HomeMy WebLinkAboutStaff Report for 2-7-23 Fee Hearing
COMMUNITY PLANNING BUILDING INSPECTION PLAN REVIEW ADMINISTRATION PERMIT SERVICES CODE ENFORCEMENT
KITTITAS COUNTY COMMUNITY DEVELOPMENT SERVICES
411 N. Ruby St., Suite 2, Ellensburg, WA 98926
CDS@CO.KITTITAS.WA.US
Office (509) 962-7506
Fax (509) 962-7682
“Building Partnerships – Building Communities”
February 7, 2023
To: Board of County Commissioners
From: Dan Carlson, AICP
Community Development Services Director
RE: Proposed 2023 Community Development Services Fee Schedule Staff Report
Introduction
Staff has updated the Community Development Services (CDS) fee model with current department staff,
expenditures, and valuation data to determine the proposed CDS fees for 2023. These fees are divided
into three categories – Building Permit Fees for New Construction (Exhibit A & B), Fees for Building
Fixtures (Exhibit C), and Fees for Planning Services (Exhibit D).
Building Permit Fees for New Construction
Building permit fees for new construction would continue to be determined based upon a multiplier
(Exhibit A), a model enabling the user to determine how much service will cost for plans examination and
building inspection given total construction valuation for the project. This multiplier is based upon the
International Code Council (ICC) suggested model, and upon the most current published Building
Valuation Data table of the International Code Council Building Safety Journal (Exhibit B). This is a
national “average” construction cost per square foot for new construction. This fee model simplifies the
permit cost process and includes foundation work, structural and non-structural components, plumbing,
mechanical and interior finish. The ICC model allows CDS to adjust permit fees based on annual
construction activity and the desired level of service determined by the Board of County Commissione rs.
The multiplier works as follows:
• Projected gross construction valuation for the coming year is divided into the projected budget for
the coming year to create a multiplier.
• The multiplier is then used against the square foot cost of the construction project estimated by
using the most current August issue of the Building Safety Journal Building Valuation Data sheet
published by the International Code Council (Exhibit B).
• This produces a permit fee adequate to process the building permit. This cost includes all
plumbing and mechanical associated with new construction.
• A five percent (5%) technology and equipment surcharge is added to permit fees to cover the
cost of repair and replacement of vehicles and equipment needed to service the building permits.
Between September 30, 2019 and September 30, 2022, the average annual construction valuation within
Kittitas County was $190,691,601. Staff used this number for the projected gross construction valuation
for 2023. The anticipated building division budget after removing individual fee revenues is $1,293,146.
The $190,691,601 annual construction valuation is divided into the anticipated $1,293,146 budget, which
produces a multiplier of 0.0068. This multiplier is then applied to the construction project valuation to
determine the building permit fee.
Example:
Using the lCC Building Safety Journal Building Valuation Data ($166.08/square foot), the valuation for a
2,000-square foot residence would be $332,160 (2,000 x $148.33). The project valuation of $332,160
would be multiplied by the proposed multiplier of .0068, equaling a base building permit cost of
$2,258.69. A five percent (5%) technology and equipment surcharge is placed upon the fee and a $150
issuance fee would be applied, for a total permit fee of $2,521.63. For comparison, the 2022 building
permit fee for the same 2,000-square foot residence would be $2,445.04 (Current multiplier is .0074;
current valuation data for a single-family residence is $148.33/square foot; and current issuance fee is
$140.00).
Fees for Building Fixture Permits
Building permit fees for stand-alone building fixture permits are determined using the fee model for cost
recovery of permit review and processing. This fee schedule applies when someone remodels, requests
individual appliance replacement, or desires miscellaneous work requiring a permit and inspections not
associated with new construction. Some construction activity permit fees can only be computed on an
estimated, hourly basis for permit intake, plan review and inspections. Examples of this would be
structural modifications to cell towers, fire damage repair and replacement, etc. For each permit type,
staff has provided the current fee, the cost of service per the fee model, and a suggested fee for 2023
(Exhibit C).
Fees for Planning Services
Fees for Planning Services are also determined using the fee model for cost recovery of land use
application review and processing. This fee schedule applies to such land use applications as plats,
conditional use permits, shoreline reviews, State Environmental Policy Act (SEPA) reviews, variances,
etc. A new fee has been added for the Public Agency and Utility Exception that was adopted with the
new Critical Areas Ordinance in 2021 but a fee had not yet been adopted. Additionally, Critical Areas
Pre-Determination and Determination fees have been proposed for 2023. A pre-determination would be
a service provided by the county to help landowners and applicants determine the extent that critical
areas affect individual properties or apply to a proposed project. A determination would be similar but it
would be received and reviewed at the same time as an underlying building permit or land use
application. The pre-determination and determination fees would be implemented when the county fills
the new Biologist position. For each application type, staff has provided the current fee, the cost of
service per the fee model, and a suggested fee for 2023 (Exhibit D).
Recommendation
Staff recommends that the Board of Commissioners approve the proposed CDS 2023 fee schedule as
shown in the attached Exhibits A, B, C, and D.
Attachments: Exhibit A: Building Permit Fee Multiplier Model
Exhibit B: lCC Building Safety Journal Building Valuation Data
Exhibit C: Proposed Fees for Building Fixtures
Exhibit D: Proposed Fees for Planning Services
Exhibit A
Building Permit Multiplier Model
Exhibit B
lCC Building Safety Journal Building Valuation Data
Exhibit C
Proposed Fees for Building Fixtures
Fees for Building Fixtures Current Fee Cost of Service Suggested Fee
[Bldg] Permit Issuance Fee $140.00 $147.00 $150.00
[Bldg] One-time Application / Permit Extension Fee $70.00 $73.00 $70.00
[Bldg] Misc - Foundation Only Permits $730.00 $746.00 $750.00
[Bldg] Misc - Fences over 7-foot high $500.00 $511.00 $510.00
[Bldg] Misc - Woodstove/Fireplace/Free Standing Stove $150.00 $287.00 $150.00
[Bldg] Misc - Modular Buildings (per sq. ft.) (Based on
2300 sq ft)
$1,150.00 $1,174.00 $1,170.00
[Bldg] Misc - Manufactured Homes (per sq. ft.) (Based
on 1800 sq ft)
$710.00 $726.00 $730.00
[Bldg] Misc - Demolition $280.00 $216.00 $220.00
[Bldg] Misc - Move Structure (per sq. ft.) (Based on
1800 sq ft)
$870.00 $889.00 $890.00
[Mech/Plum] Furnaces - Forced-air furnace or burner $280.00 $143.00 $140.00
[Mech/Plum] - Suspended heater, recessed wall heater
or floor-mounted unit heater
$280.00 $285.00 $280.00
[Mech/Plum] Appliance Vents $30.00 $36.00 $40.00
[Mech/Plum] Plenum Repairs or Additions $280.00 $285.00 $280.00
[Mech/Plum] Boiler $280.00 $143.00 $140.00
[Mech/Plum] Air handling unit $210.00 $143.00 $140.00
[Mech/Plum] Air Conditioning Unit - or Mini-Split
System
$280.00 $143.00 $140.00
[Mech/Plum] Ventilation fan connected to a single duct
(each)
$30.00 $36.00 $40.00
[Mech/Plum] Ventilation system which is not a portion
of any heating or air-conditioning system
$70.00 $71.00 $70.00
[Mech/Plum] Hood which is served by mechanical
exhaust, including the ducts for such hood
$420.00 $214.00 $210.00
[Mech/Plum] Incinerators - Domestic-type $280.00 $285.00 $280.00
[Mech/Plum] Incinerators - Commercial or Industrial-
type
$420.00 $428.00 $430.00
[Mech/Plum] Misc - For each appliance or piece of
equipment regulated by the Mechanical Code but not
classed in other appliance categories, or for which no
other fee is listed in the table
$70.00 $71.00 $70.00
[Mech/Plum] Misc - Each plumbing fixture on one trap
or a set of fixtures on one trap
$70.00 $71.00 $70.00
[Mech/Plum] Misc - Each Hot Water Heater-Electric $70.00 $71.00 $70.00
[Mech/Plum] Misc - Each Hot Water Heater-Gas $140.00 $143.00 $140.00
[Mech/Plum] Misc - Orifice change outs (each) $140.00 $143.00 $140.00
[Mech/Plum] Misc - Gas Piping System of one to five
outlets
$140.00 $143.00 $140.00
[Mech/Plum] Misc - Additional gas piping system outlet
(each)
$70.00 $71.00 $70.00
*Agricultural Building $800.00 $813.00 $810.00
Re-roofing $260.00 $137.00 $140.00
*In ground Pool/Spas & Hot Tub Permit $670.00 $689.00 $690.00
*Above ground Pool/Spas & Hot Tub Permit $110.00 $113.00 $110.00
*Residential Solar Panel Building Permit per roof face
or rack.
$280.00 $278.00 $280.00
*Commercial Solar Panel Building Permit per roof face
or rack system.
$530.00 $547.00 $550.00
*Residential Wind Turbine $260.00 $265.00 $260.00
*Commercial Wind Turbine $350.00 $350.00 $350.00
Lifting of Stop Work Order $280.00 $278.00 $280.00
Lifting of Notice to Title $460.00 $460.00 $460.00
*For any permit fee which is not listed above fees may
be determined by an hourly basis of $140.00 per hour
review and inspection, by square foot valuation or by
bid amount, determined by Community Development
Services.
*Fees for printing shall be by fee recovery schedule set
by CDS.
Exhibit D
Proposed Fees for Planning Services
Fees for Planning Services Current Fee Cost of Service Suggested Fee
Pre Application or Pre Submission (Per Meeting) $600.00 $658.00 $660.00
Accessory Dwelling Unit $1,460.00 $1,571.00 $1,570.00
Binding Site Plan $1,920.00 $2,072.00 $2,072.00
Boundary Line Adjustment $760.00 $812.00 $810.00
Comp. Plan Amendment (Text) $3,240.00 $3,531.00 $3,530.00
Comp. Plan Amendment (Map) $3,530.00 $3,851.00 $3,850.00
Large Lot $1,950.00 $2,103.00 $2,100.00
Parcel Combination $560.00 $599.00 $600.00
Cluster Plat - 5 or more lots $2,910.00 $3,147.00 $3,150.00
Cluster Plat - 4 or less lots $2,160.00 $2,337.00 $2,340.00
Plat Extension $560.00 $599.00 $600.00
Short Plat $2,160.00 $2,337.00 $2,340.00
Preliminary Plat $2,960.00 $3,190.00 $3,190.00
Final Plat $970.00 $1,046.00 $1,050.00
Final Short Plat $780.00 $854.00 $850.00
Short Plat Amendment $2,360.00 $2,550.00 $2,550.00
Plat Amendment $2,960.00 $3,190.00 $3,190.00
Public Benefit Rating System Application $2,300.00 $2,300.00 $2,300.00
Public Facilities $2,150.00 $2,316.00 $2,320.00
Planned Unit Development $4,330.00 or
Dev.
Agreement
$4,683.00 $4,680.00
Rezone $3,420.00 $3,702.00 $3,700.00
*SEPA $600.00 $2,529.00 $600.00
SEPA Optional $600.00 $2,529.00 $600.00
Shoreline Setback Variance $3,710.00 $4,001.00 $4,000.00
Shoreline Substantial Development $2,210.00 $2,380.00 $2,380.00
Shoreline Conditional Use $3,710.00 $4001.00 $4,000.00
*Shoreline Exemption $560.00 $599.00 $600.00
Sign $150.00 $823.00 $150.00
Small Wind Energy Bldg. Fee $172.00 Bldg. Fee
Transfer of Development Rights $200.00 $865.00 $200.00
Wind Farm Siting Dev.
Agreement
$3,999.00 Development
Agreement
Zoning Variance $1,850.00 $1,996.00 $2,000.000
Administrative Conditional Use Permit $2,660.00 $2,870.00 $2,870.00
Administrative Conditional Use Permit
Amendment
$2,460.00 $2,657.00 $2,660.00
Administrative Determination $740.00 $831.00 $830.00
Appeal $1,550.00 $1,674.00 $1,670.00
Conditional Use Permit $3,170.00 or
Dev.
$3,426.00 $3,430.00
Agreement
Conditional Use Permit Amendment $3,060.00 $3,297.00 $3,300.00
Development Agreement $790.00 $875.00 $880.00
Title Elimination $130.00 $131.00 $130.00
Preliminary Site Analysis $150.00 $158.00 $160.00
Pre-application Conference Waiver $120.00 $129.00 $130.00
Reasonable Use Exception $1,850.00 $1,996.00 $2,000.00
Public Agency and Utility Exception N/A $1,996.00 $2,000.00
Critical Areas Pre-Determination N/A $339.00 $340.00
Critical Areas Determination N/A $339.00 $340.00
*Shoreline Exemption and SEPA review fees not required for fish habitat projects developed and implemented through the Volunt ary
Stewardship Program (VSP).