DEPARTMENT OF PUBLIC WORKS
AGENDA STAFF REPORT
AGENDA DATE: October 3, 2023
ACTION REQUESTED: Request to Approve a Resolution initiating County Road
Project designated as CRP NO: 319-23, Horizontal Curve
Safety Project.
BACKGROUND: Kittitas County has been selected to receive $450,000 from
the Highway Safety Improvement Program (HSIP) for the
Horizontal Curve Safety Project. Roads that include
horizontal curves have been identified as high risk by the
2023 Safety Plan as well as past safety plans. Kittitas County
will benefit by collecting roadway horizontal curve data to
identify roads in need of crash prevention measures. This
grant funding will allow location selection and
implementation of improved roadside signing including
advisory speeds, LED chevrons/arrow signs, and addition
carsonites safety posts to increase driver awareness, which
can help reduce injuries on the road system.
HSIP funding is through the Washington State Department
of Transportation (WSDOT). The award does not require
matching local funds if design and construction are
authorized prior to April 30, 2026.
To meet the requirements of the program the project needs
to be initiated as a county road project and needs to be added
to the WSDOT Statewide Transportation Improvement
Program.
INTERACTION: Public Works
RECOMMENDATION: Approve a Resolution initiating County Road Project
designated as CRP NO: 319-23, Horizontal Curve Safety
Project.
HANDLING: Return one (1) original to Public Works
ATTACHMENTS: Resolution
LEAD STAFF: Josh Fredrickson, County Engineer
RESOLUTION NO.
BEFORE THE BOARD OF COUNTY COMMISSIONERS OF KITTITAS COUNTY, STATE OF WASHINGTON, in the matter
of initiating a county road project designated as:
CRP NO: 319-23 JOB NO: RC2298-HP
IT IS HEREBY RESOLVED that the Horizontal Curve Safety Project be as follows:
The project will collect data and install/upgrade signing for horizontal curves (such as advisory speeds, chevrons,
delineation).
VARIOUS LOCATIONS COUNTYWIDE
This project is hereby declared to be a public necessity and the County Engineer is hereby ordered and authorized to report and
proceed thereon as by law provided. (RCW 36.75.050, 36.80.030, 36.80.070).
IT IS FURTHER RESOLVED that an appropriation from the officially adopted road fund budget and based on the County
Engineers estimate, is hereby made in the amounts and for the purposes shown:
1 OR
❑■
W
101
PURPOSE
AMOUNT
TOTALS
PRELMINARY ENGINEERING
$ 150,000
TION ENGINEERING
$ 50,000
WAY ACQUISITION
$
Z
U250,000
rces CONSTRUCTION
$
CONTRACT CONSTRUCTION
$ 250,000
SUB -TOTAL
TOTAL PROJECT COST
$ 450,000
GRANTOR OTHER FUNDS
450,000
Grant Source: HSIP Is
TOTAL COUNTY ROAD FUND ALLOCATION
$ 0
oshua Fredrickson, P.E.
County Engineer
THIS PROJECT IS INCLUDED IN THE OFFICIALLY ADOPTED 2024 ANNUAL ROAD PROGRAM AS
ITEM NO. 8
THIS PROJECT IS HEREBY MADE A PART OF THE OFFICIALLY ADOPTED ANNUAL ROAD PROGRAM PROJECT
IN ACCORDANCE WITH RCW 36.81.130
IT IS FURTHER RESOLVED THAT:
THE CONSTRUCTION IS TO BE ACCOMPLISHED BY CONTRACT IN ACCORDANCE WITH RCW 36.77.020 ET.SEQ.
THE CONSTRUCTION IS TO BE ACCOMPLISHED BY COUNTY FORCES IN ACCORDANCE WITH RCW 36.77.065 AND
WAC 136-18,
ADOPTED this 3rd day of October, 2023.
BOARD OF COUNTY COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
Cory Wright, Chair
Brett Wachsmith, Vice -Chair
Attest:
Clerk of the Board
Laura Osiadacz, Commissioner
g:\baseXformskengkcrp-frm
9/26/2023