HomeMy WebLinkAboutResolution_CookeCanyonRoad_ProspectusKITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
AGENDA STAFF REPORT
AGENDA DATE: September 6, 2022
ACTION REQUESTED: Request to Approve a Resolution Authorizing the Chair's
Signature on the Local Agency Federal Aid Project
Prospectus for the Replacement of Bridge No. 80181 on
Cooke Canyon Road over the Hiline Canal CRP 315-22.
BACKGROUND: On July 14, 2022, Kittitas County Public Works was
advised that our Cooke Canyon Road — Hiline Canal bridge
replacement project was selected to receive funding
through the federal Local Bridge Program.
This project will require a 13.5 percent match in local funds
for the engineering and design. If construction is authorized
before December 2025 there will be 100 percent federal
funding for eligible costs.
This Project Prospectus covers the Federal Funding for the
Preliminary Engineering phase of the project.
Public Works is preparing to solicit for design support in
the fall of 2022. It is anticipated that Public Works staff
will perform 50 percent of the Preliminary Engineering.
INTERACTION: Public Works
RECOMMENDATION: Approve the Resolution Authorizing the Chair's signature
on the Local Agency Federal Aid Project Prospectus for the
Replacement of Bridge No. 80181 on Cooke Canyon Road
over the Hiline Canal.
HANDLING: Return two (2) originals to Public Works
ATTACHMENTS: Resolution, Local Agency Federal Aid Project Prospectus
LEAD STAFF: Josh Fredrickson, County Engineer
BOARD OF COUNTY COMMISSII
COUNTY OF KITTITAS
STATE OF WASHINGTON
RESOLUTION NO. 2022 -
AUTHORIZING THE CHAIR'S SIGNATURE ON THE LOCAL AGENCY FEDERAL
AID PROJECT PROSPECTUS ENGINEERING PHASE FOR THE COOKE CANYON
ROAD BRIDGE #80181 OVER THE HILINE CANAL REPLACEMENT PROJECT CRP
315-22
WHEREAS: The Cooke Canyon Road Bridge No. 80181 Replacement Project was awarded
Federal Funding through the 2022 Local Bridge Program; and
WHEREAS: The federal funding will be used for the preliminary engineering phase to design,
develop and prepare construction plans and specifications for these
improvements; and
WHEREAS: In preparation to begin work, Kittitas County Public Works is requesting the
Washington State Department of Transportation release the federal funds for
preliminary engineering; and
WHEREAS: A Local Agency Federal Aid Project Prospectus must be executed by the Chair
of the Board of County Commissioners acknowledging the project has been
reviewed and is consistent with the County's comprehensive plan for community
development; and
NOW, THEREFORE BE IT RESOLVED that the Board of County Commissioners, in the best
interest of the public, does hereby approve the Chair's signature on the Local
Agency Federal Aid Project Prospectus for the Cooke Canyon Road Bridge
#80181 Over the Hiline Canal Replacement Project CRP 315-22.
DATED on this 6th day of September 2022, at Ellensburg, Washington.
Attest:
❑ Clerk of the Board- Julie Kjorsvik
❑ Deputy Clerk of the Board- Mandy Buchholz
BOARD OF COUNTY
COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
Laura Osiadacz, Chairman
Cory Wright, Vice -Chairman
Brett Wachsmith, Commissioner
��, Washington State
�I/ Department of Transportation
Local Agency Federal Aid
Project Prospectus
DOT Form 140-101 Previous Editions Obsolete
Revised 01/2022
Prefix
Route
( )
Date
8/29/2022
DUNS Number
01-020-2547
Federal Aid
Project Number
Local Agency(
CRP 315-22 / RC 2194 -BR
WSDOT 1
Use Only J
Federal Employer
Tax ID Number
91-601349
Project Number
`
Agency
CAAgency
Federal Program Title
Kittitas County Public Works
❑� Yes ❑ No
0✓ 20.205 ❑ Other Local Bridge Program
Project Title
Start Latitude N 47.0491650
Start Longitude W -120.385876°
Cooke Canyon over HiLine Canal
End Latitude N 47.049165°
End Longitude W -120.385876 -
-120.385876°Project
Project Termini From -To
Nearest City Name
Project Zip Code (+4)
0.24 0.24
Kittitas
98926-6637
Begin Mile Post
End Mile Post
Length of Project
Award Type
✓❑ Loral ❑ Local Forces ❑ State ❑ Railroad
0.24
0.24
0.00
Route ID
Begin Mile Point
End Mile Point
City Number
County Number
County Name
0.24
0.24
N/A
19
Kittitas
WSDOT Region
Legislative Districts)
Congressional Districts)
Urban Area Number
South Cenaal Region
13
g
Total
Local Agency
Federal Funds
Phase Start
Phase
Estimated Cost
Nearest Hundred Dollar
Funding
Nearest Hundred Dollar
Nearest Hundred Dollar
Date
Month Year
P. E.
317,800.00
42,900.00
274,900.00 10/2022
R/VV
Const.
2,405,200.00
2,405,200.00 8/2023
Total 2,723,000.00 142,900.00 2,723,000.00
Description of Existing Facility (Existing Design and Present Condition)
Roadway Width Number of Lanes
24 2
single span, structurally deficient, load posted concrete bridge
Description of Proposed Work
Description of Proposed Work (Attach additional sheet(s) if necessary)
Replace existing single span, structurally deficient, load posted concrete bridge with a longer, :single span,
prestressed concrete girder structure to meet current design standards and to improve the hydrc opening.
Local Agency Contact Person
Title
Phone
Darren Case
Construction Manager
509-962-7019
Mailing Address
City
Ellensburg
State
WA
Zip Code
98926
411 N. Ruby, Suite 1
By
Approving Authority
Project Prospectus
Title County Engineer Date 8/29/2022
Page 1
DOT Form 140-101 Previous Editions Obsolete
Revised 01/2022
Agency
Kittitas County Public Works
Project Title
Cooke Canyon over HiLine Canal
Date
8/29/2022
osed Work
1
all that Apply)
dway Width
Number of Lanes
ruction ❑Path/Trail
7FD�Newconstruction
q2-R
2tion
]
❑ Pedestrian / Facilities
❑ Parking
Z✓ Bridge
Geometric Design Data
Description
Crossroad
Arterial
❑ Principal Arterial
Federal
erial
=Rural
❑ Minor Arterial
❑ Urban
❑ Collector
Functional
E]ElMajor Collector
❑Rural
E] Major Collector
Classification
El F1Minor Collector
NHS
❑ Minor Collector
✓❑ Local Access
❑ Local Access
Terrain
❑✓ Flat ❑ Roll ❑ Mountain
❑ Flat ❑ Roll ❑ Mountain
Posted Speed
50
Design Speed
50
Existing ADT
268
Design Year ADT
268
Design Year
2022
Design Hourly Volume (DHV)
Performance of Work
Preliminary Engineering Will Be Performed By
Others
Agency
shared agency and consultant
50 %
50 %
Construction Will Be Performed By
Contract
Agency
contract
100 %
%
Environmental Classification ��J
❑ Class I - Environmental Impact Statement (EIS) ❑✓ Class II - Categorically Excluded (CE)
❑ Project Involves NEPA/SEPA Section 404 El Projects Requiring Documentation
Interagency Agreement (Documented CE)
❑ Class III - Environmental Assessment (EA)
❑ Project Involves NEPA/SEPA Section 404
Interagency Agreements
Environmental Considerations
work over irrigation canal will be performed while canal system is not in service between November and
April
Page 2
DOT Form 140-101 Previous Editions Obsolete
Revised 01/2022
Project Title Date
Agency Cooke Canyon over HiLine Can 8/29/2022
Krttitas County Public Works Y
Right of Way
✓� No Right of Way Needed ❑Right of Way Needed
* All construction required by the ❑ No Relocation ❑ Relocation Required
contract can be accomplished
within the existing right of way.
Utilities Railroad
❑ No utility work required ✓0 No railroad work required
✓� All utility work will be completed prior to the start ❑ All railroad
construction rlte contract mpleted prior to the start of
of the construction contract
❑ All utility work will be completed in coordination ❑ All the railroad work will be completed in coordination
with the construction contract with the construction contract
Description of Utility Relocation or Adjustments and Existing Major Structures Involved in the Project
Utilities will be required to temporarily relocate prior to the project and then install permanent after the
construction project.
FAA Involvement
Is any airport located within 3.2 kilometers (2 miles) of the proposed
Remarks
[:]Yes W✓ No
This project has been reviewed by the legislative body of the administration agency or agencies, or its
designee, and is not inconsistent with the agency's comprehensive plan for community development.
Agency
Date By Mayor/Chairperson
Page 3
DOT Form 140-101 Previous Editions Obsolete
Revised 01/2022