HomeMy WebLinkAboutResolution_ForestRidgeFinalPlat_RemandCondition25KITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
2024 AGENDA STAFF REPORT
AGENDA DATE: February 20, 2024
ACTION REQUESTED: Request to Approve a Resolution Satisfying Condition 25
Remand from Superior Court Regarding the Final Plat of
Forest Ridge Phase 4 and Phase 5
BACKGROUND: In September 2023, the Superior Court issued a decision on
the land use petition challenging the final plat of Forest
Ridge, Phases 4 and 5. Kittitas County Superior Court
rejected all arguments regarding the final plat and the
BOCC's process except for remanding the final plat for
further review regarding the the final plat's consistency
with Condition 25 as that relates to secondary access.
Representatives for Forest Ridge are working to relocate
this easement supporting secondary access. The easement's
terms state that roads shall be relocated "commensurate
with good land use transportation planning". In order to
resolve the Condition 25 remand, Forest Ridge is also
working with another property owner and expects
resolution utilizing the primary access as depicted on the
final plat. Further easement work with that resident is in
process, but again, is a matter of private property interests
that the County does not adjudicate. Resolving Condition
25 of the remand, staff have worked with the applicant's
engineer to develop an acceptable alternate secondary
access if the preferred alternative access somehow fails to
the applicant's satisfaction. An acceptable revised
engineer's estimate has been vetted by the County Engineer
along with preliminary engineering documents suitable for
the County Engineer to represent to the Board that the
Condition 25 remand has been met. It is the department's
opinion that the final plat is consistent with Condition 25
based on the foregoing summary and that the final plat
meets all County Code and State law standards.
INTERACTION: Public Works.
RECOMMENDATION: Approve the Condition 25 remand to staff as accepted by
the County Engineer.
HANDLING: Return one original to Public Works.
ATTACHMENTS: Resolution.
LEAD STAFF: Mark R. Cook, Director.
BOARD OF COUNTY COMMISSIONERS
COUNTY OF KITTITAS
STATE OF WASHINGTON
RESOLUTION
NO.
APPROVING CONDITION 25 REMAND FORM KITTITAS COUNTY SUPERIOR
COURT REGARDING THE FINAL PLAT OF FOREST RIDGE PHASE 4 AND 5
WHEREAS: In September 2023, Superior Court remanded to staff Condition 25 of the Final
Plat of Forest Ridge Phase 4 and 5; and
WHEREAS: Legal representatives for the plat proponent are working to resolve an access
easement with an area resident to preserve the primary access as depicted on the
face of the plat; and
WHEREAS: Staff have worked with the proponent's engineer developing an alternative
access that satisfies the Condition 25 remand from Superior Court; and
WHEREAS: The County Engineer has vetted the proposed alternative access for
acceptability satisfying the Condition 25 Superior Court remand.
NOW, THEREFORE BE IT RESOLVED: The Board of County Commissioners, after due
consideration, does hereby affirm the Final Plat of Forest Ridge Phase 4 and 5 by accepting the
County Engineer's alternative access analysis for the final plat.
DATED this 20th day of February 2024, at Ellensburg, Washington,
Attest:
❑ Clerk of the Board- Julie Kjorsvik
❑ Deputy Clerk of the Board- Mandy Buchholz
BOARD OF COUNTY COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
Brett Wachsmith, Chairman
Laura Osiadacz, Vice -Chairman
Cory Wright, Commissioner