BEFORE THE BOARD OF COUNTY COMMISSIONERS OF KITTITAS COUNTY, STATE OF WASH]NGTON, iN thE MAttErof initiating a county road project designated as:
GRP NO: 319-23 JOB NO: RC229B-HP
lT lS HEREBY RESOLVED that the Horizontal Curve Safety Project be as follows:
The project will collect data and install/upgrade signing for horizontal curves (such as advisory speeds, chevrons,
delineation).
VARIOUS LOCATIONS COU NTYWDE
This project is hereby declared to be a Public necessity g1d the County Engineer is hereby ordered and authorized to report andproceed thereon as by law provided. (RCW 36.75.050, 36.80.030, 36.60.07b).
lT lS FURTHER RESOLVED that an appropriation from the officially adopted road fund budget and based on the County
Engineers estimate, is hereby made in the amounts and for the purposes shown:
il
ua Fredrickson, P.E.
. County Engineer
THIS PROJECT IS INCLUDED IN THE OFFICIALLY ADOPTED 2024 ANNUAL ROAD PROGRAM AS
ITEM NO. 8
THIS PROJECT IS HEREBY MADE A PART OF THE OFFICIALLY ADOPTED ANNUAL ROAD PROGRAM PROJECT
IN ACCORDANCE WTH RCW36.81.130
IT IS FURTHER RESOLVED THAT:
X THE CONSTRUCTION IS TO BE ACCOMPLISHED BY WTH RCW 36.77.020 ET.SEQ
THE CONSTRUCTION IS TO BE ACCOMPLISHED BY
wAc 136-18.
CE WTH RCW 36.77.065 AND
ADOPTED this 3rd day of October, 2023.
BOARD OF UNTY
Cory Wright, Chair
PURPOSE AMOUNT TOTALS
PRELMINARY ENGINEERING 150 000
CONSTRUCTION ENGINEERING $ 50,000
$RIGHT-OF-WAY ACQUISITION
SUB-TOTAL $ 200,000
County Forces coNsrRucloN $
CONTMCT CONSTRUCTION $ 250,000
SUB-TOTAL $ 250,000
TOTAL PROJECT COST $ 450,000
GRANT OR OTHER FUNDS $ 450,000
Grant Source: HSIP
TOTAL COUNTY ROAD FU ALLOCATION $0