from HARRIS beyond what is
currently scoped in this document, additional months of testing support may be added to the project at
a cost determined through the Change Control process.
Training
HARRIS will provide training on the new features of the solution early in the project in advance of the
testing phase. This training will include an overview of the new features and products in scope of the
project as well as CayStone training for those testers who are not familiar with it. CLIENT will be
responsible for the development of customized end user training materials as well as the delivery of the
end user training.
30
Cayenta V9 Statement of Work
Go Live
HARRIS and CLIENT will work collaboratively to prepare a go-live cutover checklist, drawing on templates
that HARRIS will provide. It will be a shared responsibility between HARRIS and CLIENT to ensure that all
tasks are documented and assigned appropriately. A mock go-live will be conducted approximately 4-6
weeks before the planned go-live to ensure that the cutover checklist is fully comprehensive with
respect to the go-live tasks. HARRIS and CLIENT will schedule the go-live to take place over a weekend or
a mutually agreeable timeframe.
Post Go-Live and Transition Support
HARRIS project team will continue to support CLIENT during the defined post go-live period (as indicated
in the Deliverables section of this document) as well in this time engage Cayenta Support by preparing a
Support Transition document, outlining the details of the implementation relevant to the Cayenta
Support team taking on stewardship of CLIENT support needs going forward. A transition meeting
including the HARRIS project team, CLIENT and Cayenta Support will be facilitated by HARRIS as part of
this transition.
Schedule
This is an 8-month project (including 1-week of Support transition), plus an additional 3-weeks of
Support transition (for a total of 4-weeks of Support transition), followed by a return to Standard
Support.
The schedule has been estimated based on assumed resourcing capabilities of CLIENT and is subject to
change upon planning and coordination between HARRIS and CLIENT.
Upon starting the project, the HARRIS project manager will collaborate with CLIENT Project Manager to
baseline the project schedule.
Project Environments
CLIENT agrees to the provision of infrastructure required to support the following net new environments
required for the project.
Environment
Name
Purpose
CAYPROD92 To be used as the primary environment for the project during testing as well as the
production environment upon go-live
CAYTEST92 To be used as the test environment on the new platform after go-live
Oracle Staging To be used as the data staging environment for Oracle data for the Oracle to SQL
conversion
SQL Staging To be used as the data staging environment for SQL Server data for the Oracle to
SQL conversion
31
Cayenta V9 Statement of Work
Payment Milestones
Below is a list of the payment milestones for this project. CLIENT agrees to pay the milestones upon
completion of the mapped deliverables according to the defined acceptance criteria in this document
for each deliverable.
MP# Payment Milestone Description Invoice
Amount
Deliverable
ID
Deliverable Name
MP01 Project Management Services - Month
1
$17,600.00 1.01 Project Management Services - Month
1
MP02 Project Management Services - Month
2
$17,600.00 1.02 Project Management Services - Month
2
MP03 Project Management Services - Month
3
$17,600.00 1.03 Project Management Services - Month
3
MP04 Project Management Services - Month
4
$17,600.00 1.04 Project Management Services - Month
4
MP05 Project Management Services - Month
5
$17,600.00 1.05 Project Management Services - Month
5
MP06 Project Management Services - Month
6
$17,600.00 1.06 Project Management Services - Month
6
MP07 Project Management Services - Month
7
$17,600.00 1.07 Project Management Services - Month
7
MP08 Project Management Services - Month
8
$17,600.00 1.08 Project Management Services - Month
8
MP09 Testing Support - Month 1 $31,900.00 1.09 Testing Support - Month 1
MP10 Testing Support - Month 2 $31,900.00 1.10 Testing Support - Month 2
MP11 Testing Support - Month 3 $31,900.00 1.11 Testing Support - Month 3
MP12 Testing Support - Month 4 $31,900.00 1.12 Testing Support - Month 4
MP13 Testing Support - Month 5 $31,900.00 1.13 Testing Support - Month 5
MP14 Testing Support - Month 6 $31,900.00 1.14 Testing Support - Month 6
MP15 Mock Go Live $8,800.00 1.15 Mock Go Live
MP16 Go Live Services $8,800.00 1.16 Go Live Services
MP17 Support Transition & Project Close $27,720.00 1.17 Support Transition & Project Close
MP18 CAYPROD92 Environment Build $8,800.00 2.01 CAYPROD92 Environment Build
MP19 CAYTEST92 Environment Build $8,800.00 2.02 CAYTEST92 Environment Build
MP20 Install Cognos for MS SQL $3,300.00 2.03 Install Cognos for MS SQL
MP21 Connect Web Products Installation $6,600.00 2.04 Connect Web Products Installation
MP22 New Test and Production Cayenta
Software Manager installation
$4,400.00 2.05 New Test and Production Cayenta
Software Manager installation
MP23 Data Conversion 1 $33,000.00 2.06 Data Conversion 1
MP24 Data Conversion 2 (Mock Go Live) $33,000.00 2.07 Data Conversion 2 (Mock Go Live)
MP25 Data Conversion 3 (Go Live) $33,000.00 2.08 Data Conversion 3 (Go Live)
MP26 V9.2 Overview Training & Core
Portals/Stats Training
$1,760.00 3.01 V9.2 Overview Training & Core
Portals/Stats Training
MP27 CayStone Test Cases Setup $1,760.00 3.02 CayStone Test Cases Setup
MP28 HCM Module Delivered for Testing $35,200.00 3.04 HCM Module Delivered for Testing
MP29 Time-Based Employee Master Delivery
for Testing
$26,400.00 3.05 Time-Based Employee Master
Delivery for Testing
32
Cayenta V9 Statement of Work
MP30 CONNECT Finance Delivery for Testing $22,000.00 3.06 CONNECT Finance Delivery for Testing
MP31 CONNECT Time Entry Delivery for
Testing
$22,000.00 3.07 CONNECT Time Entry Delivery for
Testing
MP32 CONNECT Employee Delivery for
Testing
$22,000.00 3.08 CONNECT Employee Delivery for
Testing
MP33 CONNECT Manager Delivery for Testing $22,000.00 3.09 CONNECT Manager Delivery for
Testing
MP34 Implement New Equipment Module $5,280.00 3.10 Implement New Equipment Module
MP35 Misc. AR Module Delivered for Testing $33,000.00 3.12 Misc. AR Module Delivered for Testing
MP36 FMS Health Check $13,200.00 3.13 FMS Health Check
MP37 WMS Health Check $13,200.00 3.14 WMS Health Check
MP38 FMS Operational Model Delivered for
Testing
$17,600.00 4.02 FMS Operational Model Delivered for
Testing
MP39 HCM Operational Model Delivered for
Testing
$17,600.00 4.03 HCM Operational Model Delivered for
Testing
MP40 FMS Analytics Module Delivered for
Testing
$17,600.00 4.04 FMS Analytics Module Delivered for
Testing
MP41 HCM Analytics Module Delivered for
Testing
$17,600.00 4.05 HCM Analytics Module Delivered for
Testing
Fixed Price Implementation Sub-total $796,620.00
MP42 FMS Scripting Assistance $1,760.00 3.03 FMS Scripting Assistance
MP43 Grants Module Delivered for Testing $33,000.00 3.11 Grants Module Delivered for Testing
MP44 Custom portal stats and interfaces
testing support (T&M)
$2,640.00 4.01 Custom portal stats and interfaces
testing support (T&M)
T&M Implementation Sub-total $37,400.00
FEE-01 3rd Party AcuCobol one-time migration
fee
$2,600.00 N/A Due on contract signing
LIC-01 Cayenta Analytics - FMS: License Fee $10,000.00 N/A Due on contract signing
LIC-02 Cayenta Analytics - FMS & HCM: 3rd
Party License Fee
$15,000.00 N/A Due on contract signing
LIC-03 Operational Models - FMS: License Fee $10,000.00 N/A Due on contract signing
LIC-04 Miscellaneous AR and Payments
Processing: License Fee
$10,000.00 N/A Due on contract signing
LIC-05 Grant Management: License Fee $10,000.00 N/A Due on contract signing
LIC-06 Cayenta Analytics - HCM: 3rd Party
License Fee
$5,000.00 N/A Due on contract signing
LIC-07 Operational Models - HCM: License Fee $10,000.00 N/A Due on contract signing
New Fee/License Sub-total $72,600.00
Project Total $906,620.00
MN-01 Annual Fee: Cognos Administrator $2,500.00 N/A Due upon installation
MN-02 Annual Fee: Cayenta Analytics - FMS $2,500.00 N/A Due upon installation
MN-03 Annual Fee: Operational Models - FMS $2,500.00 N/A Due upon installation
33
Cayenta V9 Statement of Work
MN-04 Annual Fee: Miscellaneous AR &
Payment Processing
$2,500.00 N/A Due upon installation
MN-05 Annual Fee: Grant Management $2,500.00 N/A Due upon installation
MN-06 Annual Fee: Cayenta Analytics - HCM $2,500.00 N/A Due upon installation
MN-07 Annual Fee: Operational Models - HCM $2,500.00 N/A Due upon installation
SUB-01 Annual Fee: Connect Finance Base $10,020.00 N/A Due upon installation
SUB-02 Annual Fee: Connect Finance Expense
Entry
$2,400.00 N/A Due upon installation
SUB-03 Annual Fee: Human Capital
Management (HCM)
$16,800.00 N/A Due upon installation
SUB-04 Annual Fee: Connect Employee $13,650.00 N/A Due upon installation
SUB-05 Annual Fee: Connect Manager $10,020.00 N/A Due upon installation
SUB-06 Annual Fee: Connect Time Entry $12,960.00 N/A Due upon installation
Annual Costs (Year 1) Total: $83,350.00
34
Cayenta V9 Statement of Work
Overall Terms & Termination
Terms and Conditions
1. All subscriptions, as well as license fees and related support/maintenance, shall be
billed upon signing the Statement of Work, unless otherwise noted in this document.
2. Pricing is fixed for scope as defined by this document unless it is noted as
Time and Material in the Table of Services and excludes any applicable taxes.
3. Additional services deemed out of scope (per this document) will be billed at $220 per
hour and will require documentation from HARRIS and the CLIENT and compliance with the
Change Control Process.
4. CLIENT will provide a direct connection to the Server on which the database resides.
5. CLIENT will provide any necessary infrastructure for the project.
6. Both HARRIS and CLIENT will ensure members are available on dates agreed to and
scheduled.
7. Change Orders will be created for any tasks that are requested outside the scope of the
project and will follow the Change Control Process.
8. HARRIS reserves the right to alter/enhance APIs (as well as decommission, and in
some cases replace APIs). Work to update Custom Portals is not covered by Standard
Support and if needed is billable and may require a Change Order (if the time is not
already built into the project plan). Additionally, any 3rd party costs to update
interfaces which call Cayenta APIs are the responsibility of CLIENT.
9. Additional full data refreshes after the start of the project will be an additional
cost and will be managed through the change control process
10. All project work is planned as remote, except for Health Checks.
11. Hardware costs are priced/managed directly by CLIENT.
12. HARRIS reserves the right to pause work upon notification to CLIENT if HARRIS invoices
become aged greater than 60 days.
13. In the event CLIENT terminates this Agreement, CLIENT shall be invoiced for work
done to date as of notification and CLIENT will pay all outstanding Fees and other
amounts owing to Harris under this Agreement.
14. Actual travel and living expenses will be billed as incurred without any mark-up.
Cayenta will work to minimize travel and living expenses. Expenses include:
a. Airfare
b. Lodging
c. Per Diem (HARRIS policy allows for $65/day for week days ($130 for
weekends and holidays)
d. Ground transportation (taxis, rental cars, fuel, tolls, parking, business
miles)
e. Office supplies/services (as required)
f. Internet access (airline)
HARRIS travel guidelines will be adhered to by HARRIS personnel traveling to CLIENT.
35
Cayenta V9 Statement of Work
Termination
Unless HARRIS and/or CLIENT exercises its right to terminate this Statement of Work due to material
breach or default, HARRIS must provide, and the CLIENT must purchase, Services from HARRIS for the
items defined within this Statement of Work.
The CLIENT obligations include the following:
1. Complete payment for services performed and expenses incurred prior to termination
including:
a. Any amount previously invoiced but unpaid.
b. Fees for services performed through termination date which have not been
invoiced; and
c. Any approved Travel and Living costs incurred.
If HARRIS terminates this Statement of Work without cause, then it shall:
1. Provide notice of 10 calendar days for termination without cause.
2. Refund to the CLIENT any fees that have not been earned under this Statement of Work
through the termination date.
Under no circumstances shall HARRIS be liable for any special, indirect, consequential, punitive, or
incidental damages of any kind, including but not limited to loss of revenue, loss of profits, loss of
business opportunity, loss of data arising out of or in connection with this scope statement, even if
HARRIS has been advised of the possibility of such damages. In any event. HARRIS shall not be liable to
pay any amount, in the aggregate, that is greater than the fees received by HARRIS under this Statement
of Work.
36
Cayenta V9 Statement of Work
Appendix A: Incident Priority Definitions
HARRIS and CLIENT agree to use the following priority definitions when prioritizing incidents
logged during the project.
Priority 1 – Critical
• System Down (Software Application, Hardware, Operating System, Database)
• Application errors without workarounds that prevent testers from testing.
• Incorrect calculation errors impact a majority of data.
• Aborted postings or error messages preventing data integration and update.
• Performance issues of severe nature impacting critical processes
• Performance issues impacting critical processes.
• Critical incidents assigned back to CLIENT need to be validated within a business day.
Note: the existence of a reasonable work-around precludes a Priority 1 or Priority 2 issue
in most cases.
Priority 2 - High
• Application errors that have workarounds impacting business, but the workaround
is either complex or time consuming and significantly affects productivity after go-
live.
• Calculation errors impacting a minority of records.
• Report generation failures impacting critical processes.
• Report calculation issues
• Data Security issues
• Printer related issues (related to interfaces with our software and not the printer itself)
• High Priority incidents assigned back to CLIENT need to be validated within 2- 3 business days.
Priority 3 – Medium
• Application errors/issues that have workarounds impacting business, but the
workaround is either complex or time consuming
• Report formatting issues
• Issues with workarounds for large majority of accounts
• Some recommendations for enhancements on application changes
• Performance issues not impacting critical processes.
• Usability issues
• Medium Priority incidents assigned back to CLIENT need to be validated within 5 business
days.
37
Cayenta V9 Statement of Work
Appendix B: Change Control Process
The "Change Control Process" governs changes to the Project parameters (scope, schedule, budget,
quality, risk) during the life of the Project. Change Orders can be requested by HARRIS or CLIENT;
however, all Change Orders must be approved in writing by both HARRIS and CLIENT before any changes
are formally accepted into the project.
No Change Order shall become effective unless mutually agreed to in writing by both parties. No work,
other than estimating, will be performed on a Change Order by HARRIS until sign off has been obtained
by the parties. There will not be fees charged by HARRIS to provide estimates for Change Orders.
To effectively control changes to the project, HARRIS uses an industry standard Change Control process
to assess all impacts of a potential project change. The Change Control process is described below:
Change Request Submission
CLIENT and/or HARRIS identify a need for a change to the project and submit a request. It is expected
that the party raising the request will provide as much relevant information as possible at the time of
raising the request to support proper impact assessment activities.
Such a request must be in writing and identify the business and other reasons for the requested change
and the impact it would have if the change were agreed upon, which may include Budget, Deliverables,
Milestone Payments, Schedule, Risks, and Resources.
Change Request Assessment
HARRIS and CLIENT Project Managers will assess the potential change and the impact on budget,
schedule, quality, resources, and risks. Where applicable, options will be defined and documented.
Change Order (document)
The HARRIS Project Manager will prepare a formal Change Order document and submit it to the CLIENT
for review. The Change Order document will contain at a minimum:
• Business reason/justification for the change
• Detailed description of the change
• Impact assessment of the change
• Any payment milestone revisions impacted by the change (projected billing dates and invoice
amounts)
• Project impacts of not approving the change
Any Deliverables that have already been completed and accepted by the CLIENT that are subsequently
altered because of a Change Order must be appropriately revised, pursuant to the Change Order, with
the change number and date noted. An updated version of such a Deliverable will then be signed and
stored with the project documentation.
CLIENT and HARRIS will review the Change Order for approval or rejection.
Change Order Review Period
After any request for a Change Order is made, the parties will have five (5) business days, or any
additional, mutually agreed upon period, to consider the request (the “Change Order Review Period”).
38
Cayenta V9 Statement of Work
The Change Order Review Period will commence the day the Change Order request is received in writing
by the party being asked for the Change Order. During the Change Order Review Period, HARRIS will
provide the CLIENT with all information material to the requested Change Order, regardless of which
party initiated the Change Order, including but not limited to any additional fees that would be incurred,
the impacts on the relevant Deliverables, and any alteration of the MS Project Schedule that would
result if the Change Order were agreed to. HARRIS will also, during the Change Order Review Period,
provide a time and materials or a Fixed Price cost based on the CLIENT’s desired pricing model.
During the Change Order Review Period, the CLIENT will provide HARRIS with any information
reasonably requested by HARRIS to evaluate any Change Order requested by CLIENT.
Change Order Approval
If both the CLIENT and HARRIS agree to the change, all relevant terms shall be documented in the
Change Order. Any charges not already specified in the Statement of Work, or which are different than
those in this Statement of Work will be noted in the Change Order. Any additional services performed by
HARRIS because of a Change Order will require the payment to HARRIS of additional fees as agreed.
Upon approval, CLIENT and HARRIS will sign the Change Order document and have the executed copy
stored in the project document repository.
Change Order Rejection
If agreement on a requested Change Order does not occur by the end of the Change Order Review
Period, the change order is considered rejected. At this point, either party may initiate the conflict
resolution process set forth in this Statement of Work regarding the requested Change Order, unless the
change solely regards a Deliverable that was completed and accepted before the request for the Change
Order was made.
Change Request/Change Order Log
HARRIS will maintain an ongoing log of all Change Orders during the life of the project. This will be
accessible to CLIENT.
Conflict Resolution Process
HARRIS recommends three levels for conflict escalation:
1. Project Managers to
2. Sponsors/Director to
3. Executive (VP, EVP, GM).
One representative from HARRIS and representatives from CLIENT are designated at each level. All
issues must be in written form – providing details, impacts and alternative resolutions. If the parties are
unable to resolve a dispute through this informal process, then they will follow the formal Dispute
Resolution process that is set forth in the Software Implementation Services Agreement.