DEPARTMENT OF PUBLIC WORKS
AGENDA STAFF REPORT
AGENDA DATE: July 19, 2022
ACTION REQUESTED: Request to Approve the Resolution Authorizing the Chair's
signature on the Local Agency Federal Aid Project
Prospectus for the Vantage Highway Over Cascade Canal
(Bridge 89342) Replacement.
BACKGROUND: On January 4, 2022, Kittitas County Public Works was
advised that the Vantage Highway over Cascade Canal
(Bridge 89342) Replacement Project was selected to
receive funding through the Surface Transportation Block
Grant (STBG) Regional Federal Funds Program.
On July 11, 2022, Kittitas County Public Works was
notified that an additional $968,008.00 would be available
for the project through STBG if we presented the funding
package for construction no later than September 1, 2022.
Staff has scheduled to construct this project over the Winter
season of 2022 — 2023.
Public Works is preparing to solicit for construction in
August 2022. This requires the Local Agency Federal Aid
Project Prospectus to be signed and approved by the Chair
of the BOCC prior to sending to WSDOT for approval.
This Project Prospectus covers the Federal Funding for the
construction phase and needs to be approved by WSDOT
Local Programs prior to solicitation for bids.
INTERACTION: Public Works
RECOMMENDATION: Approve the Resolution Authorizing the Chair's signature
on the Local Agency Federal Aid Project Prospectus for the
Vantage Highway over Cascade Canal (Bridge 89342)
Replacement.
HANDLING: Return two (2) originals to Public Works
ATTACHMENTS: Resolution, Local Agency Federal Aid Project Prospectus
LEAD STAFF: Josh Fredrickson, County Engineer
BOARD OF COUNTY COMMISSIONERS
COUNTY OF KITTITAS
STATE OF WASHINGTON
RESOLUTION NO. 2022 -
AUTHORIZING THE CHAIR'S SIGNATURE ON THE LOCAL AGENCY FEDERAL
AID PROJECT PROSPECTUS CONSTRUCTION PHASE FOR VANTAGE HIGHWAY
OVER CASCADE CANAL (BRIDGE 89342) REPLACEMENT PROJECT CRP 2021-202
WHEREAS: The Vantage Highway Over Cascade Canal (Bridge 89342) Replacement Project
was awarded Federal Funding through the Surface Transportation Block Grant
Regional Funds Program (STBG); and
WHEREAS: The final plans, specifications and estimate are near completion; and
WHEREAS: In preparation to advertise the project for construction in August 2022, Public
Works is requesting the Washington State Department of Transportation to
release the Federal Funds for construction; and
WHEREAS: A Local Agency Federal Aid Project Prospectus must be executed by the Chair
of the Board of County Commissioners acknowledging the project has been
reviewed and is consistent with the agency's comprehensive plan for community
development; and
NOW, THEREFORE BE IT RESOLVED that the Board of County Commissioners, in the best
interest of the public, does hereby approve the Chair's signature on the Local
Agency Federal Aid Project Prospectus Construction Phase for Vantage Highway
Over Cascade Canal (Bridge 89342) Replacement Project CRP 2021-202.
DATED on this 19' day of July 2022, at Ellensburg, Washington.
Attest:
❑ Clerk of the Board- Julie Kjorsvik
❑ Deputy Clerk of the Board- Mandy Buchholz
BOARD OF COUNTY
COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
Laura Osiadacz, Chairman
Cory Wright, Vice -Chairman
Brett Wachsmith, Commissioner
Washington State
Adft
�AP Department of Transportation
Local Agency Federa� Aid
Project Prospectus
uvi Form iau-i vi Page 1
Revised 01/2022 Previous Editions Obsolete
Prefix
Route
( )
Date
7/15/2022
Federal Aid
Project Number
DUNS Number
01-020-2547
Local Agency
CRP 310-21 / RC2292
i WSDO y 1
Federal Employer
91-601349
Project Number
` Use Only J
Tax ID Number
Agency
CAAgency
Federal Program Title
Kittitas County Public Works
0 Yes ❑ No
❑✓ 20.205 ❑ Other
Project Title
Start Latitude N 47.0002
Start Longitude W 120.4414
Vantage Highway over Cascade Canal (89342) Replacement
End Latitude N 47.0002
End Longitude W 120.4381
Project Termini From -To
Nearest City Name
Project Zip Code (+4)
MP 5.17 MP 5.33
Ellensburg
98926-9559
Begin Mile Post
End Mile Post
Length of Project
Award Type
5.17
5.33
0.16
0 Local [:]Local Forces [:1State ❑Railroad
Route ID
Begin Mile Point
End Mile Point
City Number
County Number
County Name
94001
5.17
5.33
N/A
19
Kittitas
WSDOT Region
Legislative District(s)
Congressional District(s)
Area Number
South Central Region
13
8
LN/A
Total
Local Agency
Phase Start
Phase
Estimated Cost
Funding
Federal Funds
Date
Nearest Hundred Dollar
Nearest Hundred Dollar
Nearest Hundred Dollar
Month Year
P.E.
R/W
Const.
1,838,000.00
1,838,000.00
08/2022
Total
1
1
1,838,000.00
Description of Existing Facility (Existing Design and Present Condition)
Roadway Width
Number of Lanes
28
2
The existing bridge (no. 89342) along Vantage Highway spanning the Cascade Irrigation Canal requires
replacement. The existing bridge is currently load restricted and has recent damage from a vehicle accident.
Description of Proposed Work
Description of Proposed Work (Attach additional sheet(s) if necessary)
Replace existing bridge that is damaged and load rated with a new bridge, guardrail, and approaches that meet
WSDOT's current specifications for safety.
Local Agency Contact Person
Title
Phone
Darren Case
Construction Manager
509-962-7019
Mailing Address
City
StateZip
Code
411 N. Ruby, Suite 1
Ellensburg
WA
98926
By✓�- T�%�1��
z Approving Authority
Project Prospectus
Title County Engineer
r3lzj/&zz
Date
uvi Form iau-i vi Page 1
Revised 01/2022 Previous Editions Obsolete
Agency
Project Title
Date
Kittitas County Public Works
7/15/2022
Type of Proposed Work
Project Type (Check all that Apply)
Roadway Width
Number of Lanes
❑ New Construction ❑ Path / Trail
❑ 3-R
32
2
❑ Reconstruction ❑ Pedestrian / Facilities
❑ 2-R
❑ Railroad ❑ Parking
❑ Other
❑✓ Bridge
Geometric Design Data
Description
Through Route
Crossroad
❑ Principal Arterial
❑ Principal Arterial
Federal❑Urban
❑ Minor Arterial
E] Urban
ElMinor Arterial
Functional
❑✓ Rural
❑ Collector
[:] Rural
❑ Collector
Classification
❑ NHS
❑✓ Major Collector
❑ NHS
❑ Major Collector
❑ Minor Collector
❑ Minor Collector
❑ Local Access
❑ Local Access
Terrain
❑✓ Flat [:]Roll ❑ Mountain
[:]Flat ❑ Roll ❑ Mountain
Posted Speed
50
Design Speed
50
Existing ADT
3851
Design Year ADT
Design Year
2022
Design Hourly Volume (DHV)
Performance of Work
Preliminary Engineering Will Be Performed By
Others
Agency
Consultant / County
75 %
25
Construction Will Be Performed By
Contract
Agency
Contractor
100 %
%
Environmental Classification
❑ Class I - Environmental Impact Statement (EIS)
❑✓ Class II - Categorically Excluded
(CE)
❑ Project Involves NEPA/SEPA Section 404
❑ Projects Requiring Documentation
Interagency Agreement
(Documented CE)
❑ Class III - Environmental Assessment (EA)
❑ Project Involves NEPA/SEPA Section 404
Interagency Agreements
Environmental Considerations
DOT Form 140-121 Page 2
Revised 0112022 Previous Editions Obsolete
Agency
Project Title
Date
Kittitas County Public Works
7/15/2022
Right of Way
�✓ No Right of Way Needed
❑ Right of Way Needed
All construction required by the
❑ No Relocation ❑ Relocation Required
contract can be accomplished
within the existing right of way.
Utilities
Railroad
❑ No utility work required
Z No railroad work required
❑✓ All utility work will be completed prior to the start
❑ All railroad work will be completed prior to the start of
of the construction contract
the construction contract
❑ All utility work will be completed in coordination
❑ All the railroad work will be completed in coordination
with the construction contract
with the construction contract
Description of Utility Relocation orAdjustments and Existing Major Structures Involved in the Project
PSE gas line to be relocated by utility owner prior to construction
Consolidated Communications will move their copper and fiber communication lines prior to construction.
Involvement
rISFAA,, ny airport located within 3.2 kilometers (2 miles) of the proposed project? ❑ Yes Z No
Remarks
No Airport within 2 miles
This project has been reviewed by the legislative body of the administration agency or agencies, or it's
designee, and is not inconsistent with the agency's comprehensive plan for community development.
Agency Kittitas County
Date By
Mayor/Chairperson
DOT Form 140-101 Page 3
Revised 01/2022 Previous Editions Obsolete