HomeMy WebLinkAboutCOP 4CHANGE ORDER NO.004 PROJECT NAME: KITTITAS BLOOM PAVILION ADDITION OWNER: KITTITAS COUNTY CONTRACTOR: CONCORD CONSTRUCTION, INC PROJECT NO: 2018-051 PAGE 1 of 1 DESCRIPTION OF CHANGE: COP #09 - MDP Breaker COP #10 - Temp Electrical Panel COP #11 - RFI's 43 &44 Site Grading and Drywell Revisions COP #12 - RFI 42 Swine Barn Siding COP #13 - Remove & Dispose Unknown Concrete Footing COP #14 - Remove & Dispose existing concrete foundation Original Contract Sum $1,577,400.00 Net Amount of Previously Approved Changes: $74.947.63 Contract Sum Prior to This Change Order: $1,552,347.63 Contract Sum is Increased by This Change Order: $22.052.24 Revised Contract Sum: $1,674,399.87 Original Contract Completion Date: 5/18/2024 Previously Approved Increases in Time: -0- Completion Date Prior to This Change Order: 5/18/2024 Contract time will be INCREASED by 0 Calendar Days This Change Order Revised Substantial Completion Date: 5/18/2024 Revised Final Acceptance Date: 5/18/2024 Amount $ 3.454.81 $ 3.391.26 $ 12,120.05 $ 1,000.96 $ 1,508.81 $ 576.35 Total This Change Order: $ 22,052.24 Accepted by Contractor: Concord CgAstruction, Inc. Date Recommended By: ALSC Architects, P.S. By Date�2/�2 Approved by Owner: By: Date j i j I . i I ' 0 C, 0 co,o m2— m m ao -n co m J p i J O i F- , i F � �; OJ V V `rr M cq (D � W p O i O M r co c7 c`) r C It F co i c7 vi c7 c7 m to O O O O 0 C) O O O O O O 0 0 O O O O O O f0 f0 (0 O n0 N Z m O O O Q J O O o 3 U 0 < C, C. o p 0 0 0 J o o E Q C J Q o Q F o fl O _ U H o O O O O O C 'o a 0 0 0 O O O m Q V O O O 47 M M o p o o'c O O C — C w N m U)IL Z5 O 0 o m o_ 06 � 7 0U 0 o C c7 �N1 J O V J O O N CO O 'J V w o N o U N r ca o: J lJ .� O J N o 0 N O o c °UH m ) m UF- otf Uo g Ud ro g o a>>I� mo O 7 a a) o c16 ` U O a m 7 r v 4a w a uEi i i w w 0z a N I a- m J c i f U ocL.i n l i j j n c W N 1! I j I Q x w I I I I I I O N m j Vw=j CL I I I 0 N J ~ ' i! ~ co c O I I i t CL N U I i U c w o U U m-2 ro W v O I I a m F- Qj N ) (`') N d I j i O� (—'m f , U cn a I 1 I 1 i d O I C > C f0 d N O w I 3 ♦ui - en — r �.I PHONE: 509-728-0417 I+Ax:509-494-$432 July 11, 2023 ELECTRICAL CHANGE ORDER TO: CONCORD CONSTRUCTION WAPATO, WA JOB: BLOOM PAVILION ELLENSBURG, WA ECOP 3 SUBJECT: MDP BREAKER ADDITION CB Electric is providing a change order proposal to provide and install 1 new 3P-200Amp breaker and associated hardware in the existing MDP panel to feed our new panel. The existing breaker that was supposed to be used was a 2P breaker and not the needed 3P. Material $ 2,598.00 Labor $ 132.00 P&OH: $ 423.00 Total ADD: $ 3,153.00 Exclusions: Sales tax, performance bond, excavation, bedding, backfill concrete & asphalt cutting & patching. WWW.CBELECTRICYAKIMA.COM PO BOX 8056 YAKIMA, WA 98908 LIC # CBELEEL861PS 7/11/2023 2:22:44 PM Page 1 BLOOM PAVILION MDP BREAKER Totals (Summary) - Bid Summary: Default Material Non -Quoted Quotes Sales Tax (0.50%) Total Material Labor Direct (1.32 hours @ $100.00) Non -Productive Labor Total Labor (1.32 hours) Direct Job Expenses Tools and Miscellaneous Materials Subcontracts Job Subtotal (Prime Cost) Overhead (10.00%) Profit (5.00%) Job Total Actual Bid Price Material to Direct Labor ratio: 0.95 Prime Cost per square foot Job Total per square foot Actual Bid Price per square ft Labor cost per square foot Labor hours per square foot Gross Profit % Gross Profit $ Net Profit % $2,585.00 0.00 12.93 $2,597.93 $132.00 0.00 $132.00 $0.00 0.00 0.00 $2,729.93 272.99 150.15 $3,153.07 $3.153.07 $0.00 $0.00 $0.00 $0.00 0.00 13A2 $423.14 4.76 7/11/2023 2:20:53 PM BLOOM PAVILION MDP BREAKER Job Number. 1000015583 Extension By Phase Item # Description Quantity Price U — 03 Above Ground Feeder Raceway — 4164 200A 3P Bolt -On Circuit Breaker 1 2,585.00 E — 03 Above Ground Feeder Raceway Total — Job Total Target, Labor column 2 Page 1 Ext Price Labor Hr U Ext Lab Hr 2,585.00 1.32 E 1.32 2,585.00 1.32 2,585.00 1.32 Mo 00 O O O O 66p I® lop. EIe-<�. Pe.,ticj 0 00 O NO 00 nCco ?lC N N c[7 LO cn 0 o 0 O N (O - rn mco co co In co rn w O N N N N c7 c") M M co M co m O O O O O O _ O O O 9 � 0 0 0 0 O O Q C J O Q U 7 Q in ~ O O! 0' Imui cn O O a:_ C7 ch �� 7: c9 T o c o 10,, N 0 0 cl c $ m �� c�oOB U' C7lnU) -jao0m LO 01 M N N a July 22, 2023 PHONE: 509-728-0417 FAX:509-494-8432 ELECTRICAL CHANGE ORDER TO: CONCORD CONSTRUCTION WAPATO, WA JOB: BLOOM PAVILION ELLENSBURG, WA ECOP 4 SUBJECT: TEMP CERT OF OCCUPANCY CB Electric is providing a change order proposal to provide and install a new 200 Amp Main Lug Load Center with 12 1 P-20A breakers. We will be temporary hooking up 3 new plug circuits, 2 new lighting circuits, 4 exhaust fan circuits, and 1 exterior lighting circuit. Material $ 774.00 Labor $ 1,892.00 P&OH: $ 429.00 Total ADD: $ 3,095.00 Exclusions: Sales tax, performance bond, excavation, bedding, backfill concrete & asphalt cutting & patching. z/� WWW.CBELECTRICYAKIMA.COM PO BOX 8056 YAKIMA, WA 98908 LIC # CBELEEL861PS 7/241202312:19:34 PM Page 1 BLOOM TEMPORARY POWER TO OPEN Totals (Summary) -Bid Summary: Default Material Non -Quoted Quotes Total Material Labor Direct (18.92 hours @ $100.00) Non -Productive Labor Total Labor (18.92 hours) Direct Job Expenses Tools and Miscellaneous Materials Subcontracts Job Subtotal (Prime Cost) Overhead (10.00%) Profit (5.00%) Sates Tax (0.50%) Job Total Actual Bid Price Material to Direct Labor ratio: 0.29 Prime Cost per square foot Job Total per square foot Actual Bid Price per square it Labor cost per square foot Labor hours per square foot Gross Profit % Gross Profit $ Net Profit % $773.88 0.00 $773.88 $1,892.00 0.00 $1,892.00 $0.00 0.00 0.00 $2,665.8B 266.59 146.62 15.40 $3.094.49 $3,094.49 $0.00 $0.00 $0.00 $0.00 0.00 13.85 $428.61 5.24 7/24/2023 12:20:01 PM BLOOM TEMPORARY POWER TO OPEN Job Number: 1000015592 Extension By Phase Item # Description Quantity Price U - 01 Underground Feeder Raceway - 1001 3/4" EMT 4 120.75 C 1437 314" Set Screw Steel Conn 8 171.88 C 1502 2-1/2" Comp Steel Insul Throat Conn 2 18.39 E 1557 3/4" Set Screw Steel Cplg 0 74.75 C 2279 3/4" 1-Hole Strap 1 17.25 C - 01 Underground Feeder Raceway Total - - 02 Underground Branch Raceway - 2790 #12 THHN CU Stranded Wire 13 224.23 M - 02 Underground Branch Raceway Total - - 03 Above Ground Feeder Raceway - TEMP 200 Amp Surf Load Center-Nema 1 1 506.00 E - 03 Above Ground Feeder Raceway Total - -09Trim - 54646619 200 AMP PANEL DEMOLITION 1 11.50 E - 09 Trim Total - - 13 Rough -In - 19444 3/4" GRC Coupling 5 338.05 C -13 Rough -In Total - - 18 Misc. - 54655091 2 1/2" GRC COUPLING 1 30.48 E T0001 REMOVE PIPES AND CIRCUITS 1 0.00 E T0003 200 AMP PERMIT 1 150.42 E -18 Misc. Total - Job Total Nay ' Target, Labor column 2 Page 1 Ext Price Labor Hr U Ext Lab Hr 4.83 2.70 C 0.11 13.75 0.07 E 0.56 36.78 0.46 E 0.92 0.30 0.07 E 0.03 0.09 2.63 C 0.01 55.75 1.63 2.83 6.33 M 0.08 2.83 0.08 506.00 9.78 E 9.78 506.00 9.78 11.50 4.03 E 4.03 11.50 4.03 16.90 0.07 E 0.35 16.90 0.35 30.48 0.17 E 0.17 0.00 2.88 E 2.88 150.42 0.00 E 0.00 180.90 3.05 773.88 18.92 co 00 Cl) C) (0 N C\j co N U') LD C'I 8 C4 C) r*.: U� O� C! W C) W M cl 7 U� P P; %n 06 (,o "i cy) r- 00 o o 0 (1) �2 m�r (CO4 rc-:) cR 003 ro-o- Em < 0 rq LO �2 �2 LO LO tr) to to 0 o r-i o CD 1 N 0 U� 000 00 O Ce) 'n z CC tr) to o CC 0 CL -j =� lu), (n U) rn U) TJ a c, C) CD C) R C� R 1 9 C.� 0 0 0 J 0 CD I F- C) 0 0 13 00 0 00 0 c; co CM D cn co w c3i o CW (n �r 'T LU @) z M U. u CIA ca E 2 V U') LO 3:� tf'U) c 0 (A CO Ci co M e — 0 0' 0 c M CC) cu 0 eo a E2 x (a) ca '2 C) > Ef) CC In 0 -1 ca :W 03;o: -j C) L.1v 0 ID 81.6 o C U m co c C:.Q .13 La oad 0 F- ca ~ C) C7 U) (2) !,-j M CO -6 CO 20 M .6 coin D C3 (a li to o w E (1) o w .0 r w 0 4 CL 0 z --T a C (D > 4) ILI CL LU 0 z 1110 m 0 T-, m Oa_ E - M 0. Lo 0 -j X 32 L) w U) tm tw: Q. LU LU W! I ID (D U) cn c LU in > 0 f2 I U) 0 LLJ LU 2 M a N Cn C r 00 1 O CO O) O M CD m O CO O O CO c 0 u� 0 0 O O O V D u) O u) O [- 10 p N N J (n ¢ V M M V C7 m co N 7 0 0 0 0 CO 10 V ri co LL9 O d• N 00 Vk 000pOpoaOOOOOOOOOoo rn o0 m cl)) U) 0 0 N o CO 0 m Z J O O 0 0 0 oo 0 0 o 0) 0 0 0 0 0 F zg co co co A N C .- O '••H F- Y Z ^� 0 0 1� n. ¢ W y o ~ O 2 0 2 2 N xw a�Q3O0f- w O m����¢� O O Z �ry7 O— w~ m o N N 0 0 0 0 0 O O O O _ Y co M M Lo V M N pOj �.:� NFw2Un~o c m w v m Z U U J g wpm Q ZeawZ%d� r ww20U0 O a ❑ OCU W dOw F. Z) U) �o�- aaa� V) ca uj n 3 C) W U J J W lL lL LL c w a f- Fam000 Um0 O J J J w F a m v nm co 000 D w U) ►-ram rn � a UJo 00 00000 c to r- Q ui o ui o� o 6 o �Oa) 6 ui N d, r -a a R _ Za rn c Z)w rnCl) O ClY 000Opm O N V O Cl! - N X m CD co r-avr-Unm0 u)N r,Oh 0 o ct: a 0 N V m 3 F- F- N N E �mmmmmmxo��� � T�c R n � w tL w x w z @ 0 o Q _ o � w e a c C< d a y � _ aQ o R o 1 C w wNN $S a N z a m > a = J O v a y U c c on O c t m ao s V) m Z E g N o O cYa. d,e dY co CL UJ 211 2 Ea a� Z _ ky ii W w .D O (n n Y 7 � d a) D 7 j H Ua oMCD 0 -jNO O CO t0 �a�o6 m O Z COST ESTIMATE DETAIL SHEET COP No. 12 RFI 42 - Svnne Barn Siding PROJECT: Kittitas County Bloom Pavilion Addition CONTRACTOR: Concord Construction, Inc. UNIT COSTS ITEM DESCRIPTION QTY UNIT EQUIP MTL Labor EQUIP MATERIAL LABOR TOTAL 1 Demo & dispose of existing siding 80 If 0.00 0.38 2.21 0.00 30.40 176.80 207.20 2 Install treated 2x12 edge form/base 80 If 0.00 4.09 3.32 0.00 327.20 265.60 592.80 0.00 0.00 0.00 0.001 357.60 442.40 800.00 Paid Medical Leave 2.5% 012025 11.06 11.06 Subtotal 811.06 Small Tools 5% of Labor 22.12 Subtotal 833.18 Health & Safe 2% of Labor 8.85 SubtotalM842.031Contractors Mark Up @ 15% SubtotalSubcontnetors:UNIT COSTS ITEM DESCRIPTION QTY UNIT SUB MTL Labor SUB MTL Labor00 0.00 0.00 0.00 0.00 0.00 Contractors OH & P @ 6% on Subcontractor Subtotal General Contractor Subtotal: 968.33 Subcontractor Subtotal: Subtotal: 968.33 Liability Insurance 1.7% 16.46 Bonds 1.17% 11.33 B & O Taxes @ 0.5 % 4.84 ubtotal 1, 00. TOTAL ADD: 1,000.99 Page 1 COST ESTIMATE DETAIL SHEET COP No. 13 Remove and Dispose Unknown E)d PROJECT: Job No. 2203 - IGttitas County Blaom Pavilion Addition Concrete Footing Between Bloom Addition CONTRACTOR: Concord Construction, Inc. and Swine Bam that Conflicted whew 8" Sewer Line UNIT COSTS ITEM DESCRIPTION QTY UNIT EQUIP MTL Labor EQUIP MATERIAL LABOR TOTAL 0,00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Paid Medical Leave @ 2.5% 012025 0.00 Subtotal Small Tools @ 5 % of Labor Subtotal Health &Safety 2 % of Labor Subtotal Contractors Mark Up @ 15% Subtotal Subcontractors: UNIT COSTS ITEM DESCRIPTION QTY UNITI SUB MTL Labor SUB MTL Labor TOTAL 1 Kemoved and sposeci o yer s o concre e that was in the way of the 8" sewer line between Bloom Pavilion Addition and Swine Bam, Hyatt Excavating 1 s/c 1377 0 0 1 1377.00 0.00 0.00 1,377.00 1377.001 0.00 0.00 1377.00 Contractors OH & P 6% on Subcontractor 82.62 Subtotal 1,459.62 General Contractor Subtotal: Subcontractor Subtotal: 1,459 62 Subtotal: 1,459.62 Liabili Insurance 1.7% 24.81 Bonds 1.17% 17.08 B & O Taxes @ 0.5% 7.30 u tota 1, 8. 1 TOTAL ADD: 1,f,06.81 Page 1 cop 14 4 51a�5 W.0 .2 o C:) o 0 0 C3 C) (D 0 0 0 C) p p 0000 0 n co 0 -i C) CD CD C3 < (:� q q 9 EE 0 0 C5 0 w 0 0 C) 0 co ui o 10 0 o C� o 9 U) o N. cL U) > -I _j LO 0 F- 2---- O. - E2 'o 0 Z) a. o D 5 cumc: cr w m E w o CL U) r 0 tz 51— —1-1 -i _ 'L �c 0 z rn F- LU d) L'i w Cc,. rn LL w 4)2 > 2 0 (n 0 1 0 E a 0 CO w L) a: C) '6 i I — NO W O [D `. - •- 7 W h VI N? In N a -U 0 0 N O O O C O O O G O O O O O O C O 0 m D c U) _ O 7 V)Q vNi ep _amw z1 000 2 UO a•:-d -7 W Zt/10 -2U ww <C!-5j U 2 I" C a K lox 4 W0 vo F Q G U J zoawZLLa(n F o�aoao O F �QmmmUWL y m W N W J V J vyr rQm000 O m m' FHI- a m W > > 000 0 0 0 U C r h 0 O N D ` < z� O Dw rn o � nl n �n U C O V C � v m gN o a _N � H t � j v 2 o o N c N a � 2 J d 0 v C m M N h W O W W F W o � _ a n aN Z O O O C C m a w e r Q a o C a 9 W X Q = A O U C w W O N Q Z m 'i> Q = 4a = � o U o E y m IL $ t m N O o Y C aF r>jCU wv 0W g 3, 4) w ') = C U W x W JEOUG W F G p> Lo0 Z. SHAWN HYATT EXCAVATING, INC. DAILY JOB LOG Date: A a o 3 Job Name: Now PcIvt'I,-Oh Extra Work Performed: D-q (A()(AO�). G(My�a jkIP1d 0-9CAVI C({ e —I-j f Equipment Used: Equipment/Labor Hours ws excgyc AO r Materials Used: Notes; f1 w► <c� S Authorized Signature: KITTITAS COUNTY SOLID WASTE 925 INDUSTRIAL WAY ELL•ENSBURG, WA 98926 (509)962-7542 R E C E I P T Bill Acct:TEMPi23 TEMP 123 Account Haul Acct:TEMP123 TEMP 123 Account SITE:RY Ryegrass Landfill DATE:08/07/23 TICKET03017819 TIME IN:02:03 PM ID IN:TDW TIME OUT:02:03 PM ID OUT:TDW TRUCK:TEMP1 PO: ------------------------------------- LBS TONS GROSS: 0 0.00 TARE: 0 0.00 NET: 0 0.00 VOL: 4 ------------------------------------- MATERIAL:Concrete RATE: 15.00/CY TIP FEE: 60.00 SPEC FEE: 0.00 TAX FEE: 2.16 TOTAL FEE: 62.00 Darren NOTE:Darren Shawn Hyatt 4 yrds of con *****Reprint***Reprint*-***