HomeMy WebLinkAboutResolution_LibertySwaukCreekBridge_Prospectus_Updated (2)KITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
AGENDA STAFF REPORT
AGENDA DATE: February 6, 2024
ACTION REQUESTED: Request to Approve a Resolution Authorizing the Chair's
Signature on the Local Agency Federal Aid Project
Prospectus for the Liberty Road Swauk Creek Bridge
Replacement CRP 306-21.
BACKGROUND: On March 29, 2022, Kittitas County was informed that the
Liberty Road Swauk Creek Bridge Replacement Project
was selected to receive funding through the Federal Lands
Access Program (FLAP). The Federal Funds are
administered through Washington State Department of
Transportation (WSDOT) Local Programs per the Local
Agency Guidelines (LAG).
Public Works has also been granted additional funding
from the FLAP program to cover the higher than
anticipated construction costs. Public Works was notified in
November 2023 that an additional $1,200,000.00 was
approved for the project. Due to the continuing resolution
at the federal level, the Federal Highway Administration
has noticed Public Works that additional award will be
formalized at a later date. This prospectus is showing this
additional funding as local funds on the Prospectus but will
supplement our Local Agency Agreement with WSDOT
when the additional Federal Funding is formalized and
released.
The LAG requires Federal Funds for each phase of a
project to be obligated separately. The Preliminary
Engineering phase was obligated in May 2022. We are now
preparing to advertise for construction and are ready to
obligate the Construction Phase funds.
A Local Agency Federal Aid Project Prospectus must be
executed by the Chair acknowledging the project has been
reviewed and is consistent with the County's
comprehensive plan for community development.
INTERACTION: Public Works
RECOMMENDATION: Approve the Resolution Authorizing the Chair's signature
on the Local Agency Federal Aid Project Prospectus for the
Liberty Road Swauk Creek Bridge Replacement CRP 306-
21.
HANDLING: Return one original to Public Works
ATTACHMENTS: Resolution, Local Agency Federal Aid Project Prospectus
LEAD STAFF: Josh Fredrickson, County Engineer
BOARD OF COUNTY COMMISSIONERS
COUNTY OF KITTITAS
STATE OF WASHINGTON
RESOLUTION NO.2024 -
AUTHORIZING THE CHAIR'S SIGNATURE ON THE LOCAL AGENCY FEDERAL
AID PROJECT PROSPECTUS FOR THE LIBERTY ROAD SWAUK CREEK BRIDGE
REPLACEMENT, CRP 306-21
WHEREAS: Public Works has received funding through the FFY 2022 WA Federal Lands
Access Program (FLAP); and
WHEREAS: The federal funding will be used for the construction of a new bridge on Liberty
Road crossing Swank Creek; and
WHEREAS: In preparation for construction advertisement Kittitas County Public Works is
requesting the Washington State Department of Transportation release the federal
funds for the construction phase; and
WHEREAS: A Local Agency Federal Aid Project Prospectus must be executed by the Chair
acknowledging the project has been reviewed and is consistent with the County's
comprehensive plan for community development; and
NOW, THEREFORE BE IT RESOLVED that the Board of County Commissioners, in the best
interest of the public, does hereby approve the Chair's signature on the Local
Agency Federal Aid Project Prospectus for the Liberty Road Swank Creek
Bridge Replacement, CRP 306-21.
DATED on this 6th day of February 2024, at Ellensburg, Washington.
Attest:
❑ Clerk of the Board- Julie Kjorsvik
BOARD OF COUNTY
COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
Brett Wachsmith, Chair
Laura Osiadacz, Vice -Chair
❑ Deputy Clerk of the Board- Mandy Buchholz
Cory Wright, Commissioner
I►
w7Washington State
A#F Department of Transportation
Local Agency Federal Aid
Project Prospectus
Prefix
Route
( )
Date
1/11/2024
Projecctt Number Fede
u
FLAP - STBGR
2019
031
DUNS Number
01-020-2547
Lo Jal Agency
Project Number
RC 2193, CRP 306-21
( WSDO 1
` Use OnlyJ
Federal Employer
Tax ID Number
91-601349
Agency
CAAgency
Federal Program Title 20.224
Kittitas County Public Works
❑✓ Yes ❑ No
E120.205 ❑✓ Other Federal Lands Access Program
Project Title
Start Latitude N 47 14'35.21
Start Longitude W 120 41'S1.20
Liberty Road Swank Creek Bridge Replacement
End Latitude N 47 14'36.32
End Lon it deW 120 41'47.84
Project Termini From -To
Nearest City Name
Project Zip Code (+4)
MP 0.02 MP 0.07
Cle Elum
98922-9118
Begin Mile Post
End Mile Post
Length of Project
Award Type
0.02
0.07
0.05
0✓ Local ❑Local Forces ❑State ❑Railroad
Route ID
Begin Mile Point
End Mile Point
City Number
County Number
County Name
38350
0.02
0.07
N/A
19
Kittitas
WSDOT Region
Legislative District(s)
Congressional District(s)
Urban Area Number
North Central Region
13
8
N/A
Total
Local Agency
Federal Funds
Phase Start
Phase
Estimated Cost
Funding
Date
Nearest Hundred Dollar
Nearest Hundred Dollar
Nearest Hundred Dollar
Month Year
P.E.
799,000.00
317,700.00
481,300.00
05/2022
RIW
Const.
3,812,800.00
1,790,600.00
2,022,200.00
04/2024
Total
4,611,800.00
2,108,300.00
2,503,500.00
Description of Existing Facility (Existing Design and Present Condition)
Roadway Width
Number of Lanes
26'
2
Swauk Creek bridge # 07101 on Liberty Road is currently load restricted and needs to be replaced. The current
structure is 40' long x 30' wide and was originally built in 1955 and rebuilt in 1977.
Description of Proposed Work
Description of Proposed Work (Attach additional sheet(s) if necessary)
Replacement of bridge 07101 with new structure, realign stream and roadway
Local Agency Contact Person
Title
Phone
Darren Case
Construction Manager
509-962-7019
Mailing Address
City
State
de
411 N. Ruby, Suite 1
Ellensburg
WA
T98C9026
By
Project Prospectus
Approving Authority
Title County Engineer
Date 1/30/2024
DOT Form i4u-iun Page t
Revised 01/2022 Previous Editions Obsolete
Agency
Project Title
Date
Kittitas County Public Works
Liberty Road Swank Creek Bridge Replacq£_
1/11/2024
Type of Proposed Work
Project Type (Check all that Apply)
Roadway Width
Number of Lanes
❑ New Construction ❑ Path / Trail
❑ 3-R
32', 36' at bridge
2
❑ Reconstruction ❑ Pedestrian / Facilities
❑ 2-R
❑ Railroad ❑ Parking
❑ Other
Z Bridge
Geometric Design Data
Description
Through Route
Crossroad
❑ Principal Arterial
❑ Principal Arterial
Federal
❑ Urban
❑ Minor Arterial
ElUrban
ElMinor Arterial
Functional
W1 Rural
❑ Collector
❑ Rural
❑ Collector
Classification
❑ NHS
❑ Major Collector
❑ NHS
❑ Major Collector
0 Minor Collector
❑ Minor Collector
❑ Local Access
❑ Local Access
Terrain
❑ Flat Z Roll ❑ Mountain
❑ Flat ❑ Roll ❑ Mountain
Posted Speed
35
Design Speed
35
Existing ADT
153 - existing <400
Design Year ADT
400
Design Year
2022
Design Hourly Volume (DHV)
N/A
Performance of Work
Preliminary Engineering Will Be Performed By
Others
Agency
Agency and Consultant
75 %
25
Construction Will Be Performed By
Contract
Agency
Contractor
100
Environmental Classification
❑ Class I - Environmental Impact Statement (EIS)
Class II - Categorically Excluded (CE)
❑ Project Involves NEPA/SEPA Section 404
✓❑ Projects Requiring Documentation
Interagency Agreement
(Documented CE)
❑ Class III - Environmental Assessment (EA)
❑ Project Involves NEPA/SEPA Section 404
Interagency Agreements
Environmental Considerations
uv i rurm 140-1u I Page 2
Revised 01/2022 Previous Editions Obsolete
Agency
Project Title
Date
Kittitas County Public Works
Liberty Road Swauk Creek Bridge Replaeq
1/11/2024
Right of Way
❑✓ No Right of Way Needed
❑ Right of Way Needed
" All construction required by the
❑ No Relocation ❑ Relocation Required
contract can be accomplished
within the existing right of way.
Utilities
Railroad
❑ No utility work required
✓❑ No railroad work required
❑✓ All utility work will be completed prior to the start
❑ All railroad work will be completed prior to the start of
of the construction contract
the construction contract
All utility work will be completed in coordination
❑AII the railroad work will be completed in coordination
with the construction contract
I with the construction contract
Description of Utility Relocation or Adjustments and Existing Major Structures Involved in the Project
All utility relocations will be performed by the utility owners
FAA Involvement
Is any airport located within 3.2 kilometers (2 miles) of the proposed project? ❑ Yes ❑✓ No
Remarks
This project has been reviewed by the legislative body of the administration agency or agencies, or it's
designee, and is not inconsistent with the agency's comprehensive plan for community development.
Agency
Date By
Mayor/Chairperson